Post Job Free

Resume

Sign in

Commissioning Engineer Manager

Location:
Pattaya, Chon Buri, Thailand
Posted:
June 16, 2021

Contact this candidate

Resume:

Curriculum Vitae

*

NAME: Malcolm Pogue

ADDRESS: ** ******* ******** ********** ********* TS14 8DU

Note : Presently Based In Thailand

TELEPHONE +66-625****** (mobile )

E MAIL ADDRESS adm5y9@r.postjobfree.com

DATE OF BIRTH: 8 January 1953

NATIONALITY: British

QUALIFICATIONS: City and Guilds of London Certificate Instrument and Control

CARREER SUMMARY: Completed apprenticeship in Instrument and Control and subsequently gained experience within Petrochemical, Oil and Gas (both On and Offshore), Topsides, Marine, Sub Sea, Power Generation and Nuclear Industries. Positions Attained :

Commissioning Technician, E&I Supervisor, Lead QA/QC Surveyor, Lead Completions & Commissioning Engineer / Manager & Hook Up / Commissioning Superintendent.

Experienced in Construction, Hook Up, Pre Commissioning, Commissioning, Completions & Certification, On & Offshore, Platform Topsides & FPSO Marine & Topsides( New and Refurb ) .

Experienced on all types of Systems, including Fire & Gas and DCSS Systems ( Emerson Delta V, Konsburg, Invensys, Honeywell, Yokagawa and Bailey Infi 90 ) ESD Systems, Power Generation, UPS Systems and Gas Compression Systems. I am familiar with both Computer based and hand written PTW systems as an Area Authority and a Performing Authority, Hazops and Simod procedures . Overseas experience gained in Saudi Arabia, Netherlands, Belgium, Norway, France, Pakistan, Singapore, Vietnam, Indonesia, Brazil, Nigeria, U.A.E., Qatar, China & Russia.

Curriculum Vitae

2

WORK HISTORY:

From : July 2019 to April 2020

Employer : Automation Solutions FZC, Sharjah .

Project : ADNOC Gas Processing Plant Abu Dhabi .

Position : Senior E&I Construction / Commissioning / Engineer Duties : Consultant and Supervision during the Installation and Commissioning activities by Local Contract Labour performing the following activities :

• Installation of cable trays and associated structural supports.

• Laying and termination of instruments and power cables.

• Installation of new Fire & Gas detectors.

• Relocation of of existing Fire & Gas detectors and demolition unused Fire & Gas detectors.

• Installation of new marshaling cabinets at IES-7, and modification of system and marshalling cabinet at IES-5 and IES-6.

• Modification of existing Yokogawa DCS and FGS system, Honeywell AMS

(Alarm Management System), and existing HSSD system (Tyco). From : May 2016 to June 2019

Employer : AHI. Carrier

Project : Yamal LNG Tiangin China / Sabetta / Russia Position : E&I Commissioning / Construction Specialist (HVAC) Duties : Overseeing the E&I Construction HVAC activities for 15 off LNG Modules being Constructed in Bomesc Yard China.

Follow on to Sabetta, Yamal LNG Site for Installation and Commissioning of HVAC systems .

Modules included : HTF Transfer Pumps, Nitrogen Production, Plant Air, Demineralised water, BOG Compressor, Fuel Gas, Gas Condensate, Electrical Switch Rooms & Central Control Room .

From : June 2015 to April 2016

Employer : Qatar Petroleum

Project : National Security Shield

Position : E&I HUC / Commissioning Superintendent

Duties : Oversee the Installation and Commissioning by Contractor of 7 Offshore Platforms E&I Installations, including Cummings Diesel Generator sets and associated MV / LV Switchgear, UPS, Navaids, Fiber Optic / Scada Systems and all associated Instrument and Electrical equipment to power and control the remote offshore Platforms and their Radar, Infra Red Camera and Satellite systems for the Security Shield of Qatar .

Curriculum Vitae

3

From : Aug 2013 to June 2015

Employer: Occidental Qatar

Project : ISND Field Development

Position : Construction / Hook Up / Commissioning Superintendent / PTW Area Authority.

Duties : Responsible for a multi discipline team of 50 plus multiple Nationalities, carrying out Construction / Hook Up, Upgrades and Commissioning Projects on Main PS1 Complex and over 45 Satellite Platforms Offshore Qatar . Work includes all Hook up and Completion work for new Well Completions, including Fabrication, Piping, welding, Electrical, Instrumentation and Testing work prior to handover to Operations.

Also responsible for the Installation and Commissioning of New Solar Gas Power Generator on Main PSI Complex and the Upgrade and testing to the Complex ESD/F&G System.

From : April 2012 to June 2013

Employer: Petrofac Malaysia

Project : Berantai FPSO (Onshore Singapore/Offshore Malaysia) Position : Deputy Commissioning Manager, Lead Commissioning / Completions Engineer .

Duties : Attend meetings with Client to agree Project Completion and Commissioning strategy . Be the focal point for Completions and Commissioning related matters of the various Disciplines. Write Completion and Commissioning Plan for the Project, define system limits and issue mark-up P&IDs and Single Line Diagrams (Project system/sub-system structure), Supervision of the various Engineering leads to ensure that Completions Database ( WINPCS )is adequately populated (i.e. populate check sheets versus Tag Numbers),Define with Procurement and Project the involvement of Completions in the Free Issued packages, define list of Commissioning deliverables (i.e. List of Operational Test Procedures), schedule the issue of the Commissioning deliverables, Manage the issue of Commissioning deliverable (i.e. supervision on Completions Engineers writing the OTPs). Attend PTW meetings to assess priorities and any clashes between different disciplines. From : April 2011 to March 2012

Employer: Premier Oil Vietnam Offshore B.V.

Project : Lewek Emas FPSO (Onshore Singapore/Offshore Vietnam) Position : Lead Commissioning / Completions Engineer, PTW Area Authority Duties : Overseeing Contractor Carrying out Pre Commissioning and Final Commissioning of Tanker Conversion to an FPSO, including Marine and Fire & Gas Systems . Verify all mechanical completion and pre-commissioning activities performed by the Contractor also responsible for ensuring quality of installation met with all aspects of the design specifications. Responsible for workforce within my Area as regards to signing on the PTW as the Area authority. Commission systems/subsystems in accordance with the commissioning procedures and commissioning and start-up schedule. Direct the work performed by subcontract Curriculum Vitae

4

labour. Assist Vendor servicemen with their commissioning activities. Enter all relevant documentation into Completions Data Base for handover and acceptance of systems to Operations Group.

From : Oct 10 to April 11

Employer: Heerema Marine Contractors Nederland BV

Project : SSCV Thialf Crane Barge Control and Power Upgrade Position : Lead Inst /Elect Engineer, PTW Area Authority Duties : Responsible for the E&I Installation, Inspection, Commissioning and Handover of following : 4x 4.3KW New Diesel Generator Alternator Sets and their associated Auxiliary Instrument and Control Systems including new HV and LV Switchboards, Transformers and Upgrade to existing Kongsberg D.P. Thrusters Control System.

From : Sept 09 to Oct 10

Employer: Satoil Indonesia

Project : Anoa Field Development Natuna Sea Indonesia Position : Lead Inst / DCSS Commissioning Engineer, PTW Issuing signature Authority .

Duties : Overseeing Sub Contractors for the timely hand over of Instuments and Emerson Delta V DCSS System to Owners Start up Team . Answering all Engineering queries related to my Systems Issues . Attend all PTW Pre Issuing meetings and planning .

Leading a team of local and expatriate Technicians during Commissioning Phase. Attending Simod, Hazops and Daily Production meetings. On Anoa FPSO and Anoa Gas Export Riser Platform.

From : Nov 08 to Sep 09

Employer : AGIP KCO PROJECT

Project : Kashagan Development

Position : Lead Inst/ Elect QA/QC Engineer Offshore Kazakhstan Duties : As below

From : May 06 to Oct 08

Employer: AGIP KCO PROJECT : Kashagan Development

Position : Lead Inst/ Elect QA/QC Engineer Onshore Dubai Duties : to Review and approve EC Project quality plans, mark up hold and witness points in accordance with project identified risks, Co-ordinate QC Inspection activities for EC supplied items, AGIPKCO direct procured items EC construction activities, Offshore Installation and Hook up activities, Review QC Inspection reports, ensure all corrective actions and non conformances are tracked and closed out and input into QA/QC Group reports.

Curriculum Vitae

5

From : June04 to March 06

Employer: Halliburton K B R Ltd

Project : Barracuda / Caratinga FPSO Projects Brazil Position : Lead Instrument Commissioning Completions Engineer Working as part of Halliburton’s dedicated project team, installing, pre commissioning, commissioning and dynamic testing of all topside and vessel systems, ready for handover to client (Petrobras).Duties also included writing and demonstration of system test procedures to clients certifying authority (ABS). From : Oct 03 to June 04

Employer : Mobil Exxon Nigeria

Project : Erha Development Offshore Nigeria

Position : Lead Instrument Commissioning / Completions Engineer Working as part of Mobil Exxon Project team, reporting directly to the Commissioning Manager, Overseeing the performance of the Major contractor, Vendors & Subcontractors during Pre Commissioning & commissioning Phases of EPIC contract, with regards to all relevant Control, Safety & Environmental systems, including Delta V DCSS System, through to final acceptance . Duties also included approval of Project Specifications, Drawings & Test Certification for lifetime record, final Performance Testing and Completions for Handover to Mobil Exxon Acceptance / Start Up Team.

FROM : Feb 03 toOct 03

EMPLOYER: Modec International ltd

PROJECT : FPSO Fluminense Singapore /Offshore Brazil POSITION : Instrument Commissioning Engineer

Commissioning of following on Fpso in Singapore shipyard / during voyage to location /, offshore Brazil and final start up for first oil / gas : Solar Gas Turbines, Silvertech Pcs / Fire & Gas / Esd System, Universal Gas Compressors and Smit Inert Gas Generation system . Duties included planning of work, compilation of documentation and attending daily progress meetings. FROM : Sept . 02 toFeb 03

EMPLOYER: Lasmo Oil & Gas Pakistan Ltd

PROJECT : Bhit LNG Gas Terminal

POSITION : Lead Instrument Field Engineer

Commissioning of following systems for new LNG Gas Plant : Rolls Royce Turbines, ABB Fire & Gas / ESD system, ABB distributed Control System and Wormald Wellhead / Flow Line / Telemetry Systems, using local Pakistani Sub Contractor Labour

Curriculum Vitae

6

FROM : MAY.01 to Sept . 02

EMPLOYER : TOTAL FINA ELF LTD

PROJECT : ALWYN B SYSTEMS UPGRADE

POSITION : Instrument COMMISSIONING ENGINEER ON / OFFSHORE Working in Tyco Systems Manchester factory,carrying out extensive testing of following Systems : I C S Trusted ESD/ Fire & Gas, and Fisher Rosemount Delta V Process Control System. Then offshore As part of the ASU Commissioning team, to test, commission and hand over to Operations a fully tested system with the minimum of disruption/down time to Production on the Alwyn B Facility. FROM : JAN.01 to MAY.01

EMPLOYER : DEVONPORT MANAGEMENT LTD

PROJECT : 9 DOCK REDEVELOPMENT

POSITION : INST/ ELECT QA/QC SURVEILLANCE ENGINEER PROJECT : SEDCO EXPRESS SEMI SUB DEEP WATER DRILLING RIG FROM : FEB.00 to Dec.00

EMPLOYER: TRANSOCEAN SEDCO FOREX (Brest Project Task Force) POSITION : INSTRUMENT COMMISSIONING SUPERVISOR

.

FROM: AUG. 98 TO DEC 99

EMPLOYER: SMEDVIG NORGE

PROJECT: WEST NAVION DRILLING SHIP (SANDNES, NORWAY) POSITION: SENIOR INSTRUMENT COMMISSIONING SUPERVISOR FROM: MARCH 99 TO JULY 99

FROM: SEPT 97 TO JULY 98

EMPLOYER: AKER MARITIME LTD.

PROJECT: PIERCE (F.P.S.U.) ON/OFFSHORE

POSITION: SENIOR INSTRUMENT COMMISSIONING SUPERVISOR FROM: FEB 96 TO SEPT 97

EMPLOYER: A.R.C.O. BRITISH LTD.

PROJECT: A.R.C.O WAVENEY PLATFORM

POSITION: INSTRUMENT AND ELECTRICAL CO-ODINATOR



Contact this candidate