SUMMARY:
Quantity Surveying professional over 11+ years of experience, out of which 9+ years in UAE from esteemed organizations with ability to work in a fast paced environment, meet stringent deadlines, qualities of adaptability and capable of working harder to meet the commitments of the organization. JOB OBJECTIVE:
To be a competent Construction Commercial Professional with focused approach in a Leading Organization and doing challenging global Projects, from inception to the completion, utilizing prior experience and demonstrated expertise in Quantity Surveying.
Total years of experience : 11+ years
Current location : Coimbatore, India
Location preference : No preference
ACADEMIC PROFILE:
Bachelor of Technology (Civil)
Diploma - Civil Engineering (DCE)
SOFTWARE SKILLS:
Diploma in AutoCAD
Planswift
On Screen Take off.
Xpedeon ERP solutions
Aconex Document Management systems
Diploma in STAAD Pro & MS Project
SUMMARY OF SKILLS AND EXPERIENCE:
A keen commercial professional with 9+ years of rich gulf experience in Quantity Surveying and Contracts Management of Construction projects.
Quantification & Costing, Procurement, Subcontracts, Contracts Administration, Cost Control & Commercial Management are the main skills of expertise.
Comparison of technical/commercial quotes from subcontractors in liaison with project specifications to finalize scope of works
Drafting Contract agreements for sub-contractors
Drafting commercial correspondences to consultants and contractors
Identification, Initiation, submission of Claims.
Rate analysis, comparison of the Items in the quotation against project specification.
Cost control with established cost control methods in construction. Page 2 of 5
Key Duties & Responsibilities:
Post-contract functions, monthly valuations, project variance reports and Identification of claims for extra items of work at sites.
Responsible for maintaining Monthly payment status, Variation log, Sub-Contractor agreements& Payment log.
Floating Enquiries and following up for the Quote from the Vendors / Manufacturers / suppliers
Prepares detailed cost breakdown as per the scope including detailed material take off, activity wise resource requirements, subcontracts, indirect costs, etc.
Projecting of Project cost &Budget by liaison with cost control strategies.
Following-up with clients & consultants for Payment certificate and payment for the work done at site.
Following up for approval of Variations & Variations orders with the Consultants.
Responsibility for agreeing and recommending approval of contractual payments leading to the settlement of the “Final Account” for small and medium civil engineering schemes.
Knowledge of FIDIC, POMI for the purpose of documentation and discrepancy for various contractual claims.
Preparation of Schedules of Rates, Activity Schedules and associated contractual documentation.
Certification to the Sub-Contractor for the value of work done on monthly basis.
Responsible for managing all project costs from pitch to completion.
Undertaking costs analysis for building projects.
Supervision the construction activities at site
Preparation and submission of periodical progress report to the employer and senior management
Ensure that the quality of construction is built and maintained
Performed all aspects of field engineering assignments including the development of plans, schedules, contracts, procedures, construction methods and systems for the project
On completion of internal inspection of the completed work, originate the field inspection requests, so as to get the final work inspection approved by the consultant/engineer
Forecast manpower requirements and project details to planning department/Hr department and assist them in experience sourcing in accordance with the project requirements
Responsible for reviewing the performance of subcontractors to assure contract compliance, the application of accepted construction technology and standards and acceptable standardization of materials and supplies
Report and Liaise with senior engineers/officers and provide periodical reports and Co-ordination of the progress of construction activities
PROFESSIONAL EXPERIENCE:
Employer : M/s. Sobha Engineering & Contracting LLC Period : From September 2017 to Till Date
Designation : Senior Quantity Surveyor
Page 3 of 5
Projects Involved
CONSTRUCTION OF 2B+G+23 FLOORS+R KEMPINSKI BUSINESS BAY HOTEL TOWER AT BUSINESS BAY, DUBAI, U.A.E
Project Cost : 230 Million Dirhams
Duration : 2 years (Ongoing)
Contract Type : Lump sum
Consultant : M/s. National Engineering Bureau
Project Manager : M/s. MACE International Ltd
Client : M/s. Seastar Properties Ltd
CONSTRUCTION OF R-1030-PORTS VIEW MIXED USE DEVELOPMENT, MADINAT DUBAI Project Cost : 330 Million Dirhams
Duration : 18 Months (Completed)
Contract Type : Lump sum
Consultant : M/s. Design & Architecture Bureau (DAR) Client : M/s. Government of Dubai – WASL LLC
Employer : M/s. Ghantoot Transport & General Contracting LLC Period : From April 2013 to August 2017
Designation : Project Quantity Surveyor
Projects Involved
CONSTRUCTION OF FUJAIRAH HOTEL & RESORTS S+G+6 FLOORS+ROOF, AL AQQA BEACH, FUJAIRAH
Project Cost : 235 Million Dirhams
Duration : 3 years& 2 Months (Completed)
Contract Type : Lump sum
Consultant : M/s. National Engineering Bureau
Client : M/s. Al Ain Properties, M/s. Intercontinental Hotel Group CONSTRUCTION, COMPLETION OF EMIRATES NATIONAL SCHOOL & RESIDENTIAL BUILDINGS AT RAS AL KHAIMAH
Project Cost : 476 Million Dirhams
Duration : 1 year & 2 Months (Completed)
Contract Type : Lump sum
Consultant : M/s. Heberger Consultant Engineers
Client : M/s. Ministry of Presidential Affairs, Abu Dhabi Employer : M/s. Proscape LLC
Period : From March 2011 to March 2013
Designation : Quantity Surveyor
Page 4 of 5
Projects Involved
AL GHURAIR CITY CENTRE, PHASE II - EXPANSION, Dubai. Project Cost : 9 Million Dirhams.
Duration : 2 Years & 3 Months (Completed)
Contract Type : Lump Sum
Consultants : M/s. Arif & Bintoak, M/s. Davis Langdon Client : M/s. Al Ghurair Centre
PPM CONRAD HOTEL, Dubai.
Project Cost : 7 Million Dirhams.
Duration : 1 year & 6 Months (Completed)
Contract Type : Lump Sum
Consultant : M/s. WS Atkins & Partners
Client : M/s. Private Property Management (PPM), Abu Dhabi THE BUILDINGS BY DAMAN AT DIFC, Dubai.
Project Cost : 20 Million Dirhams.
Duration : 1 Year (Completed)
Contract Type : Re-Measured
Consultant : M/s. Arif & Bintoak, M/s. Currie & Brown International Client : M/s. Daman Real Estate Capital Partners Limited Employer : URC Constructions Pvt. Ltd, India
Period : From April 2009 to March 2011
Designation : Executive Engineer - Projects
Projects Involved
CONSTRUCTION OF SEWAGE TREATMENT PLANT, Tamilnadu, India. Project Cost : 17 Million Rupees.
Duration : 9 Months (Completed)
Client : Tamilnadu Govt. Water Authority & Drainage Board CONSTRUCTION OF CEMENT CONCRETE ROAD @ MEPZ, Chennai, India. Project Cost : 12 Million Rupees.
Duration : 1 Year & 2 Months (Completed)
Client : Central Public Works Department (CPWD), India Consultant : M/s. Kitco Pvt. Ltd
Page 5 of 5
PERSONAL PROFILE:
Date of Birth & Age : 25th September, 1985 & 35
Father’s name : Mr. M.S.ABDUL SATHAR
Languages known : English, Hindi, Urdu & Tamil.
Strength : Hard worker & Team player.
Driving License : UAE Driving License-LMV–A / India-LMV Passport Details : Passport No: S 2954264& Validity until 19 June 2028 Local Address : 16F, 2nd Floor, Balasubramaniam Nagar, Peelamedu,
Coimbatore – 641004.
India.
Permanent Address : No: 4/74-2, Sanarpalayam,
Kuppandapalayam post,
Komarapalayam – 638183
Namakkal (DT),
Tamilnadu, INDIA.