CARRICULAM VITAE
Proposed candidate Details.
Name Muhammad Taufiq Shahbaz
Position proposed Unit In charge (Plant Maintenance)
Passport No. GY5147392
Passport Exp Date 26-03-2023
Qualification B. Tech (Mechanical)
CONTECT +92-333*******…….adna8s@r.postjobfree.com
Permanent Address House no 1134 -T, block masoom shah road Multan
Years of Experience in Oil &Gas Environment/EPC Project 30 Years
Years of Relevant Experience in Maintenance, shutdown/ 25 years
Number of Major Shutdown/Turnaround handle in Oil& gas 20 No’s
Worked in similar Role in Turnaround 20 No’s
EXPERTISE……Plant Maintenance……Plant Re-Vamping…….process piping ….EPC Projects.
PLANTS………OIL REFINERY,,,PETRO CHEMICAL,,FERTILIZER,,POWER HOUSE,,OIL&GAS
Detail of Relevant Experience
From January 4th To April 4th 2021
Company, QATAR Engineering & Construction Company (QCON)
Clint..Doha Petroleum NGL3
Designation. Area coordinator
Furnes,Vessal,Sulphur Tank,Sulphur Pit.Air Receiver.Knock out Drums.Exchangers
Job Responsilities.
Pre-shutdown, shutdown-post shutdown Activities
Maintenance as per scoop of work
Ensure all maintenance activities as par Approved Method statement
Ensure all Activities safely and secure as per JSA
From October 2019 to May 2020
Company. Doha petroleum construction company (DOPET)
Client. Qapco. Qatar Petrochemical company QATAR
Designation. Execution in charge (vinyl) EDC. VCM. Chlorine.
Oxy Reactor. DC Reactor. Exchanger. Column. Vessels. Tanks. GRP lines. Electrolizer .piping
JOB RESPONSIBILITES.
Supervision, monitoring and coordinate of all shutdown activities which include maintenance, inspection and testing of Oil&Gas plant.
Evaluate field requirements. Follow shutdown plans and carry out shutdown activities in the area of responsibility.
Coordinate and liaising with the client for the shutdown preparation and activities.
Maintenance of all major static equipment oxy Reactor. DC Reactor. Pressure vessels .heat exchange. Tanks. Columns. Servicing and inspection.
Ensure that all maintenance /modifications /Fabrication /installation work are carried out according to approved engineering codes/standard.
Ensure all maintenance activities carried out safely, as per company's safety rules and regulations.
Final handover of shutdown activities and documents.
Participants J.S.A Meeting.
Preparing Method statement
Attend internal weekly meeting
Attend weekly client meetings
Resolve site issues.
Arrangements of TSF area.
Preparing tool and equipment list.
Calculate supervisor. Site Coordinator and technical staff
Area visit with sub-contractors and client for scaffolding /hydro jetting/critical jobs
Arrangements of critical lifting.
Participate PTW training.
Assign supervisors and Area coordinator
Follow safety procedures and 12 golden rules of Qapco.
From February 2019 To April 2019
Client. ADNOC LNG, oil & gas (Abu Dhabi (ADGAS.Dasisland)
Designation Area in charge (Night shift) DESCON engineering limited
JOB RESPONSIBILITIES:
Assign supervisor on Equipment’s as per work scope
Get the work permit from area Shift controller
Held a T.B.T before start any activity at site
Follow 10 No’s lifesaving rules of ADNOC
Spading -DE-spading with B.A
Give instructions to site team for scaffolding & tagging
Follow all instruction written on permit.
Open, clean, Repair (if any), inspection & box up. (254 work pack)
Get the work pack from Turnaround planning department
visit the assign Area and check Equipment and location
From November 2018 To February 2019
Designation Unit In charge (1Butene)
Client Adnoc Polymer Borouge 3 Abu Dhabi
Project Nature Annual Turnaround 2019 (DOOSAN Babcock engineering)
JOB RESPONSIBILITIES:
Get the work pack from planning DEP
Visit the assign Area and check Equipment and location.
Preparing Tagging and fixed at location.
Assign supervisor on different work scope, vessels, column, Heat exchanger, MV, CV, and PSV’s.
Get the work permit.
Held a T.B.T.
Follow 10 lifesaving rules of ADNOC
Blinding and open equipment
Arrange ventilation, Lights & material for internal scaffolding
open, clean, Repair (if any), inspection & box up
From December 2017 To April 2018
Designation Unit in charge plant maintenance (PE3 unit 23,26) (E2)
Project ADNOC polymer Borouge 2 chemical Ruwais Abu Dhabi
Project Nature Annual Turnaround 2018 (DESCON Engineering limited)
JOB RESPONSIBILITIES:
Maintenance of equipment such as columns. filter, Heat exchangers, Reactors
Vessels, piping Modification,
Tagging, joint integrity, blinding, open, clean, inspection, Box up, DE-blinding
From October 2017 To November 2017
Designation unit in charge Plant maintenance UREA AREA 9468
Project ADNOC Fertilizer (FERTIL) 2 Ruwais Abu Dhabi (IMDAD Engineering)
JOB RESPONSIBILITIES:
Maintenance of column, repair internal, Unloading, loading pall Rings
Reactor, removing of source, bolts Tensioning, internal cleaning and inspection
Stepper Removing and re installing Ferrules 5000, ferrules Teflon Rings, testing, inspection
Vessels internal cleaning, inspection
Heat exchanger Blinding, DE, Blinding, open, inspection, bundle pulling, hydro jetting, Eddy current, re-fixing bundle, Hydro testing.
From February 2017 to March 2017
Designation Unit in charge plant Maintenance FZ #11
Client Dolphin Energy onshore Raslaffan Doha QATAR (DESCON Engineering)
JOB RESPONSIBILITIES:
PTW daily collect permit from ITR
Distribute work to supervisor
Close monitoring of work sequence and progress
96 equipment of FZ#11, column, drum Heat Exchanger, Mixer, vessels, Fin fan cooler & Stack.
Daily meeting with client & Descon shutdown management
Provide resources to supervisor to boost work progress
Blinding, As open inspection, arrange blower &Air ejector, apply confined space permit,
Check L.E.L by operator, Entry, safely complete scope of work. Inspection, N.D.T, Box up
Singing of blind list by area operator, de-blinding, finely close the permit.
Participate daily tool box talk.
Daily meeting with Area planer about remaining work
Supervise all B.A jobs
Supervise all supervisors’ jobs
From August 2016 To December 2016
Designation piping incharge
Client ADNOC Ruwais Fertilizer Industries LTD. FERTIL. UAE (DOOSAN Babcock)
JOB RESPONSIBILITIES:
Supervise and provide technical guidance to tradesman in fabrication and onsite installation
Maintain of shop and site progress report, look ahead planning and scheduling
Manage material requisition or transfer slip, oversees layout, fabrication and assembly of Pipes and piping system components
Plan work schedule and determine Supervision Area B process line piping erection and installation of Utility piping
Review all drawings and specification for fabrication and installation program
Undertake Piping and associated materials control on site
Supervise lay down yard spool segregation.
Coordinate rigging procedures for erection
From February 2015 To May 2015
Designation Unit in charge (Area 4 Night Shift) OFFSHORE
Client ADNOC gas (ADGAS) Das island Abu Dhabi. Train 1 (Q.CON Engineering)
SCOPE OF WORK: Spading, DE-Spading, All Exchanger, Bundle pulling &inspection, Column, Vessel, Maintenance, and R&R Job LNG Treated Replacement and Maintenance.
JOB RESPONSIBILITIES:
Coordinate with client &TAPD regarding all issues, Daily Progress, Material shortage & required material specification update.
Weekly Progress Review meeting with Client.
Manage tool box safety talk on site.
Supervise all Supervisor jobs
Ensuring the material specification as per TAPD.
Manage and organize Hydro testing& pneumatic testing preparation and execution of said tests.
Generate extra claims for all Extra jobs
Ensure all jobs under supervision in liaison of applicable Quality standards
From November 2014 to January 2015
Designation Mechanical Superintendent (piping & Equipment) (DESCON Engineering)
Client Pakistan Refinery / National Refinery Annual turnaround
2014/2015(Pakistan)
Project Nature: All Piping works in shutdown Scope.
SCOPE OF WORK: CS & SS Piping Above/Underground, (20000 Día Inches) Installation/Replacement, X RAYS, Hydro testing
JOB RESPONSIBILITIES:
Coordinate with client & design team regarding all isometric issues, Daily Progress, Material shortage & required material specification update.
Ensure survey coordinates as per drawings.
Weekly Progress Review meeting with Client.
Manage tool box safety talk on site.
Supervise all Supervisor jobs
Ensuring the material specification as per isometrics.
Manage and organize Hydro testing& pneumatic testing preparation and execution of said tests.
Ensure all jobs under supervision in liaison of applicable Quality standards
From September 2012 to July 2014
Designation Mechanical Superintendent (piping) (E.K.L )
Client ADNOC Ruwais Sulphur Handling project
SCOPE OF WORK: CS & SS Piping Above/Underground, (256,000 Día Inches) Installation of Stacker Reclaimer, Ship Loader, Transfer Towers and Conveyors (10,000 MT)
JOB RESPONSIBILITIES:
Coordinate with client & design team regarding all isometric issues, Daily Progress, Material shortage & required material specification update.
Ensure survey coordinates as per drawings.
Weekly Progress Review meeting with Client.
Manage tool box safety talk on site.
Supervise all Supervisor jobs
Ensuring the material specification as per isometrics.
Manage and organize Hydro testing& pneumatic testing preparation and execution of said tests.
Generate extra claims for all modification jobs
Ensure all jobs under supervision in liaison of applicable Quality standards
From July 2009 to August 2012
Designation Piping Superintendent
Project BYCO oil Refinery Hubchoki Baluchistan (DESCON Engineering)
JOB RESPONSIBILITES:
To develop detail schedule based on client requirements.
Daily monitoring and feedback of progress, material, quality and safety work.
Coordination with client and sub-contractors for deliveries against specification and order
Supervise and provide technical guidance to tradesman in fabrication and onsite installation
Maintain of shop and site progress report, look ahead planning and scheduling
Manage material requisition or transfer slip, oversees layout, fabrication and assembly of Pipes and piping system components
Plan work schedule and determine• Supervision Area process line piping erection and installation of Utility piping
Review all drawings and specification for fabrication and installation program
Undertake Piping and associated materials control on site
Coordinate with rigging team for erection
Check material and site manpower requirements
Prepare test pack for site activities
Participate in HSE meetings on daily basis to reduce the risk of any LTI
From December 1989 To April 2009
Designation Sr-project Supervisor
Company OLAYAN DESCON Industrial
Company Jubail/Yanbu Saudi Arabia
Projects Workshop, Manufacturing& repair of vassal, column,
Heat Exchanger, piping& Hydro testing,
JOB RESPONSIBILITES
Prepared all materials, consumables and tools needed on approved drawings of the project and mobilization of equipment.
Review all isometric drawings before start all spool fabrication, and preparation of documents.
Planning and scheduling of ongoing project on my area of responsibility
Update the actual progress of the ongoing work base on schedule of the project.
Supervise the fabrication and installation of Fin fan condenser header for refinery in Jeddah.
Supervise for installation of pipes and supports for corrosion line project Saudi Aramco
Follow & Implement Sabic & Aramco safety rules during plant work.