Over ** years’ Experience on Large Projects within Energy sector in the field of Pre-Commissioning, Commissioning, Operation and Quality in Gas Processing with a proven track record in the execution of complex industrial equipment’s. I’ve gained vast experience developing and motivating multi-disciplined workforces. Managed numerous high profiles Commissioning Projects through the full lifecycle. Passionate of new technologies. Working purely through “Safety First” actions in mind, enhancing key Project objectives to the highest international standards for Safety, Quality, Health, Security and the Environment (HSSE).

CAREER ACHIEVEMENTS

• Leading activities in Pre-Commissioning, and Commissioning of Systems up to Hand over (Operations Start-up) in Buildings Project, Gas Processing (LNG), Oilfield (onshore/ offshore), Utilities and Process Trains in greenfield/ brownfield Projects.

• Successfully delivered a variety of key projects by driving smooth flow of supply chain processes and complete alignment across projects, ensuring conformance with technical, quality, and contractual requirements, company policies, budget limitations and meeting Commissioning Facility objectives.

• Supervision of System Completion activities (onshore/ offshore) in accordance with schedule imperatives,

• Development of Commissioning Procedures, Work Method Statement and Operational Test Procedures.

• Development of P&ID drawings systemization limits markups to facilitate commissioning execution.

• Execution of Static & Dynamic Commissioning tasks. Assistance in resolutions of issues to ensure systems completion.

• Equipment installation, configuring and testing equipment software (HMI) prior to commissioning.

• Development of relevant methods and procedures to promote safety awareness and best practices onsite by using strong communication tool in addition to safety bulletins, to provide site personnel with up-to-date key technical information.

• Successfully provided day-to-day support for Projects by managing complex interfaces between key internal/ external stakeholders through weekly/monthly/quarterly progress reports and meetings enhancing project efficiency.

• Punch List tracking, Field preparation prior execution, planning review for early execution and man-hours impact estimates.

• Acting as advisor during activities from Mechanical Completion (MC) to Ready for Startup (RFSU) for MAP Turnover.

• Co-ordinate Systems Completion acceptance milestone processes,

• Construction support, Sub-contractors and Vendors interface for Packages Equipment to ensure all the different teams are fully conversant with Project strategy.

• 3D Model review for Construction and Commissioning/ Operation/ Maintenance to anticipate clashing or access issues.

• Toolbox Talk, Safety awareness during field walkdown, Risk Assessment and JSA, Readiness, Kick-off and Closeout meetings for critical activities.

• Intensive site walks down for Punch categorization, issuing and Close out.

• System Completion Database on McPlus (TCO Chevron), ICAPS (TOTAL), WinPcs, QEDI/ GoCompletion (ExxonMobil), TOMAS (RasGas, ExxonMobil, JGC), SmartPlan (Iter Organization).

PROJECTS TYPE

Nuclear/ Onshore/ Offshore/ LNG Plant/ Sour Gas/ Train/ Utilities/ Process/ Offsite/ Oilfield/ Brownfield/ Greenfield/ FPU/ FPSO/ Engineering Procurement Construction Contracts (EPC/ EPCC/ PC). TRAININGS

Risk/ Hazard Assessment (Chevron Kazakhstan, ExxonMobil Dubai/Iraq, RasGas Qatar, Total LNG, Shell Nigeria LNG) HSSE Induction (Chevron Kazakhstan, ExxonMobil Dubai/Iraq, RasGas Qatar, Total LNG, Shell Nigeria LNG) Gas-in Awareness (ExxonMobil, RasGas Qatar, Total LNG, Shell Nigeria LNG) Permit to Work (ExxonMobil, RasGas Qatar, Total LNG, Shell Nigeria LNG) Work at Height (ExxonMobil, RasGas Qatar, Total LNG, Shell Nigeria LNG) Confined Space (ExxonMobil, RasGas Qatar, Total LNG, Shell Nigeria LNG) Chemical Use (RasGas Qatar, Total LNG, Shell Nigeria LNG) SIMOPS (RasGas Qatar, Total LNG)

C18-510 Electrical safety (RasGas Qatar, Total LNG, Shell Nigeria LNG) TapRoot Incident Investigation & Root Cause Analysis Course (RasGas, Qatar) BOSIET/ HUET (Offshore Sea Survival, Fire Fighting) – OPITO Course 5700, Cert No: 14295700230915002839 SENIOR COMMISSIONING ENGINEER

CAREER SUMMARY

Oct-2020

Present

Aug-2019

July-2020

Mechanical Project Engineer

ITER Saint Organization Paul Lez Durance, France

ITER is an international, large-scale scientific collaboration intended to prove the viability of fusion as an energy source, and to collect the data necessary for the design and subsequent operation of the first electricity-producing fusion power plant. To achieve this goal, seven countries (China, European Union, India, Japan, South Korea, Russia and the United States), have joined forces to build the ITER Tokamak: the world’s largest Fusion Device.

• Responsible for achieving Mechanical completion activities on the ITER site.

• Coordinate Construction Workpacks (CWP) and Installation Workpacks (IWP).

• Handover/ Turnover phase to Commissioning group.

• Endeavor to ensure that works completion activities are carried out successfully and in a timely manner by all stakeholders (Domestic Agencies [DAs], Contractors and Construction Managers.

• Collaborating and influencing construction stakeholders in the preparation of the Mechanical Completion Dossiers and the Mechanical Completion Certificate that formally marks the end of construction work and the start of the system commissioning and operation phase.

• Participation in Ready for Commissioning Meetings, verify the Ready for Commissioning Certificate

(RFCC) with all appendices and signs on.

• Attendance in surveillance walkdown and actions required by the surveillance plan/ guides to judge the conformity of the test.

• Follow up on actions raised in field and in meetings with all stakeholders.

• Preservation support with Commissioning and Operation teams.

• Writing of progress reports, workshop presentation to support Commissioning process with Contractors. Senior Systems Completion Engineer

Tengizchevroil FGP (Future Growth Company, Project) TCO// Wellhead Chevron join Pressure venture Management Project (WPMP) 3rd Tengiz, Generation Kazakhstan Injection Plant (3GI) Injection Project Major expansion of TCO’s oil production capacity, FGP project features three new main ISBL process facilities: Pressure Boost Facility (PBF), 3rd Generation Plant (3GP) and 3rd Generation Injection plant

(3GI)• . Leading Pre-Commissioning and Commissioning activities on subsystems covered on 3GI Utilities and Trains 1&2 Process Gas Injection.

• Preparation of Commissioning strategy for Utilities, Reception, Trains 1&2 and Injection to Wells.

• Assistance to Construction Hook up for pipe racks activities, interconnecting lines, and Construction Work Packs (CWP) development.

• Development of Commissioning Plans, Procedures and Work Method statement for Utilities and Process.

• P&ID’s mark-up development to support test execution (LO Flushing, Cooling Water flushing, Dynamic test, system run-in, LP/HP leak testing).

• Tracking of 120 days look ahead program and confirm alignment with Systems completions schedule.

• Attendance piping borescope inspection with Quality and Piping discipline lead.

• Stewarding resource to complete all aspects of site execution (manpower, isolations, timing).

• Review and approval changes to systemized drawings (P&ID, PFD, UFD, SLD, Block diagrams).

• Review of system boundaries limit to ensure efficient Pre-Commissioning and Commissioning.

• Review of check sheets allocation in database and report for correction/ modification.

• Contractor and Vendors support for Pre-Commissioning and Commissioning execution.

• Monitoring status of progress of A and B Check sheets.

• Review and categorization of punch list items during MC and RFSU walkdown.

• Management of the selection, procurement and management of temporary equipment, spares, consumables and first fills.

• Site walkdowns attendance and punch items raising and closing out.

• Collaboration with Engineering, Fabrication, Construction and Operations teams.

• System completion execution from Mechanical Completion (MC) up to Ready for Start-up (RFSU).

• Monitoring McPlus Database review for progress.

• Steward achievement of RFSU and RFO for all assigned subsystems.

• Preparation of stewardship program for handover to Operations team. Resume: Mob: +33 Bernard 6

Wood UAE (Dubai)Group/ / Iraq Shell (Project, Basra) Basrah Gas Company Basrah Gas Company is an incorporated Joint Venture between Iraq’s South Gas Company holding 51% of its shares, Shell 44% and Mitsubishi Corporation 5%. The Joint Venture captures associated gas currently • Leading being Commissioning flared from three support oil fields to Shell in southern CSU team Iraq on – various Rumaila, BGC West Projects Qurna in Iraq. 1 and Zubair.

• Main Wood commissioning interface for commissioning preparation

• Assist Construction and Completion teams for Workpacks development in Dubai offices (UAE).

• Assist Co-ordination and execution of the commissioning activities.

• Assist Co-ordination liaison for all interfaces at site (Iraq) with integrated groups to ensure the project requirements and performance standards are achieved, maintaining schedule and cost targets.

• 3D Model review on Navisworks for field engineering support.

• Reviews the project technical documentation and the contractual requirements.

• Review Project System Completion Plan.

• Development of systemization Process/Utilities P&ID’s systems and sub-systems boundaries mark- up,

• Prioritization of commissioning tasks aligned with start-up plan.

• Tracking proper check sheets (ITR) population in GoCompletion (Qedi database). Commissioning Lead

Wood Exxon Group/ Mobil - Houston, ExxonMobil USA Project, West Qurna 1, UAE (Dubai)/ Iraq (Basra) ExxonMobil Iraq Limited (EMIL), an affiliate of Exxon Mobil Corporation and the South Oil Company of the Iraq Ministry of Oil agreed to rehabilitate and redevelop the West Qurna I field in southern Iraq

(Rumaila field, west of Basra). West Qurna is believed to hold 43 billion barrels (6.8 109 m3) of recoverable reserves. The project is set to improve the current oil processing facility to increase the field production.

• Leading System Completion team for ExxonMobil projects involving Commissioning activities from Construction up to Turnover to Company.

• Commissioning Lead on PMC 2/3/4 Projects managing multi discipline Engineers,

• Mentoring Contractor(s) works in accordance with Company requirements.

• Leading all Commissioning activities with site personnel by ensuring proper Hand Over and Turnover to Operation as per contract requirements.

• Execution of Commissioning tasks for Utilities and Process systems, in respect of Project specifications.

• Driving Completions Management through Handover, Pre-Commissioning, Commissioning and Turnover.

• RACI chart development showing Project roles and responsibilities for each stakeholder.

• Development of Commissioning deliverables and Procedures as per schedule and Mechanical Completion targets. Issuing documents in documents database tracker for Company review and approval.

• Development of Mechanical Completion Dossiers and Turnover Completion Packages (Commissioning Dossiers) for Systems/ Sub-systems,

• Field technical support for Commissioning tasks, and final inspection with Contractors/ Vendors,

• Attendance for Electrical panels powering up, Instrument Cold/Hot loops, Motor solo run, Pumps run, Static and Dynamic tests, Leak/Tightness Test and Nitrogen inerting.

• Coordinate with Field Engineering identification of required Vendors and Licensors for pre- commissioning and commissioning works.

• Participate in Systems Walk downs with Contractors for system inspection, punch items issuance/ clearance.

• Review and update P&IDs, PFD’s, Isometrics. Ensure latest revision and red lines mark-up

• Assign Check sheets (ITR’s – All disciplines) for population in database

• Development of System & Subsystems P&ID Boundary Mark-up, ICSS Mark-up, Single Line Diagram,

• Coordinate Risk Assessments study/SIMOPS and ensure application at site,

• Attendance in PSSR (Pre-Safety Review) walkdown.

• Tracking of Project Level 4 schedule on Primavera.

• Monitor Commissioning Progress using System Completion Database: QEDI (GoCompletion) and CCMS.

• Monitor work performance and addressing any area of concerns, Technical Queries, Non-Conformity Report.

• Participation in daily, weekly and monthly meetings for Construction and Commissioning look-ahead,

• Support to Operation Team for Pre-Start-up preparation run. Resume: Mob: +33 Bernard 6 6285 4341

Pre-Commissioning Lead

Total Integrated E&P Congo, Team (Moho iTeam)Nord, Ponticelli, 1Bis Project Technip, (Alima Spie FPU), Congo Republic The development comprises a total of 28 subsea wellheads tied back to Floating Production Units

(FPUs) and 17 more wells from a new tension leg platform (TLP). The project is expected to have a production capacity of 140,000 barrels of oil equivalent per day.

• Leading Pre-Commissioning field activities on Moho Nord 1bis Project,

• Field supervision as Company representative on the offshore Alima Floating Production Unit,

• Ensuring all Pre-Commissioning tasks such as Test Packs Hydrotesting/ Pressure testing, Electrical and Instruments tests are completed as per planning and reported/ signed on check sheets,

• Coordinate Pre-comm activities during plant shutdown

• Management of completion signatory of RFC (Ready for Commissioning) Dossiers,

• Ensure all punch items are cleared to enable smooth transition to Commissioning group,

• Ensure Hand over to Commissioning Team is done as per contract specification.

• Ensure isometrics used for Test Packs dossiers development are updated (As Built markups),

• Anticipating all Pre-Commissioning activities (material preparation, manpower, PTW coordination),

• Tracking work progress with Discipline Engineers (Piping, Electrical, Instrument, Mechanical),

• Participating to daily meetings with Construction, Commissioning groups, QA/QC and Safety groups,

• Follow up with Technip when it comes to engineering issues or modifications and new revision,

• Monitor Project schedules during plant shutdowns for retrofits, improvements and repairs tasks,

• Progress tracking database on ICAPS (Total) and Ponticelli software support. Senior Completion Engineer

RasGas Japan Gas – Exxon Corporation Mobil, BARZAN (JGC), Yokohama Onshore Project, Ras Laffan, Qatar Exxon Mobil - Houston, USA

Onshore Gas processing facilities for Natural Gas (Train1/2, Utilities & Offsite, Common Process). Production: 1.4 billion cubic feet of gas a day. Qatar Petroleum (QP) and Exxon Mobil Barzan Limited, subsidiary of Exxon Mobil Corporation. Development of Barzan Gas Project ($10.3bn).

• Senior Completion Engineer Leading Trains 1 and 2 (SRU, AGR, SMR, Dehydration Unit, NGL/NRU),

• Field Supervision of the Mechanical Completion & Commissioning activities as Company Representative.

• Management tracking of Mechanical Systems Completion Packages (SMCP) and sign-off of 434 Mechanical Systems Completion Certificate (SMCC).

• Responsible for overseeing JGC Contractor group for all preparations and executions of field works to reach Systems Mechanical Completion.

• Tasks covered: Piping Cleaning, Water Flushing, Water jetting, Air Blowing, LO Flushing, Chemical cleaning, Bore scope inspections, Pumps MTR, Gas/ Steam Turbines No Load/Load run, preparation for live-up Fuel Gas, Steam, Condensate, Utilities, Refractory Dry out, Catalyst loading, Chemical Degreasing, LP/HP Leak tests, Cooling Water Passivation.

• Tracking Electrical and Instrument loop/Function tests with disciplines leads.

• Field participation to all tests, coordinating and witnessing activities for Mechanical Acceptance Packages on all systems in Trains 1 and 2.

• Responsible for the management of completion signatory from Construction, Pre-Commissioning, Commissioning and acceptance of Systems.

• Ensure Hand over is done properly as per contract requirement.

• Provide guidance and advices to safely reach Completion and Turnover of MAP systems.

• Ensure all tasks are performed as per Project specifications and Company Safety rules.

• Assist Contractor and Vendors with Method Statement, JSA, Detailed Procedure preparation and review.

• Participate on system walk-downs/Punch list Consolidation/Verification prior to systems handover.

• Support to Operation team for ‘Early access’ preparation run (Dedusting, preservation, CW circulation).

• PTW coordination to ensure all isolation and de-isolation certificates have been issued.

• Intensive Field walk downs for Punch issuing and close out, daily follow up using progress curves.

• Manage database tracking of Mechanical Completion of MAP Systems prior handover to Operations.

• 3D Model review for Construction installation and Commissioning/ Operation access. Resume: Mob:

Pre-Commissioning Manager/ Coordinator

ROSETTI ASHTART MARINO Revamping (Italy)Project, SEREPT for SEREPT (Oil Research, (COMPANY)Exploitation, Sfax, Tunisia and Production Company of Tunisia)

• Pre-Commissioning Manager/ Coordinator - Revamping of 5 offshore fixed platforms PP1/PP2/PF1/PF2 and satellite platform PF3 (60,000 barrels oil per day),

• Development of all Pre-Commissioning activities and supporting Documents,

• Coordination of activities with all disciplines leads working onshore and offshore,

• Daily meeting with client for Pre-Commissioning activities offshore (preparation and schedule). Commissioning Systems Leader

TOTAL, Hyundai BONGKOT Heavy Industries Project (Phase HHI Ulsan 4A, PTT Korea)Exploration, PTG (Indonesia & Production Cilegon)Public, Bonghot Company (Thailand)LTD. .

• Commissioning Utilities Systems Leader (Living Quarters Platform & Processing Platform Topside,

• Supervision of EPCC Contractor activities linked to the Commissioning of the Process (sub)-systems of the Topsides and Interfaces during the Preparation/ Execution phases,

• Responsible to monitor the organization, preparation and the execution of the commissioning activities are performed as per Company safety rules. Writing and review of commissioning procedures,

• Supervision of the commissioning activities (Onshore/ Offshore) as Company Representative,

• Utilities Leader offshore (Water systems, Air Compressor system, Nitrogen package, Gas Turbine, Firewater, Electro chlorination, UV Sterilizer, Sewage, Heating Medium),

• Intensive Punch items issuing and close out. Progress status tracked on Database,

• Ensure quality and compliance with OPERCOM and ICAPS Database in the daily execution tasks,

• Ensure liaison with Project (Construction/ Pre-Commissioning) and Operations Team. Maintenance Superintendent

TOTAL, YLNG Project, Yemen LNG Limited, Yemgas (FZCO), Huntoil, Technip.

• Employed as Maintenance Superintendent, part of the construction of two LNG Trains, associated with Utilities and offsite facilities (US$900 million) for TOTAL. Production of 6.7 million metric tons/year of LNG

• Managing and follow up general technical assistance activities carried out by maintenance team and contractors in the process and offsite areas of plant facilities

• Coordinates maintenance night activities of mechanical, instrument, electrical and control system tasks.

• Supervision of Disciplines Supervisors and Lead technicians.

• Coordinates all tasks completion as per Production Manager priorities,

• Supervise implementation of modifications approved through CR’s (Change/ Modifications requests)

• Provides necessary guidance and technical expertise to general maintenance technical services.

• Participates in the pre-engineering and planning of major maintenance and main shutdowns.

• Submits written reports to Maintenance Manager and Head of Production. Commissioning Engineer

TOTAL, YLNG Project, Yemen LNG Limited, Yemgas (FZCO), Huntoil, Technip.

• Employed as System commissioning engineer, part of the construction of two LNG Trains, associated with Utilities and offsite facilities (US$900 million) for TOTAL. Production of 6.7 million metric tonnes of LNG per annum.

• Interface & follow up of EPCC commissioning Contractor activities on Utilities systems: Gas Turbines 26.3 MW (GE/ Nuovo Pignone), Emergency Diesel Generator 1.75 MW (SDMO), Nitrogen unit

(Costain), Flares and Burn Pits, Boiler, Water System,

• Tracking progress of Air Product (APCI) equipment such as Nitrogen Unit, MCHE (Main Cryogenic Heat Exchanger) with Process/Utility teams.

• Knowledge of the LNG process including AGR, Dehydration, MRU, Fractionation, Liquefaction and Refrigeration units.

• Review of Pre-commissioning & Commissioning procedures including OTP’s.

• Monitoring of all aspects of commissioning tasks to ensure the works completed are as per the Project specification and Quality. Ensure handover is in accordance with the project cost/ schedule, including implementing Company HSE policy,

• Review and comment of Start-up procedures covering Utilities & Offsite Areas issued by Contractor,

• Advice, assistance and leadership to Utilities Contractor team during start-up phase,

• ICAPS database status tracking for Pre-Commissioning and commissioning progress (OPERCOM).

• Punch List issuing and follow-up. PTR (Project Technical Review) audit follow-up,

• Witnessing field activities: Mechanical (motor solo run/ pump alignments), Instrument (Loop testing, Cause & Effect, DCS), Piping (Hydro-test, Flushing, Blowing, Inerting), Electrical load shedding.

• SIMOPS methodology during gas-in.

• Review & signing of Commissioning Dossiers prior hand-over to Operations Department. Resume:

Commissioning Engineer

ENTREPOSE Shell, NLNG Six CONTRACTING Project, Bonny – Delattre Island, Nigeria Bezons LNG Nigeria Limited, (DBN) Technip (TSKJ)

• Development of Pre-commissioning & Commissioning Packages Work Method Statement, Test Procedures, Test forms and Inspection Test Plan (ITP) as per Project Specifications. Construction of the 6th Train including Utilities facilities (350M€) for Shell Company,

• Activities achievement preparation from Mechanical Completion (MC) up to Start-up (RFSU),

• Supervision of commissioning activities on Nitrogen unit and LPG Storage tanks Butane/ Propane,

• Responsible for development of the entire Project Commissioning Procedures distribution and update,

• Writing of Commissioning Work Instruction (CWI) of various equipment tests (Electrical, Instrument

&Control, Mechanical and Piping).

• Pre-Commissioning: Piping cleaning (Blowing, Flushing, Tightness, Drying). Flush Packs development. Catalyst/ desiccants loading and box-up records,

• Supervision of Utilities systems: ensuring Systems are commissioned as per project specifications,

• Daily progress tracking with database support for commissioning activities,

• Working and modification of engineering PID’s (NPIC) using Management of Changes. Preparation of safeguarding tests (C&E matrix). Coordination with Invensys/ Foxboro/ Triconex Team (DCS/ SGS/ FGS) for programming needs.

• Management of multidiscipline local Nigerian team for Pre-Commissioning and commissioning activities.

• Field walkdown for punch list issuing, clearance and close out verifications.

• Control and inspections of equipment. Interface with third party for Instruments calibration,

• Interface with Vendors for factory acceptance testing and pending items (Carry over work).

• Follow-up of all technical queries with client (Shell),

• Monitoring of Equipment first fills, temporary equipment to support pre-comm. and commissioning tasks.

• Vendor Spares Parts (SPIRS) review (Commissioning, 2 years Operations). Commissioning Engineer

ENTREPOSE NLNG Six Project, CONTRACTING Paris, France.

• Development of all Project Pre-Commissioning and Commissioning procedures,

• Assignment of Pre-commissioning and commissioning Check sheets for all disciplines,

• Review of process engineering drawings including isometrics with engineering office (Doris)

• Engineering detail analysis and follow up of PID/ PFD/ PEFS,

• Site interface with Shell Nigeria for review of Commissioning documents and planning.

• Instruments data sheet and ICS configuration database (INTOOLS) with disciplines leads. Maintenance Manager

TOTAL Photovoltaic ENERGIE Energy, (TENESOL) Toulouse, – Joint-France. Venture TOTAL/ EDF

• Project Support in a New plant creation managed by TOTAL (Oil and Gas) and EDF (National French Energy supplier). Manufacturing of Solar-photovoltaic Power systems with a capacity of 17MW,

• Maintain the complete production equipment involving improvements/ changes,

• Ensure performance levels by preventive/ curative operations,

• Technical intervention on robotized equipment (Electrical, mechanical, software),

• Site Safety management (staff training, intervention of safety organisms),

• Planning of maintenance interventions.

• Vendors coordination and technical support.

Field Support Engineer

EADS Toulouse, Test France. & Services, Airbus France.

• Worldwide Customer Test benches equipment’s installations. Product Support and failures analysis. Preventive and curative maintenance tasks on flight aircrafts (fleet A320, A340, A380), Technical intervention on civil ATEC test benches (5000, 6serial) for worldwide aeronautic companies: Air Canada, British Airway, Japan Airline and Korean Air.

• Spares Parts management. Technical support (phone and physical interventions),

• Electrical and Mechanical repairs on specific measurement resources. Hydraulic and Pressure equipment’s installation (Voltage, Current and Frequency tests). Module calibration and Test on bench.

• Maintenance intervention aligned with Customers contracts (Europe, Asia).

• Symposium attendance and speech for new products presentation.

Field Service Engineer

RECIF France: TECHNOLOGIES Toulouse, Grenoble (Semiconductor Equipment Manufacturer Company) United States: Phoenix, San Francisco, Portland, Boston.

• Installation, set-up and maintenance of robotized equipment’s (corrective/ preventive) dedicated to semi-conductor silicon wafers transfers,

• Advise international customers and provide technical valuation on the diagnosis on site. Interventions for worldwide recognized Semi-conductor Companies (Motorola, Siemens, Samsung, TSMC),

• Physical (ESD) and chemical measurements – Research Center (LETI/ CEA, Grenoble- R&D),

• Measurements tools used for micro inspection TENCOR (laser type) + NIKKON (optical),

• Robotic unit installations including silicon wafer identification technology and Mechanical system,

• Training of local production operators. Technical reports writing,

• Daily progress meeting with customers for plan and investigation,

• Maintenance operations. Parameters adjustment. Technical interventions on customers plants located in United States, Asia and Europe,

• Company representative to achieve facility project and maintenance target. Field Service Engineer

RECIF INTEL TECHNOLOGIES Electronic, Albuquerque (Semiconductor (United States)Equipment, Qyriat Manufacturer Gat (Israel), Company) SAMSUNG (Korea) VMT Handling Machines Project + BPP Project

• Interfacing with client as Resident contract.

• In charge of all equipment’s start-up and tool installations (electro-mechanical, automation and video recognition). Works carried out in clean room environment (class 10),

• Corrective and preventive maintenance on equipment’s 24h Technical intervention,

• Training to local employees. Main focal point to customer for new software test and equipment’s upgrade.

• Development of Operating Manuals as per specifications and project quality rules.

• Safety Risk and Hazard Operations training. Certification obtained for working in Chemical environment.

EDUCATION, TRAINING & QUALIFICATION

Date of birth: 17 April 1973

Nationality: French

Language: English (Fluent), French (Mother tongue), Spanish (basis) Marital status: Married

Qualification:

• BTec Higher National Diploma, Electrical & Mechanical Engineering, BTS (Electrotechnique), France (1996)

• High School Diploma, Electrical & Mechanical, Bac F3 (Electrotechnique), France (1994) Software :

• MS Office Pack, MS Project, Primavera P6 planning tools, Aconex, Coreworx

• Database: McPlus, ICAPS, WinPCS, GoCompletion (Qedi), Tomas, SmartPlan

• Navisworks Viewer 3D Model

• Data processing programming under UNIX, ADA, C++, Atlas.

• PLC automation and HMI programming, TENCOR (laser inspection), NIKKON (Micro Particles Optical inspection).