GURUPADA MAITY
Engineer – Mechanical Component GE Power India Ltd.
adluf9@r.postjobfree.com +91-983******* linkedin.com/in/gurupada-maity-83190515/
SKILLS
Expert in manufacturing processes & material take-off
Expert in PFMEA risk & MOC analysis
Excelling in Boiler Pressure Parts detail engineering
Proficient in LEAN Six Sigma methodologies
Driving & evaluating KAIZEN projects for Cost Reduction
Driving ACTION WORKOUT for manufacturing process improvement
TOOLS
AutoCAD, iGEMS, Enovia PLM, SAP, Most 2D
ACHIEVEMENTS
Winner in 38th National CII KAIZEN competition
Runner up in 15th National CII Champions Trophy
EDUCATION
B.Tech (Mech), Rajasthan Vidyapeeth University, Udaipur, 2011
Diploma (Mech), A.P.C. Roy Polytechnic, Jadavpur, 2008
TRAININGS
LEAN Six Sigma Yellow Belt, GE, 2020
PERSONAL
Age: 36
Married
HIGHLIGHTS
Single point of contact for all Customer issues at execution stage
Implemented an automated Engg. & Manu. Design System at Durgapur Factory
Driving Re-engineering projects for oOEM design to increase boiler performance
Worked as Liaison Engineer in China for a CFB & a Supercritical boiler project
PFMEA/MOC/Lean Six Sigma Projects
Used various Lean Tools (PFMEA, Yamazumi Chart, SWCS, Kaizen) to reduce a total of 1527 hours at Element Shop to decrease the lead time by 20% and increase the profitability for the service market
Lead a LAWO to enhance the productivity of Element Shop by 5% from 87% to 92% to cater the service market
Saved Rs. 14.4 Lakhs for 3 units by utilizing received length of tube, reduced 2880 cuts of SS tube out of 3472 cuts to make coil of RH-01_Barh-I
Saved Rs. 12.2 Lakhs for 2 units by increasing bend radius for LTRH Banks of Patratu, reduced PFHT scope
Optimizing raw material & adjusting design parameters to reduce fabrication activities and reducing fabrication lead time
Mitigate revisions of SA 213 T23 tube requirements in some Back-pass circuits of Patratu Project, which is under WIP at supplier end with 400MT tube by keeping original cut length to avoid financial impact of Rs. 7 Cr.
Improve project margin by Rs.7.5 lakh for WBPDCL Bandel & Kolaghat Reheater coils, by changing material grade from SA 182 F22 to SA 217 WC9 after technical evaluation
Improve project margin by Rs. 8 lakhs for WBPDCL Kolaghat & Bandel RH coils by eliminating site welding attachments after assessed by customer at their end by keeping the same order value
WORK EXPERIENCE
Engineer – Mechanical Component Nov’15 - Present GE, Durgapur
Providing feedback in RFQ’s by calculating boiler weight & comparing with material handling capacity of shop floor & shipment facilities
Executing engineering by calculating pressure parts of boiler as per ASME & IBR design
Developing critical components like Spiral Panels, Elements including material optimization along with machine program (Bend Manifest for System Bender) and proven expertise in working with First Supercritical Boiler
Consulting the manufacturing process function for Material Take Off for all Tubular products
Process troubleshooting at shopfloor and provide engineering approval of extra Butt Joints
Dispositioning of internal NCR for multiple Pressure Parts manufacturing
Contributed in FGD Ti Outlet Duct by doing 3P and created the manufacturing process
Made nominal changes to the job to facilitate fabrication of most LTRH banks to run System Bender efficiently along with modified manifest for all the contracts.
Provided detailed work instructions, material replacement & welding profile details for multiple projects
Design Engineer Jul’08 - Oct’15 Alstom, Durgapur
Created ordering information of primary & secondary raw material for fabrication of boiler pressure parts
Spearheaded entire design & engineering activities for Boilers projects fleet
Analyzing all boiler attachments in scope as per Design Standard, Standard Drawing & contract specific input drawings from US & Europe to provide input for manufacturing drawings
Generated drawings of Wind Box arrangement & detailing, Tube bend data sheet preparation, isometric drawings of Tube, Spiral Wall drawings, arrangement & detailing of various openings (Observation Door, Acoustic Steam Leak Detector, Wall Blower)
Ensuring conformance to the quality specifications by applying defined quality procedures