PROFESSIONAL SUMMARY
• Created PLC programs and hardware setups for various projects (chemical, petrochemical, steel and power industries) utilizing Rockwell (ControlLogix, SLC 500), Modicon, Siemens, General Electric, and Reliance.
• Created HMI screens and programming utilizing Wonderware, RsView, Cimplicity, and Intellutions software.
• Engineered DC Motor Drive designs for steel mill and process line applications.
• Succeeded and heavily involved in the areas of Electrical Construction, Field Startups, and the Commissioning of equipment on many projects.
PROFESSIONAL EXPERIENCE
Universal Creative February 2016 - Present
Orlando. Fla.
Senior Manager, EHS
• Responsible for reviewing and updating specifications for ride/show attractions for theme parks.
• Manage ride/show vendors from concept design through detail design to ensure correct control design for the intended attraction.
• Becoming well versed and trained in in ISO 12100, 13849-1, 13849-2, and IEC 60204 for safety of machinery and safety related parts of control systems.
• Becoming well versed in risk assessment and risk reduction for safety of machinery.
• Responsible Individual (R.I.) for control system for water theme park attraction and round rides.
• Have great experience with ControlLogix Controllers and I/O and modest experience with GuardLogix Safety Controllers and I/O.
Chester Engineers April 2015 – February 2016 Pittsburgh, Pa.
Automation Engineer
• Responsible for electrical design of control and power systems for LNG project.
• Responsible for developing control system, instrumentation, MCC, and VFD specifications for LNG project.
• Responsible for election of ControlLogix and GuardLogix PLC hardware (including the use of safety I/O products and intrinsic safety barriers) and instrumentation for LNG project.
• Responsible for programming of PLC and HMI development.
Tenova Core Feb. 2015 – April 2015 Pittsburgh, Pa.
Electrical Engineer (Contractor)
• Responsible for electrical design of control and power systems for industrial furnaces
• Utilize AutoCad for electrical schematics, single line diagrams, and control cabinet layouts.
Heyl & Patterson April 2011 – Dec. 2014
Pittsburgh, Pa.
Electrical Design Engineer
• Responsible for electrical design of control and power systems for dumpers, coal barge unloaders, rotary dryers, and calciners
• Utilize RsLogix 5000 software and Factory View ME Station (HMI Screens) for most applications
• Utilize AutoCad for electrical schematics, single line diagrams, and control cabinet layouts.
• Startup and commission all equipment engineered and fabricated.
GE Transportation October 2010 – April 2011
Erie, Pa.
Electrical Integration Engineer (Contractor) .
Responsible for all harnessing, cabling, connectors, and schematics for electric and diesel locomotives
Developing purchase specifications for domestic and international cabling and connectors.
Integrated Project Resources July 2009--December 2009
Chicago, IL.
Electrical Construction Manager
Tracked the electrical construction progress (equipment setting, electrical cable pulls, and cable terminations) of a Steam-Turbine Power Plant.
Reviewed electrical schematics of the project for discrepancies in connections versus the cable/conduit schedule.
Hatch Associates March 2008 – Jan 2009
Pittsburgh, Pa.
Senior Electrical Engineer
Co-Gen Project for USS – Granite City:
• Designed all 480 and 4160 VAC motor control center and CCTV system schematics for entire facility.
• Designed the DCS I/O list from P&ID drawings for entire facility.
• Wrote the electrical specification for the Bentley Nevada vibration system for large horsepower motors.
• Developed the fiber-optic routing drawings (PLC communications) for entire facility.
Project Engineer/Lead Automation Engineer
Slag Management Project for USS – Fairfield:
• Developed the Sequence of Operations for the facility.
• Engineered the PLC electrical schematics for all instrumentation and valving for Allen-Bradley Controllogix (RsLogix 5000) including the development of the Ethernet network.
• Developed the Radio Remote Control specification for front loaders and slag haulers.
• Designed PLC cabinet layouts and operating station layouts.
River Consulting LLC (Formerly Trimark Engineers) July 2006 - March 2008
Pittsburgh, Pa.
Supervisor of Automation & Controls
• Performed an Electrical Classification Site Survey for Kinder Morgan Tank Storage Facility in Harvey, LA.
• Modified PLC programs and HMI screens utilizing Allen/Bradley Controllogix PLC (RsLogix 5000) for a new DuPont Filter Press project.
• Updated instrumentation and PLC hardware on bulk storage tanks for Kinder Morgan Tank Storage Facility including developing the specifications for the procurement of instrumentation.
S/D Engineers November 2005 – July 2006
Pittsburgh, Pa.
Electrical Engineer (Contractor)
• Programmed A/B SLC 500 and developed HMI (RSView) screens for Reliant Energy (coal-fired power plant) for upgrade to two (2) Clarifier, Gravity Filter, and Clearwell systems.
• Commissioned and started up both systems.
Aker Kvaerner June 2004 – November 2005
Pittsburgh, Pa.
Instrumentation and Control (Contractor)
• Programmed GE Series 90/30 PLC and developed HMI screens (Wonderware In-Touch) for Basic Oxygen Furnace Electrical Precipitator upgrade for USS-Great Lakes.
• Commissioned and started up the system.
Rockwell Automation April 2003 – June 2004
Warrensville Heights, OH
Instrumentation and Control Engineer (Contractor)
• Worked in their Flex Factory Group designing control panels.
• Specified and scheduled all electrical components within the panels utilizing mostly Allen-Bradley products.
• Designed and drafted (AutoCad 2004) mechanical layout of control panels and cabinets and developed the electrical schematics associated with the cabinets.
• Created bills of material for all components of cabinet.
• Worked with shop floor to resolve any issues concerning control panels.
• Worked with clients on any special needs or problems concerning the cabinets
• Took a special assignment (Electrical Construction) in Tuscaloosa, AL at a Mercedes-Benz assembly plant on an installation for a plant expansion; work included supervising electricians installing electrical cabinets, resolving cabling issues, and resolving Devicenet and Ethernet networking problems.
Trimark Engineers Sept 2001- July 2002
Pittsburgh, Pa.
Lead Electrical Engineer
Boiler Room addition for Pechiney Rolled Products:
• Designed PLC (Modicon 584) layout developed the electrical schematics and programmed the PLC.
• Designed the motor control center layout and single line schematics
• Developed electrical specifications for motor control centers and AC motors.
Carbon Reactivation Plant – Calgon Carbon:
• Collaborated with Electrical Designer in the design of lighting, power distribution, grounding, and Ethernet communications and the layout of embedded conduit between plant and office building.
• Designed layout of all motor control centers for the Reactivation Plant.
• Developed all electrical specifications necessary for the construction of the office building.
• Specified all PLC equipment (Allen-Bradley Controllogix) necessary for the entire plant.
• Designed the layout of substation for the power feed to the plant and office building.
• Worked with the local power utility to size the incoming transformer for the plant.
Svedala Industries July 2000 - August 2001
Neville Island, Pa.
Principal Electrical Engineer/Lead Electrical Engineer
Stacker-Reclaimer – Venezuela:
• Developed electrical schematics, specifications and power single lines for all facets of the project.
• Specified electrical equipment for the project including: AC motors, motor control centers, programmable logic controller, AC Frequency drives, position limit switches, encoders, motor tachometers, and instrumentation.
• Designed PLC (Allen-Bradley 540) cabinet layouts, AC drives enclosures, and operator consoles.
• Reviewed panel and enclosure internal wiring layout.
• Coordinated with mechanical and structural disciplines for mounting of all electrical equipment.
• Developed P&ID schematics and specifications for electrical house (control room) and operator consoles.
Gensystems (Herr-Voss Division) Jan. 2000 - July 2000
Evans City, Pa.
Project Engineer/Senior Electrical Engineer
Tension Leveling Line – Walbridge Coatings
Kvaerner Metals May 1994 - Jan. 2000
Eastlake, OH and Pittsburgh, Pa.
Senior Electrical Engineer/Automation Engineer
Galvanizing Process Line Upgrade – USX – Fairless
Robicon Corporation Sept. 1989 - May 1994
Pittsburgh, Pa.
Senior Electrical Engineer/Project Engineer
Skip Hoist System: LTV Steel (Cleveland, OH) and Rouge Steel (Dearborn, MI)
Coke Furnaces: USX Coke Works (Clairton, PA)
Tippins Inc. April 1979-Sept. 1989
Etna, Pa.
Electrical Engineer
• Designed Control systems for Steel Mill projects.
EDUCATION
Penn State University