HARI SHANKAR SHARMA

Qtr.No. B -**, Prism cement Colony

Mankahari, Satna, M.P 485001

Mobile – 095******** Res.- 073********

E – Mail adiscq@r.postjobfree.com.

adiscq@r.postjobfree.com.

Professional Experience: - May 94 – Aug 95 Elin Electronics Ltd.

Ghaziabad (U.P.)

Aug 95– March 06 Ultra tech cement (Grasim)

Mar06- Sep 07 Ultra tech cement (Raj Shree)

Sep 07 – Mar.09 Acc Cement, Wadi

Mar.09 - Aug-13 OCL Cement Line 2, Rajgangpur

Name of Present Employer: - Prism Cement Line 2

Designation: - Unit 2 Line Incharge (General Manager)

Key Responsibility in Prism Cement: - Mech.Maintenance of lime stone crusher to Packing plant of line2

Planning of manpower, material and other resource.

Preparation and Execution the Budget and control the cost within the limit.

Implementation of SAP PM Module in department to monitor the history and life cycle of equipment to improve the reliability of equipment.

To create positive work Envoirment in work place.

Leader of innovation & Implementation team to improve the plant efficiency with the help of QC tools and technique.

Implementation of IMS System in plant

Co-ordinate among department to resolve the issues and delay of work.

Circle leader of Cement Mill TPM team.

Co-ordination with condition monitoring team to improve the life of the equipment.

Previous Employer: - Erection & Commissioning of OCL line 2 Project

Of 4000 TPD Clinkerisation & Loesche cement &

Grinding VRM.

. The Major equipment

Suppliers are HWI for kiln and cooler, Loesche for

Raw mill, coal mill and cement grinding.

Schenck process for weighing system

Material handling By L& T

. Dedusting system by Thermax

.

Erection of 2 x 27 MW Power Plant .2 no’s IJT boilers, Coal Handling and Turbine

Previous Employer: - Mech.HOD at ACC Wadi Cement Works

Name of the previous Employer: - Ultra TECH Cement Group.

(Raj shree Cement & Grasim Cement)

(A Unit of Aditya Birla Group of Industries)

Producing Varieties of cement, Total installed

Capacity – 3.8 MT. at single location

Responsibilities in Raj shree: - Section Head of Pyro- section with Job Band 9 Cement

Key Responsibilities in

Grasim Cement: - Maintenance & Commissioning of Ball mill (230tph)

KHD ROLL – PRESS (through put 850 tph) Dynamic separator SKS – 3000 & its auxiliary equipment.

Maintenance of LOESCHE VRM LM –50.4 (290 tph) in raw mill. & VRM LM- 26.3 (40 tph) in coal mill & its auxiliary equipment.

Maintenance of L & T Kiln (3300tpd) FLS – COOLER & SIX – STAGE PRE – HEATER.

Maintenance of twin boom Cimmco stacker & Bridge type reclaimer in lime & coal both.

Maintenance of L&T coal crusher (850 tph), ROTA – SIDE – XL wagon tippler, and Truck tippler in coal handling system.

Erection, Commissioning & Maintenance of slag Grinding. POLYCSIUS ROLL – PRESS (size 17/10-7-s) Dynamic separator & hot air generator.

Erection & maintenance of material handling system like bucket – elevator, DDPC Ammund, belt conveyor & screw conveyor.

Erection, Commissioning & Maintenance of high speed fans, blower & compressor.

Erection & Maintenance of weighing system like on line motion weighbridge, weigh feeder (PBL) & solid flow meter.

JOBS DETAIL

Planning & scheduling of manpower and maintenance activity.

Preparation of equipment history, why- why analysis of breaks down & record keeping in SAP.

Technical evaluation & inspection of new equipment.

Inventory & cost control.

Supervision & costing of contractor jobs.

Modification & improvement of equipment.

Spare parts planning & follow- up with store & purchase.

Developing system format & check sheet as per

ISO –9002 & 14001.

Co–coordinating & working in SAP PM

Module & MM Module system.

Develop & creation of equipment Schedule.

Orders, task lists and implementation in sap pm

Module.

Implementing and working in WCM / TPM work

Culture

SPECIAL ASSIGNMENT: - Erection & commissioning of pfister pump

( Rota scale ) in Rajshree Cement

Erection & commissioning of Multi core in

kiln Firing System & Kiln Feed system

Erection & Commission of Pyro – Step Cooler

Erection & commissioning of modified version of

Classifier in raw mill. (LJKS – 93 to LSKS-78)

Complete over hauling & replacement of FLENDER

KMP-710 gearbox & PSZ 355.

Complete over hauling & replacement of lohman

Gearbox GPV- 395. Also, develop indigenous

split type ring gear, planet gear & sun shaft.

Extension of rail track in L.S. Reclaimer.

Certified Auditor of ISO – 9002 from BVQI.

Facilitator and leader of various QC forum and TPM

Activity

As a trainer in RTC Jammul on VRM & BALL

Mill.

Tech. Training Thermal power plant & Tool Room in TISCO

Jamshedpur.

Thermal Power Plant KTPS, Patna.

Maintenance & Balancing of Industrial Fan from RTC

Jamul Durg

MDP Training From NIIT Rourkela, Odisha

Training on QUALITY SYSTEM & PRESENTATION in IIT Kanpur

Educational Qualification

Qualification

Institute/ University/ Board

Marks

HSC

BSSE Board, Patna

63 %

10+2

BIEC Patna

54 %

B.SC. (Mech.

Engineering

M.I.T Muzaffarpur Bihar

73 %

Computer Skills

MS Office, Auto – Cad, Networking

Personal Profile

Date of Birth 22 Aug. 1967

Sex Male

Marital Status Married

Language known English / Hindi

Permanent Address S/o Sri Bindeshwari Sharma

S.D.E Telecom, Patna

Passport No.

A- 1527718

Present Salary 42 Lacs / Annum