Summary of Experience

A registered Engineer with the knowledge of the oil and gas industry, experienced in the areas of Process Engineering, offshore and onshore Engineering, industrial equipment maintenance, business consultancy studies, Safety and in the use of Process Engineering simulation tools to meet the desired goals and objectives of the oil and gas industry.

Soft skills:

Offshore and onshore Operations, Commissioning/Pre-commissioning, Project Inspections, QHSE, HYSYS/Unisim, Flarenet, Pipesim, Equipment Sizing, NGL Recovery and Fractionation, Refinery Operations, A drive for continuous improvement, Effective team Player and Ability to work in a multicultural environment.

Education

University of Port-Harcourt

Masters(M.Eng) in Petroleum & Gas Engineering

2012 - 2014

Rivers State University of Science and Technology

Bachelors of Technology(B.Tech) in Chemical/Petrochemical Engineering

2001 - 2006

Work Experiences

Technical Integrated Global Services Limited, Lagos Dec. 2018 – Date

Position: Process/QHSE Engineer Supervisor(Process Engineering, Fire protection systems, Project Cost Estimating, Equipment Maintenance, Bids/Tender and Business development)

Responsibilities: I am responsible for all the activities listed below which includes the following;

Accountable for establishing QHSE corporate performance metrics and Compliance Management

Created reports; incidents investigations, risk assessment and safety presentations

Prepared yearly department budgets and assisted in the management of company’s yearly budgets

Ensured safety inductions are carried out for new hires.

Developed measures to assure personnel safety and ensured Company’s HSE policies are strictly adhered to and followed and monitored the installations of safety equipment in office complex

Monitored the issue of Permit to work, journey management plan, Inspected sites, Conducted toolbox meetings, job hazard analysis and developed updated risk assessment register

Follow-up and supervision of Firefighting & HSE systems upgrade contractors

Follow-up of Quality Control Audit

Ensures effective co-ordination between technical safety group and other disciplines participating in a project

Responsible for interface with other organizational units and implementation of quality standard

Fire protection system design (using water, foam, dry chemicals and inert gas) for hydrocarbon facilities

Reviewed PIPENET modeling/hydraulic calculation of fire water networks and deluge systems, Fire & Gas detection systems and F&G detectors mapping.

Prepared Safety audit inspections competency report, developed fire prevention awareness presentations and ensured periodic servicing of safety equipment

Sound working knowledge of relevant industry codes and Conversant with appropriate technical software

Understanding the SoW and Preparation of deliverables list, software needs, and clarification requests

Identified competence gaps and recommendation of potential specialist assistance/support

Participated in company’s CTR review to fit the project required budget

Regular offshore and onshore trip to ensure industrial machinery and equipment runs smoothly and reliably

Reviewed company’s logistics, quality assurance and quality control plans

Verified to ensure that all tools and equipment are adequate and safe for use

Supervised engineering and technical staff on equipment maintenance task

Participate in Preparations of tenders and pre-qualifications by proper distribution, evaluation, compilation and organization of all information in format requested in the RFP and according to approved standards

Ensured preparation of pre-qualification bids with standard are in line with company information

Assisted the Operations Manager to coordinate the Company’s activities in the Oil and Gas Industry, especially with: NAPIMS, DPR, NCDMB, NIPEX, NNPC etc.

Knowledgeable and familiar with proposals preparation and/or project management with the knowledge of the Local Content Laws

Position: Process Engineer( Oct2014 - Nov 2018)

(Agbami Gas Monetization Project, Process Safety Information(PSI), Facility Information(FI), Flare/Vent & Compressor Optimization Project on Agbami FPSO)

Responsibilities: I am responsible for all the activities listed below which includes the following;

Prepared reports - Basis of Design, Process Description, Process Simulation reports, Calculation reports, Operating and Control Philosophy, etc.

Carried out Steady State Simulation and Updated Flare and vent system’s capacity lists using operating conditions from Agbami FPSO

Reviewed Project output (steady and dynamic state simulation, blowdown study, cooling water and sea water hydraulic calculations, utility balance and reviewed sand corrosion calculation comment and response

Updated and Managed information database for outstanding management of change(MOC)

Worked as a team to deliver all process modeling and simulations, HAZOP and carried out design reviews of production system optimization and provided process engineering support to Agbami operating asset.

Prepared Site Visit checklist for offshore and onshore projects, developed Site sketches, site visit report, on-site sketches to As-build Drawings and Prepared API I4C Compliance Report.

Verified separator, compressor, pump, PSV, PCV and Flare KO drum sizing calculations using in-house software, Checked technical quality of calculations, HYSYS simulation software and other Process deliverables

Provided process engineering expertise in the review and optimization of existing production facilities.

Verified vendors’ design data by comparing design datasheet with CES, international codes and standards (API, ASME, etc.), as built documents, 3D Models, etc.

Visited offshore hydrocarbon processing facilities for as built verification.

Reviewed plant modifications, checked data design basis for new projects and reviewed process flow diagrams (PFDs), P&IDs, datasheets, 3Dmodels etc.

Verified Vendor’s design data by calculating it against Chevron’s Engineering Standard (CES), ANSI etc. and submitted variance for management action.

Developed/modified BFDs, UFDs, PFDs, PSFDs, P&IDs in line with project Scope of work.

Prepared departmental Master Deliverable Register (MDR).

Worked as a team on Gap Assessment and closure on Agbami FPSO(TOPSIDE&HULL).

Updated and Managed information database for outstanding MOCs, Process Safety information, Facility information (PSI & FI) and Migrated Resource interface (MRI).

Carried out Tie-in point evaluation for various utilities/flare system, new gas compression train and export gas line to gas export riser end termination.

Evaluated gas metering technologies in line with API, MPMS and Chevron Engineering Standards for gas custody transfer and Participated in their Process design data verification

Worked as a team on the evaluations and installations of Gas Metering Units.

Developed a comparison report of different Gas metering devices(DP Orifice, Turbine Radial Vane, Coriolis& Ultrasonic multipath).

Generated Piping Isometric drawings using Aveva E3D from 3D Models and point cloud data.

Carried out Steady State Simulation and Updated Flare and vent system’s Capacity list, Safety Instrumentation Systems (SIS) Using Operating Conditions from the Agbami FPSO.

Prepared reports - Basis of Design, Process Description, Process Simulation reports, Calculation reports, Operating and Control Philosophy, etc.

Interpreted process engineering flow schemes, process drawings and carried out Flare and vent networks, Flare header, flare boom report review

Used Intelligent Pressure relief systems Management (IPRSM) for Pressure relief systems, calculation sheets updates and reports

Reviewed Liquid mass flow calculation sheets/reports and Blowdown/relief system design and selection analysis.

Designed, audited, and documented both new and existing pressure relief system

Work Experiences

Pro-Ebehi Integrated Services, Port-Harcourt Nov.2010 – Sept.2014

Position: Process/Project Engineer(Chemical Injection Skid Installation & Maintenance on Oil and Gas flow Stations and Fields)

Responsibilities: I am responsible for all the activities listed below which includes the following;

Prepared work scope and deliverables for commissioning of projects.

Worked as a team for the Installations of semi- automatic chemical injection systems at flow stations and fields

Supervised all Maintenance activities on gas flow lines, instrument panel, pressure switches, and installed de-mulsifier, gas dryer and biocide pumps.

Reviewed all Chemical Supplier Vendors List along with their corresponding MSDS.

Obtained and validated PTW daily for commissioning and start-up of large and small process plants

Ensured the routine maintenance on chemical injection pumps.

Supervised the Laying of cable trays to accommodate instrument cable and injection line

Created and carried out test procedures and investigated problems to ensure faults are identified and fixed

Prepared project reports and documentation, provided technical support and ensured safe working conditions

Ensured at site, the management of commissioning and start up activities, coordinated the activities carried out by Client/ Contractors, Suppliers, and third parties, availing with the assistance of Construction Manager

Supervised the preparation of the Commissioning, start up and handing over procedures

Prepared design calculation report, coordinated site investigation for equipment installations, commissioning and start-up of electrical systems at the client’s sites

Worked in a team for the preparations of project execution plans and subcontracts requirements

Ensured the installations/operations of Skids are in line with the operations guide line of the flow station, gas stations and other assets in a safe and efficient manner in compliance with stipulated guidelines.

Collaborated with the maintenance team on assigned tasks and activities

Worked as a team on the injection of chemicals through hydrocarbon production lines

Monitored the adequate maintenance of all offshore and onshore equipment.

Performed daily check and carried out minor maintenance based on the check list.

Work Experiences

Sputech Nigeria Limited, Port-Harcourt Nov.2008–Oct. 2010

Position: Supervisor(Logistics &Tank Farm Operations)

Responsibilities: I am responsible for all the activities listed below which includes the following;

Monitored truck Maintenance/Loading and Offloading of products.

Responsible for the safety of the truck and its cargo.

Truck Logistics(Prepared Trucks for dispatch assignment).

Responsible for product delivery and bulk Supply to customers

Getting POD (point of delivery) signatures and perhaps taking payment or orders

Procured truck parts.

Work Experiences

Madonna Comprehensive College Makurdi Feb.2007–Jan.2008

Position: Science Teacher(National Youth Service Corp((N.Y.S.C)

Responsibilities: I am responsible for all the activities listed below which includes the following;

Served as a Mathematics, Chemistry, Physic and Integrated Science tutor.

Conducted examinations, marked scripts and entered the scores in report sheets.

Work Experiences

Weam & Company Nigeria Limited Port-Harcourt Jun.2005–Jan.2006

Position: Process Engineering Student’s Internship(Simulations and Software Service)

Responsibilities: I am responsible for all the activities listed below which includes the following;

Prepared site visit checklist for offshore and onshore projects, Developed Site sketches and site visit report, Developed on-site sketches to As-build Drawings, Prepared API compliance report.

Prepared valve list, Line list & Tie-in list and carried out FEED verification activities

Oil and Gas Process Modelling Using ASPEN HYSYS

Process CADing and sizing calculations

Preparation of Process philosophies, reports and other documentations

Verification of design data, consistency checks and preparation of technical queries (TQs)

Prepared and updated utilities and equipment datasheets, Simulated flare systems using ASPEN FLARENET.

Verified separator, compressor, pump, PSV, PCV and Flare KO drum sizing calculations using in-house software, checked technical quality of calculations, software simulations and other Process deliverables.

Analyzed Production tests and record as well as inflow performance using PIPESIM software

Worked in a team on Engineering consultancy studies and assisted new trainees on the use of HYSYS, FLARENET and PIPESIM simulators, SCADA and OLGA.

Analyzed and Carried out Plant Processing, Amine Sweetening Unit Dehydration Unit, Crude Oil Stabilization Unit, Gas Compressor Operation With the aid of simulations tools

Work Experiences

Boskel Nigeria Limited Port-Harcourt Jan.2003–April.2003

Position: Process Engineering Student’s Internship(Thermal/Process Engineering/Environmental Management)

Assisted in the daily sorting, sampling and tagging of liquid, chemical, and solid wastes.

Assisted in the loading of wastes into the incinerator.

Assisted in the installations of gas flare stalk (horizontal and vertical).

Health, Safety and Environmental Management

Hydrocarbon Process Safety

Fire protection and Emergency Response

Waste water Treatment

Incinerator operations

Training/Courses & Certifications

COREN Certified

ISO 9001:2015 Certified

OSHA Safety certified

OPITO BOSIET/SAFETY

OSP(Offshore Safety Permit)

Natural Gas Processing & Conditioning ((IFP school Paris& University Of Port-Harcourt)

Process Engineering simulation Training1&2 (Nigeria & South Korea)

Natural Gas Liquid Recovery and Fractionation

AVEVA PDMS E3D 2.1 Chevron/ARA Engineering (South Korea) Lagos

Flare & Relief systems Chevron Lagos