MUTHUKUMAR M

ENGINEER– * + Years’ Design / Project experience in the field of Thermal Power Plant Project and Industrial Water engineering

Mobile No.:+917*********

: +60-169****** E-mail: adjdym@r.postjobfree.com

CAREER OBJECTIVE:

To work in a challenging and creative environment to realize my potential and effectively contribute towards the goals of the organization as a team player.

PROFESSIONAL EXPERIENCE: (8+ Years)

CURRENT EMPLOYERS:

MINCONSULT SDN BHD, MALAYSIA (JAN, 2019 to PRESENT)

ENGINEERING SPECIALIST

Payra 1320MW Thermal Power Plant Projects (Phase-II)

1.Responsible for Review and approval of Balance of Plant (BOP) Basic design documents, P&ID and Detail design drawings (Such as Raw water intake system, Raw water Pre-treatment system, Water Treatment system, Coal Handling system, Ash handling system, Cooling Tower and Cooling water system, Firefighting and detecting system, Heat and Ventilation system and Compressed Air system).

2.Responsible for Co-ordination of Main plant system basic design documents, Piping and Instrument drawings and Detail design drawings approval (Such as Boiler and Steam turbine auxiliary system).

3.Responsible for Co-ordination of inter departments like Civil, Electrical and C&I design documents approval and provide the input details required to review interfacing documents.

4.Responsible for interface engineering as per the Contract Scope and Terminal Points.

5.Responsible for Preparation of Project status report

RUPSHA 800MW Combined Cycle Power Plant project

Natural Gas Pipeline from Central Gas Station to RUPSHA RMS.

1.Responsible for Review and approval of Natural gas pipeline Documents, drawings and Calculation from EPC.

2.As-built drawings approval

3.Responsible for Document co-ordination between inter departments like Civil and Electrical departments.

4.Involved in updating the Master document list.

Combined Cycle Plant area

1.Involved in Pre EPC stage activities like Technical tender Clarification and Evaluation activities.

2.Review the tender documents submitted by different bidders.

3.Responsible for Review and approval of Main plant and Balance of Plant (BOP) Basic design documents, P&ID and Detail design drawings (Such as Mechanical System (GT, ST, HRSG, HSD Oil system, ACC, Fuel Gas system, RMS, FFC and CCW), Hydraulic system, Chemical System (Raw Water Treatment, Reverse osmosis system, DM Water Treatment, Waste Water Treatment, and Zero Liquid discharge plant), Firefighting Detection and Protection system (FDPS), Heat Ventilation and Air conditioning system (HVAC)).

4.Responsible for Co-ordination of Main plant system basic design documents, Piping and Instrument drawings and Detail design drawings approval (Such as Boiler and Steam turbine auxiliary system).

5.Responsible for interface engineering as per the Contract Scope and Terminal Points.

Kedah combined cycle power plant 1200 MW - Malaysia

1.Involved in Preparation of Preliminary Plant general layout and finalization.

2.Involved in Preparation of Tender Document (Only technical Portion) and Tender drawings Preparation.

2 x 660MW Payra Coal based power plant Project in Bangladesh (Phase – I)

1.Responsible for Review and approval of Balance of Plant (BOP) Basic design documents, P&ID and Detail design drawings (Such as Raw water intake system, Raw water Pre-treatment system, Water Treatment system, Coal Handling system, Ash handling system, Cooling Tower and Cooling water system, Firefighting and detecting system, Heat and Ventilation system and Compressed Air system).

2.Responsible for Co-ordination of Main plant system basic design documents, Piping and Instrument drawings and Detail design drawings approval (Such as Boiler and Steam turbine auxiliary system).

3.Responsible for Co-ordination of inter departments like Civil, Electrical and C&I design documents approval and provide the input details required to review interfacing documents.

4.Responsible for interface engineering as per the Contract Scope and Terminal Points.

5.Responsible for Preparation of Project status report.

Sirajganj-3 225MW Combined Cycle Power Plant Project in Bangladesh

1.Responsible for Review and approval of Mechanical design documents, Drawings and Design calculation from EPC

2.Involved in Non plant Buildings design drawings (such as Fire station and 10-storied dormitory building) approval activities.

3.Responsible for Review and approval of 10- Storied Dormitory building Plumbing, Firefighting drawings from EPC.

4.Responsible for Document co-ordination (i.e., Structural, Architectural and Fire alarm drawings) between inter departments like Civil, C&I and Electrical departments.

5.Documents updating server.

6.Involved in review and approval of new scheme of Cooling Tower blowdown water treatment system design drawings. Still detail design documents are yet to be received on this case.

M/s MEENAKSHI ENERGY LIMITED, (INDIA POWER), KOLKATTA. (MARCH 2017 to December 2018)

2 x 350 MW Coastal Thermal Power plant, Thamminapattinam, Andrapradesh.

ROLES:

1.Engineering co-ordination.

2.Preparation of Boiler & BOP (WTP, AHP, CT, Electro chlorination) package specification.

3.Preparation of capacity calculation for FDPS, AHP, CHP, CT, and Water balance calculation for WTP package.

4.Preparation of flow diagram & Scheme for FDPS, AHP, CHP, WTP and FDPS packages.

5.Preparation of P&ID (Piping & Instrument Diagram).

6.Review /approval of vendor drawings (BOILER, BOP (CT, AHP, WTP, CHP, FDPS)).

7.Interface engineering & project management control.

8.QA/QC and Expedition works.

9.Co- ordinate with suppliers.

10.Attending technical meeting with customer and suppliers whenever required.

PREVIOUS EMPLOYERS:

M/s TRACTABEL CONSULTING ENGINEERS PRIVATE LIMITED, CHENNAI. JUNE 2014 to SEPTEMBER 2016.

1 x 800 MW Coal based Super Critical Thermal Power plant, North Chennai Thermal Power Plant, Ennore.

ROLES:

1.Preparation of Design basis report.

2.Preparation of Boiler & BOP (AHP, WTP, CT, FDPS and CHP) package specification floating enquires to various suppliers.

3.Preparation of layouts, process flow diagram and capacity calculation for Boiler & BOP (CHP, WTP, CT, FDPS and AHP) package.

4.Review/Evaluation of the Technical offers submitted by the bidders.

5.Involved in Pre bid meeting and Post bid meeting for finalization of vendor.

2 x 350 MW Coastal Thermal Power plant, Meenakshi Energy India Ltd., Thamminapattinam, Nellore.

ROLES:

1.Engineering co-ordination.

2.Preparation of Boiler & BOP package specification.

3.Preparation of capacity calculation for AHP, CHP, CT, and Water balance calculation for WTP package and Hydraulic calculation for FDPS package.

4.Preparation of flow diagram & Scheme for AHP, CHP, WTP and FDPS packages

5.Preparation of P&ID (Piping & Instrument Diagram).

6.Review /approval of vendor drawings (BOILER, BOP (CT, AHP, WTP, CHP, FDPS)).

7.Interface engineering & project management control.

8.QA/QC and Expedition works.

9.Co- ordinate with suppliers from the position of client consultant.

10.Attending technical meeting with customer and suppliers whenever required

M/s CETHAR LIMITED, Tiruchirappalli, Tamilnadu JUNE 2011 to MARCH 2014.

2 x 350 MW PC FIRED BOILER, Ind Barath Energy(Utkal)Ltd., Orissa

1.Involved in Site Fabrication and Inspection activities (Boiler and ESP Structure materials, ESP Hoppers and Casings)

2.Involved in Boiler area Pressure Parts and piping (Critical and Integral Piping) Erection and Construction activities

3.Involved in Ducting (Air and Gas) Erection and alignment

4.Involved in Burner Erection and alignment activities

5.Involved in Site Seals and attachments closing

6.Involved in Insulation and Refractory construction activities

EDUCATIONAL QUALIFICATION

Qualifications

College/Board

Year of Passing

% marks

BE, Mechanical

Government College Of Engineering, Salem-11.

2011

80

H.S.C

Government Boys Higher Secondary School, Pattukkottai.

2007

83.5

S.S.L.C

Government Boys Higher Secondary School, Pattukkottai.

2005

86.4

SOFTWARE KNOWLEDGE

- AUTOCAD

- GT PRO

- ST PRO

- PEACE

- MS OFFICE

PERSONAL DETAILS

Name : M. Muthu Kumar

Father’s Name : C. Mohan

Nationality : Indian

Date of Birth : 12-07-1990.

Languages Known : Tamil, English (Read and Write)

Hindi (speak only).

Permanent address : 282, Marriyamman kovil [st],

Kottagudi,

Panna vayal [post], Pattukkottai [tk],

Thanjavur [dt].pin:614602,

Tamilnadu

PASSPORT DETAILS

Passport number : M0051055.

Date of expiry : 09/07/2024.

Place of issue : Trichy.

DECLARATION

I hereby declare that the above information is true up to the best of my knowledge and belief. I undertake to abide by the conditions of employment specified by the recruiters and to uphold the reputation of the institution.

PLACE: CHENNAI YOURS TRULY,

DATE: 02.01.2021

(MUTHUKUMAR M)



Contact this candidate