KRISHANKANT SONI

Email: adm5w0@r.postjobfree.com

Phone: +91-798*******/942-***-****

C/O Shiv sadan, Behind Aditra Masjid, Near K.V. Teacher's Colony,

Port Okha-361350, Dist - Dwarka - Gujarat- India

MENTOR: PIPING & TANK

Offering over 17 + years in the OIL & GAS industry, seeking challenging assignments in OIL & GAS.

SUMMARY OF SKILLS

Extensively skilled, competent and result-driven professional, putting forth 17+ years of experience in Oil & Gas quarters with an exceptional depth understanding. Handled Project Management Operations, delivered strategic directions for improving efficiency and elevating the organisation. Adept at moving into new environments and extrapolate from the existing experience to quickly adapt to new ways fluently.

SKILL & EXPERTISE

● Fabrication & Erection ● Testing ● Monitoring ● Coordination ● Bill Verification. ● Material Reconciliation

Accomplishments

I have proven record of managing small to large green & brown fields projects with an effective supervising team of 360 to 670 workers. I have the ability to form a safe environment of our contractors and team. All jobs have done with in scheduled timeframe and budget.

Manage all aspects of the project requirements in order to ensure adequate contract deliverables for successfully completion of projects.

Assist Project Managers in establishing construction management objectives and

perform accordingly in order to meet project deliverables.

Initiate and maintains liaison with client contacts to facilitate Construction activities.

Consistently and successfully deploys solutions for key accounts as assigned.

Overseas Working Experience

SEEH AL Sariya : April 18 to May 2020

Construction Manager Piping (OXY FIELD)

Accountabilities

To plan and manage execution of multi disciplinar projects (in particular. flowlines and Wellhead facilities)including Front End Design,Detailed Design, construction and commissioning, in full accordance with Company's HSE,technical and quality requirements,and on schedule and within budget.

To facilitate and execute the flowlines and wellhead facilitie installation program.

Planning & scheduling of assigned yearly flowlines,includingdevelopment of yearly Baseline plan and KPI in accordance to the latest Drilling Rig in coordination with subsurface team.

Ensure that own actions and contractor actions are conducted in accordance with the company as HSE management system. Specific accountabilities are set out in the HSE Policy, Commitment and Accountabilities booklet.

Manage Annual Plans/expenditures related to the Budget and the workloads and execution of Flow line Projects, Integrity replacement,Hookups and Manifolds in liaison withclients such as Operations,Petroleum and Concept Engineers etc. to meet production targets.

Drive the HSE and Quality aspects during the Project execution and ensure the compliance during the life circle of the project delivery including the Introdution of Hydrocabon.

TETCO LTD: Feb 16 to Feb 18

Construction Manager Tank Maintenance PROJECT (PDOC)

Accountabilities

Accountable for Tank maintenance work of 82.1 mtr X 17.8 mtr 3 nos as per API 653 & 650 - Double deck flooting roof Crude Tanks.

Responsible for Tank cleaning, Tank inspection as per approved ITP, Tank bottom replacement based on Inspection reports, Mechanical roof seal installation, Cathodic Protection repair, Installation of Stopaq sealent, Ring beam repair, Dyke area preparation, Commissioning and handover.

Accountable for maintain liaison with consultant and contractor for getting approval on project design & execution.

Coordinate and conduct meeting to discuss project progress and project problem resolution, both internally and externally. Follow up on the actions detailed in the meeting.

Ensured technical support to consultants and project owners with recommendations regarding methods of maintaining schedules and construction specifications.

Responsible for establishing, promoting and maintaining a safe and hazard free working environment.

DOHA PETROLEUM CONSTRUCTION LTD : Nov 14 to Dec 15

Sr. Mechanical Engineer, acting C.M -Piping & Tank ( Q.P OFFSHORE FILED)

Accountabilities .

Accountable for Fabrication, Erection, Mechanical Clearance, Hydro test / Pneumatics & Flushing and final handover of A/G, U/G ISBL/OSBL 32634 " dia Piping and 36 Mtr X 16 Mtr - 01 no's, 20 Mtr X 12 Mtr- 01 no Tanks for Produced Treated Water & Crude Oil Distillation unit.

Coordinate for the fabrication of different piping system, installation and hydro testin (CS, LTCS, SS, Alloy Steel, Hdpe).

Preparation of Piping spool details and assembly drawings for shop fabrication and field erection.

To check the Bill of Material (Material Take Off) as per drawing for ensuring requirements are realistically quantified as per scope and budget and follow up the delivery of the project/construction materials.

Sound knowledge of international piping codes and standards like ASME, ASTM, API, MSS etc.

Preparation of field piping system test packages,including system limit on P&ID and piping Isometric.

Responsible for line checking after hydro test to complete the post punch list prior to sign-off the test packages before signing the completion of piping / mechanical and make sure that all punch list items are resolve for final handover.

Successfully completed 14 TIE INs (fabrication and installation of Tie ins ) SHUT DOWN JOBS of Total Energy for PWT & COD expansion OFFSHORE unit within scheduled Time.

Responsible for follow and adhere to the Management System Manual as per client safety standards.

AL HUSAM: NOV 11 to Aug 12 - ABU DHABI

Sr. Mechanical Engineer

Accountabilities

Fabricated & Erected 48 " Dia Pipeline.

Mechanical clearance and hydro testing of pipeline.

Planning to achieve target in planned schedule.

Participating in weekly meetings and discussing with clients about the Progress and the backlogs.

Coordination with procurement dept for purchasing of piping materials for Shop and field fabrication works.

Third party inspection at site or at vendor end.

Indian Working Experience

Trident India Ltd :Aug 12 to Nov 14

Deputy Manager - Piping

Accountabilities

Fabrication, Erection, Mechanical Clearance, Hydro test / Pneumatics & Flushing of ISBL/OSBL PIPING.

Supervised a work force of not less than 50 to 90 men composed of : 3 Engineer, 5 to 7 Foremen - piping / welding / equipment / electrical / civil / scaffolding and all kinds of trade skilled workers / labors as indirect & direct manpower required.

Prepared & follow - up the weekly advance manpower, materials availability, tools & equipment requirements for various field activities of my staff respective job assignment.

Responsible for counter check the orientation and alignment of respective equipments and pipe rack in accordance with Isometric / Piping Plan drawings prior to spool erection.

Assist Engineering Department in solving Piping Modification and Technical Problems in the Field.

Involved in budgeting, scheduling, develop Purchase Request, Purchase Order with respect to scope of work.

Project Schedule, control and Monitoring as per schedule.

Implementation of works as per the drawings & co-ordination with Engineering Department for preparation of as built drawings.

Responsible for carrying out Mechanical Clearance, Conducting Hydro and Pneumatic tests, fulfilling commissioning and Pre-Commissioning requirements for the project.

Reconciliation of materials.

SPML INFRA LTD - April 09 to Nov 11

Project Coordinator, Delhi Head office

Accountabilities

Ensured technical support to consultants and project owners with recommendations regarding methods of maintaining schedules and construction specifications.

Involved in Budgeting, scheduling, P.R, W.O with respect to scope of work.

Reviewed engineering plans for construction.

Managed payments through project progress meetings with contractors, engineers, project owners, and others.

Monitoring the daily work activities of Sub Contractor and updating Sub Contractor Progress Reports.

Carrying out final P&ID check of installed piping systems in the module.

Prepare different work procedures and coordination for the inspection of work with client.

Responsible for carrying out Mechanical Clearance, Conducting Hydro and Pneumatic tests, fulfilling commissioning and Pre-Commissioning requirements for the project.

Reconciliation of materials.

ESSAR Construction (I) ltd: May 04 - April 09

PROJECT ENGINEER – (PIPING & TANK)

Accountabilities

Worked for ESSAR OIL LTD. Intermediate Storage Tanks South & North PIT - Oil & Gas Refinery project.

Executed, hydro tested & system handing over Double & Single Deck Floating roof of High Speed Diesel, Naphtha Tank farms (62 Mtr X 20 Mtr - 06 no's, 50 Mtr X 20 Mtr- 05 no's, 44 Mtr X 20 Mtr- 04 no's, 30 Mtr X 20 Mtr- 05 no's ) Tanks for Phase I at PIT area.

Fabrication, Erection, Mechanical Clearance & Hydro test of 74568" Dia ISBL/OSBL PIPING

Responsible for daily planning to achieve target in planed schedule.

To ensure the yard is supplied with the correct material & drawing for fabrication & installation work to meet schedule requirements.

Monitor daily and weekly progress and productivity correctly and accurate

Closing out all raised Site Query and develop As-built drawings if required.

Closing out all Piping Preservation Punch List.

Successfully completed shut down job of Essar oil Ltd for Pig launching of Spool fabrication & erection, valve removal & installation as scheduled Timing.

Reconciliation of materials.

EDUCATIONAL CREDENTIALS

Academic

Diploma in Mechanical Engineering from Government Polytechnic - May 2005.

B.Tech in Mechanical Engineering from MB University - June 2012.

Non Academic

Post Graduate Diploma in Piping Design & Engineering from M.I.T - Feb 2010.

PERSONAL DETAILS SOFTWARE

DATE OF BIRTH : 17th August, 1981 M.S. PROJECT

NATIONALITY : Indian MICROSOFT OFFICE

RELIGION : Hindu AUTOCAD



Contact this candidate