CURRICULUM VITAE
PERSONAL DATA
Name: Mr.Paitoon Sareesai
Date of Birth: January-20-1967
ID. card no. 317**********
Religion: Buddhism
Languages: English/Thai
Permanence Address: Laem-chabang town,99/11,Moo9,Thungsukla,Sriracha,
Chonburi,Thailand,20230
Education: B.Ed. Bansomdejchaopraya Institute Bachelor degree
of Education in computer education
Diploma Pathumwan Technical Collage Major
welding industrial Technology
Computer Skills: Microsoft Office/Excel Word/E-mail/Internet/Outlook
E-mail Address: ***********@*******.***
Mobile Phone: +66(0)818741247
Skype ID: Paitoon Sareesai
WhatsApp: Paitoon Sareesai
PROFESSIONAL EXPERIENCE
Title: Superintendent/Senior/Supervisor/QA-QC/Coordinator in Welding/Piping/Structure/Pressure Vessel/Refractory/Furnace/Fired Heater/Heat Exchanger/NDT/Boiler/Sphere/LNG Storage Tank/Modules.
I have experienced Multi-discipline field onshore Construction over 29 years in EPC and PMC The oil and gas Industry/Power plant Specialist: Construction/Fabrication/Third party Inspection/Quality Control, Management/
Welding/Piping/Steel Structure/Sphere tank/LNG Storage tank/Heater Exchanger/Boiler/Pressure Vessel/
Module-LNG/GAS/Jacket Platform/Jack up-Rigs/Main Hull Structure/Pipeline/Petroleum/Petrochemical/
Power Plant/Fired Heater/Refractory/Furnace. I strong believed in the Specialist with following project special require and apply international standard and Codes: ASME-Boiler and Pressure Vessel for Construction. ASTM/ASMEI/II/V/VIII/IX/B31.1/B31.3/B31.4/B31.8/PFI-standard-ES-3/API-620/API-630/API-530/API-560/
API-650/API-1104/AWS-D1.1/AS-1554.1/AS-2980/AS-4100/AS-3678/AS-3679.2/DNV-OS-F101/DNV-OS-C401/
DNV-OS-B101/DNV-OS-C101/IACSNo.47/Rules-ABS/Part2 and NORSOK: M-101/M-501/M-601/ISO-15614-1 and BS EN-10025/BS EN-10088/BS EN-1090-2.
ü Special Training: Training Completed Under Examination CWI/AWS-QC1
ü Special Training: Welding Inspector CSWIP 3.1 Certificate of Attendance
ü Basic of Phased Array Ultrasonic Testing interpretation required Attendance
ü Qualified of Certifications for NDT
ü ASNT/SNT-TC-1A Level II in Radiographic Testing/Certificate Number: 813-05-006
Expiration/Date: 01-09-2023
ü ASNT/SNT-TC-1A Level II in Magnetic Particle Testing/Certificate Number: 813-05-006
Expiration/Date: 01-09-2023
ü ASNT/SNT-TC-1A Level II in Liquid Penetrant Testing/Certificate Number: 813-05-006
Expiration/Date: 01-09-2023
ü Confined spaces Certificated No.E61-0079
Period from Jan-2020 to- Open contract
Organization: Cimtas/China
Position: Specialist QC. Welding Inspector Structure
Project name: JACKSON PROJECT <MODULE STRUCTURE SKIDS GAS TURBINE>
Client: MHPS/AMERICA/FABRICATION BY UNITHAI SHIPYARD THAILAND
Main Duties & Responsibilities:
ü Inspection fabrication fit-up/dimensions check assembly follows ITP, refer project spec. required
Standard ASME Sec. II part A, ASTM / V / IX / B31.1/ AWS D1.1
ü Inspection material verifies steel plate mill certificate review report follow standard ASTM A36 / SS400
ü Review procedure NDE RT/PT/MPI/UT/PAUT reference construction specification acceptant criteria
ASME B31.1 and AWS D1.1
ü Review & witness procedure PQR, WPS, welding consumables, follow project specs, ASME B31.1/AWS D1.1
ü Review report mechanical test carbon steel accept criteria follow standard AWS D1.1/ASME B31.1
ü Witness WQT process SMAW, FCAW welding qualified butt weld in plate position 3G+4G
Acceptance criteria follow standard AWS D1.1
ü Visual inspection acceptance criteria follow standard AWS D1.1
ü Check quality of weld MPI, UT and RT Inspection NDE report follow acceptance criteria ASMEB31.1/ AWS D1.1
ü Coordinator and inspection review document requires of fabrication workshop & site NDT reports.
ü Supervise the subcontractor at site and the erection of steel structure
ü Review the received material packing list and check the ability of erection
ü Supervise the steel structure site modifications due to revised drawings and fabrication defect
ü Supervisor Check and solve the field construction technical query
ü Prepare daily and weekly erection status and all required reports
ü Prepare and follow up clearance of punch list.
ü Final overall dimension, Visual weld, assemble, Painting.
Period from Sep-2019 to Dec-2019
Organization: TTSJV<TechnipFMC-Tecnicas Reunidas-Samsung>
Position: Specialist QC. Supervisor Inspector Refractory
Project name: BAPCO Modernization Program
Client: BAPCO Bahrain Refinery Plant<VIPCO Vender Manufacturer/THAILAND>
Main Duties & Responsibilities:
ü Reviewed document describes the general criteria to carry out the castable / fibers application and
Inspection (workshop) relevant to the plant mentioned on the cover sheet of this document
ü API STD 560 / ISO 13705 Fired heaters for general refinery service
ü API STD 936 4th ed. 2014 Refractory installation quality Inspection and testing monolithic refractory
ü ASTM C 113 Reheat change of refractory bricks
ü ASTM C 133 Cold crushing strength and modulus of rupture of refractories
ü ASTM C 134 Size, dimensional measurements and bulk density of refractory brick and insulation firebrick
ü ASTM C 860 Determining the consistency of refractory castable using the ball in hand test
ü ASTM C 862 Preparing refractory concrete specimens by casting
ü Inspection: Crew prequalification Each Crew,Each castable Refractory material,Ref.procedure Apply codes/
Standards/Specification F9 PAR.7.1/ PAR.7.3/ F8 PAR.4.5.2 AND Acceptance standards API STD.936
ü Refractory Type: Morgan advanced materials FIRELITE 105: BACK UP <1st layer>
ü Crew prequalification testing shall be undertaken at least one week prior to actual jobsite refractory
Installation to allow time for curing and laboratory testing of prepared specimens
ü Ceramic Fiber Installation Anchors shall be inspected (PMI, hammer test) in accordance with ITP
ü Refractory Type: Morgan advanced materials KAOLITE 2500-LI: HOT FACE <2nd layer>
ü Inspection: Ref. Procedure/Specification F9-PAR.10.2 Ball hammer about 0.4kg.30 cm. maximum center
And acceptance standard F9-10.2C.Max. VOID 152 mm2/OR 12.7 mm are not allowed.
ü Crew prequalification testing shall be undertaken at least one week prior to actual jobsite refractory
Installation to allow time for curing and laboratory testing of prepared specimens
ü Ceramic Fiber Installation Anchors shall be inspected (PMI, hammer test) in accordance with ITP
ü Visual and Dimensional Inspection 100% Castable only Before Dry-out Ref.API-560-Par.17.5.5 (b)
ü Hammer Test 100% of Castable only surfaces After Dry-out the lining have set for 24 hours.
ü Visual and dimensional Inspection 100% Castable after dry-out Ref.API-560-Par.17.5.5 (b)
ü Hammer Test 100% of castable only surfaces after dry-out
ü Inspection: Assembly Convection coil, PROCESS RADIANT COILS, welding, Dimension, PWHT, NDT, Hydro Test.
ü Inspection: Dry-out and Cleaning, Manufacturer data book index specification, packing list, IRC
Period from March-2019 to August-2019
Organization: TOYO Engineering<Korea>Limited
Position: Specialist Senior QC. Supervisor Inspector Pressure Vessel/Heat Exchanger
Project name: EXPENTION PLANT Project<Petrochemical plant>
Client: BST Bangkok Synthetics Co.,Ltd/Rayong/Thailand
Main Duties & Responsibilities:
ü Pre-Inspection Meeting and Agenda
ü Material received inspection/actual material check and marking/reviewed material certificate/Heat number
Apply ASME-II Part-A apply ASTM SA516 Gr.60/70 & SA312 GrTP304/304L / ASTM A387 Cr-Mo
Alloy Steel Pressure Vessel Plates Gr.2, 21, 21L and 22L and follow project specification required.
ü Reviewed PQR/WPS apply ASME-IX/NDT method and procedure RT/MPI/PT/UT/UTM Apply ASME sec.V
ü Inspection Head Forming/Thickness/Visual/Dimensional & Shape Check after forming sec. VIII div.1/UG-79-81
ü Inspection for Alignment/Angle/Root gap/Cleanliness/Visual Check of Weld Edges Bevel preparation
& Fit-up for circum seam apply ASME VIII div.1
ü Inspection Nozzle Marking/Check Location and Orientation/ Nozzle Fit-up (Cat. B/C)/Check Alignment
And Cleanliness Fit-up of nozzle to shell (Cat. D joint) - Check Alignment and Cleanliness/ Fit-up
For Internal/External attachment/Check Alignment and Cleanliness apply ASME VIII div.1
ü Inspection Nondestructive Examination for Category "D" Joint/UT and PT shall perform where the
Shell thickness is 18mm. apply ASME VIII div.1
ü Inspection Bundle Inspection - Cleaning check/bundle pre-assembly
After finished drilling for tube sheet/PT after seal welding tube to tube sheet.
Expanding check& Leakage test using soap with air for tube to tube sheet after expanding.
Bundle final inspection before insert. Apply ASME VIII div.1
ü Final Dimensional Check and Visual Inspection/Completed Vessel Visual and Dimensional Check
Overall Length, Location, Inclination, Height and Orientation for nozzle Location for Attachment
ü Witness Pad leak test - Holding Time At least 5 minutes/Test Pressure Min.1.76kg/cm2 Apply ASME VIII div.1
ü Witness Hydrostatic Test/shell side/tube side holding Time At least according to project specification
Required minimum 1 hour and apply ASME VIII div.1/UG-99
ü Drain inspection check for drain/drying condition after hydrostatic test follow Project Spec. Fully drain and dry
ü Painting Inspection - Surface Preparation prior to Painting and Surface Temperature, Humidity
Dew point/Dry film thickness check follow procedure painting and project specification required.
ü Witness Preparation for Approved Paint Procedure/Packing/Shipment/ Rust Prevention/nitrogen (N2)
Charge at 0.5 kg/cm2 with valve and pressure gauge (Shell side & Tube Side)
Period from Jan-2019 to Feb-2019
Organization: GC Glycol Company
Position: QC. Inspector Welding/Piping/Pressure Vessel & Heat Exchanger/Mechanical
Project name: Turnaround Project<Petrochemical plant>
Client: GC Glycol company/Rayong Thailand
Main Duties & Responsibilities:
ü Implementation of client approved quality plan
ü Prepare and participate in required audits during Execution and post with client
ü Take a lead role in quality system implementation and follow up.
ü Contractor side as per project specification client Procedures.
ü Responsible for all the quality forms/certificate’s job execution.
ü Follow up of quality plan for effective implementation.
ü Develop standard or specific technical quality checklists for all jobs to be execution in the Turnaround
ü Follow up of quality plan and reports daily status to client.
ü Control all technical checklists after the jobs have been completed.
ü Participation in the weekly construction meeting with responsive operations to highlight any quality related issue.
ü Set up meeting with sub-contractor quality responsible persons to ensure affective implementation of
Client approved quality plan and procedures.
ü Material received inspection, actual material check and marking, reviewed material certificate, Heat number
Apply ASME-II Part-A
ü Reviewed Material Mill Certificates/PQR/WPS/NDT method and procedure RT/MPI/PT/UT/PAUT apply sec.V
ü Inspection fabrication and of piping spools follow ITP/WPS used standards and project specification.
ü Witness WQT follow ASME-Sec-IX and ASME-B31.3 Inspection ferrite test RT/PT/MPI/PMI
ü Inspections and apply as per API 570 corrosion cracking erosion dents mechanical Physical or
Chemical impacts apply API 571,574,577,578 and API 510 corrosion cracking erosion dents other
Mechanical and Apply API 571,572,576,577,578 ASME VIII division.1 and division 2
ü Reviewed Piping Test Package, Inspection line check walks before hydro test.
ü Witness Hydro test/Cleaning/Flashing/Reinstated/Reviewed ensure Site queries.
ü Clear list checked punch list, Review and approval of final document MDR.
Rotating Equipment Installation, Static Equipment Installation Inspection
ü Review Field Quality Plan corresponds to respective field works.
ü Review method statement, erection procedures and Inspection Test Plan (ITP).
ü Ensure latest revision drawings are being used at site and maintain As-built drawing for quality documentation
And submission to field engineering for verification.
ü Advised and Supervise to responsible in all static and rotating equipment due to installation and
Alignment Function key inspection as in transportation/installation/centering/levelling/alignment/
Grouting/bolt setting/bolt torque and etc. Prevision protects as rotate /corrosion prevent/
Packing condition/lubricant oil & grease and etc.
ü Alignment inspection of static equipment and rotating equipment such as Vertical Sulphur Pumps,
Vertical Sump Pumps, Horizontal Centrifugal Pumps/Heat Exchanger/Compressor
ü Preparation package all of Static equipment and Rotating Equipment Vertical Sump Pumps
Horizontal Centrifugal Pumps/Heat Exchanger/Compressor Cooling tower
ü Reviewed document and final MDR
Period from Sep-2018 to Nov-2018
Organization: BLCP Power Plant
Position: Specialist QC. Coordinator & Inspector Boiler Welding Supervisor
Project name: BMS Project<Power plant>
Client: BLCP/ESCO/ Turnaround Shutdown/ Rayong Thailand
Main Duties & Responsibilities:
ü Implementation of client approved quality plan
ü Prepare and participate in required audits during Execution and post with client
ü Take a lead role in quality system implementation and follow up.
ü Contractor side as per project specification client QA-QC. Procedures.
ü Responsible for all the quality forms/certificate’s job execution.
ü Follow up of quality plan for effective implementation.
ü Develop standard or specific technical quality checklists for all jobs to be execution in the Turnaround
ü Follow up of quality plan and reports daily status to client.
ü Control all technical checklists after the jobs have been completed.
ü Participation in the weekly construction meeting with responsive operations to highlight any quality related issue.
ü Set up meeting with sub-contractor quality responsible persons to ensure affective implementation of
Client approved quality plan and procedures.
ü Reviewed Material Mill Certificates/PQR/WPS/NDT/WQT method and procedure RT/MPI/PT/UT/PAUT
ü Apply material alloy steel SA213-T12/T22/Stainless steel SA312-TP347H/TP310H/SA387/
SA240-TP347H/SA335-P4/P5A
ü Inspection Boiler fabrication/Fit up/Welding/Visual/NDT Boiler Unit-1&2 area Economizer System/
Tertiary Superheater Tube and Water Wall Tube follow ITP/WPS used standards ASME-I and ASME B31.1
And apply standard EN 12952 for Water Tube Boilers and refer. ASME-I and ASME-II
EN 5817 for Welding-Fusion-welded joints in steel/nickel/titanium and alloys reference ASME-IX and I
EN 15614 for Welding procedure Qualification and reference ASME-IX and ASME-I and project spec require
ü EN 287-1 Qualification Test of Welders-Fusion welding-Part-1<WQT> and reference ASME-V and ASME-IX
And Inspection test RT/PT/MPI/PMI and UTM and Reviewed Boiler Test Package
Period from June-2018 to Aug-2018
Organization: TPC
Position: QC. Coordinator & Supervisor Welding/Piping/Mechanical inspector
Project name: VCM2 Project<Petrochemical plant>
Client: TPC/ Turnaround Shutdown/ Rayong Thailand
Main Duties & Responsibilities:
ü Implementation of client approved quality plan
ü Prepare and participate in required audits during Execution and post with client
ü Take a lead role in quality system implementation and follow up.
ü Contractor side as per project specification client QA-QC. Procedures.
ü Responsible for all the quality forms/certificate’s job execution.
ü Set up meeting with sub-contractor quality responsible persons to ensure affective implementation of
Client approved quality plan and procedures.
ü Reviewed Material Mill Certificates/PQR/WPS/NDT method and procedure RT/MPI/PT/UT/PAUT
ü Inspection fabrication and of piping spools follow ITP/WPS used standards and project specification.
ü Witness WQT follow ASME-Sec-IX and ASME-B31.3 Inspection ferrite test RT/PT/MPI/PMI
ü Inspections done as per the reviewed Piping Test Package, Inspection line check walks before hydro test.
ü Witness Hydro test/Cleaning/Flashing/Reinstated/Reviewed ensure Site queries, engineering
ü Clear list checked punch list, Review and approval of final document MDR.
Rotating Equipment Installation, Static Equipment Installation Inspection
ü Review Field Quality Plan corresponds to respective field works.
ü Review method statement, erection procedures and Inspection Test Plan (ITP).
ü Ensure latest revision drawings are being used at site and maintain As-built drawing for quality documentation
And submission to field engineering for verification.
ü Advised and Supervise to responsible in all static and rotating equipment due to installation and
Alignment Function key inspection as in transportation/installation/centering/levelling/alignment/
Grouting/bolt setting/bolt torque and etc. Prevision protects as rotate /corrosion prevent/
Packing condition/lubricant oil & grease and etc.
ü Alignment inspection of static equipment and rotating equipment such as Vertical Sulphur Pumps,
Vertical Sump Pumps, Horizontal Centrifugal Pumps/Heat Exchanger/Compressor
ü Preparation package all of Static equipment and Rotating Equipment Vertical Sump Pumps
Horizontal Centrifugal Pumps/Heat Exchanger/Compressor Cooling tower
ü Reviewed document and final MDR
Period from October-2016 to Nov-2017
Organization: MPS/MES Mitr Project Services
Position: Specialist Construction QC. Welding Supervisor/Piping Inspector
Project name: EX-22-24-G1 Project<Petrochemical plant>
Client: Shin Etsu Silicones/Thailand
Main Duties & Responsibilities:
ü Reviewed Material Mill Certificates/PQR/WPS/NDT method and procedure RT/MPI/PT/UT/PAUT
ü Inspection fabrication and of piping spools follow ITP/WPS used standards and project specification.
ü Witness WQT follow ASME-Sec-IX and ASME-B31.3 Inspection ferrite test RT/PT/MPI/PMI
ü Inspections done as per the reviewed Piping Test Package, Inspection line check walks before hydro test.
ü Witness Hydro test/Cleaning/Flashing/Reinstated/Reviewed ensure Site queries, engineering
ü Modification done, Review the As built drawings. Review package Check P&ID, drawing, certificate Equipment.
ü Clear list checked punch list, Review and approval of final document MDR.
Period from Sep-2013 to Dec-2015
Organization: Amec Foster Wheeler Thailand
Position: Specialist QC. Supervisor Welding/Piping/Sphere & Storage Tank/NDT.
Project name: UHV/IRPC-Project/Thailand<Refinery plant>
Client: IRPC/Thailand
Main Duties & Responsibilities:
ü Implementation of client approved quality plan
ü Prepare and participate in required audits during Execution and post with client
ü Take a lead role in quality system implementation and follow up.
ü Contractor side as per project specification client Procedures.
ü Responsible for all the quality forms/certificate’s job execution.
ü Follow up of quality plan for effective implementation.
ü Develop standard or specific technical quality checklists for all jobs to be execution in the Project.
ü Follow up of quality plan and reports daily status to client.
ü Control all technical checklists after the jobs have been completed.
ü Participation in the weekly construction meeting with responsive operations to highlight any quality related issue.
ü Set up meeting with sub-contractor quality responsible persons to ensure affective implementation of
Client approved quality plan and procedures.
ü Reviewed Material Mill Certificates/PQR/WPS/NDT method and procedure RT/MPI/PT/UT/PAUT
ü Inspection fabrication and of piping spools follow ITP, WPS, used standards and project specification.
ü Witness WQT follow ASME-Sec.-IX, and ASME-B31.3 for low alloy steel Gr.P9/P11/P22 Inspection PT/MPI/PMI
ü Inspections done as per the Piping Test Package/Inspection line check walks before hydro test
ü Witness Hydro test/Cleaning & Flashing/Reinstated. Reviewed ensure Site queries, engineering
ü Modification done, Review the As built drawings. Review package Check P&ID, drawing, certificate Equipment’s
ü Clear list checked punch list, Review and approval of final document MDR.
Control and management/Fabrication/Inspections/Storage Tank/Follow project specification & ITP
ü Reviewed Material received and inspection apply Carbon steel P1+P1 G1&G2 ASTM SA36/SA105/SA283 Gr.C/
SA333 Gr.11/SA350 Gr.LF1/SA516 Gr.60&70/SA672 Gr.C60 actual check and Identify reviewed
Material certificate Heat number accept criteria Apply ASME-II Part-A and Project specification required.
ü Review procedure NDE for RT/PAUT/MPI/PT/UT reference construction specification/ASME-V
ü Review & witness procedure PQR/WPS/welding consumables follow project specs/ASME-IX/API650/API620
ü Review report mechanical test carbon steel/post weld accept criteria follow standard API650/ASME-IX/VIII div.1
ü Witness WQT process FCAW/SMAW/SAW for welding qualified butt weld in plate and shall comply with
Follow standard ASME-IX/API-650 for storage tank
ü Coordinator and inspection review document requires of fabrication workshop & site NDT reports.
ü Inspection: Assemble/Fit up/Pre-heat before welding control/during welding/Post welding inspection/NDT-after
ü Review of welding record/Pressure test package preparation, review and approval
ü Reviewed Punch before pressure test and review and verification of punch clearing.
ü Witness of the pressure test/Reinstatement after pressure test
ü Visual inspection/Harness Test/Hydro Test acceptance criteria follow ASME-IX/API650/ASME-VIII div.1
ü Review and approval of final document MDR.
Period from Dec-2012 to July-2013
Organization: Noble Drilling/Singapore
Position: Specialist QC. Superintendent Structure Inspector/Welding/NDT
Project name: JU3000N <Jack-Up Rig Drilling Unit/Jurong-Singapore>
Client: Noble Drilling-Singapore/Thailand
Main Duties & Responsibilities:
ü Inspection fabrication fit-up/dimensions check assembly follows ITP, refer project spec. required
Standard ABS Rules IACS/AWS D1.1/ASTM/ASME Section: V<NDE>RT/PT/MPI/UT/PAUT
ü Inspection material verifies steel plate check, mill certificate review report follow standard ABS Rules
Grade A, B, D, and E, AH32&36, DH32&36, EH32&36
ü Review procedure NDE reference construction specification acceptant criteria qualification, ABS-Rules
ü Review & witness procedure PQR, WPS, welding consumables, follow project specs, standard ABS, AWS D1.1
ü Review report mechanical test carbon steel accept criteria follow standard ABS Rules, AWS D1.1
ü Witness WQT process SAW, SMAW; FCAW welding qualified butt weld in plate position 1G+3G+4G
Acceptance criteria follow standard / AWS D1.1
ü Visual inspection acceptance criteria follow standard ABS Rules / AWS D1.1
ü Check quality of weld MPI, UT and RT Inspection NDE report follow acceptance criteria standard ABS Rules
ü Coordinator and inspection review document requires of fabrication workshop & site NDT reports.
ü Supervise the subcontractor at site and the erection of steel structure
ü Review the received material packing list and check the ability of erection
ü Supervise the steel structure site modifications due to revised drawings and fabrication defect
ü Check the extra work done by subcontractor and sign the time sheet
ü Supervisor Check and solve the field construction technical query
ü Prepare daily and weekly erection status and all required reports
ü Prepare and follow up clearance of punch list.
ü Supervise and management for all of quality control & Review and approval of final document MDR.
Period from Sep-2012 to Nov-2012
Organization: Technip-Australia
Position: Specialist QC. Supervisor/Piping Supervisor/Structure/Welding/NDT
Project name: Macedon Gas Plant Projects<Fabrication/Inspection Module-GAS>
Client: Bhpbilliton-Australia/Thailand
Main Duties & Responsibilities:
ü Reviewed Material Mill Certificates/PQR/WPS/NDT method and procedure RT/MPI/PT/UT
ü Inspection fabrication and of piping spools follow ITP, WPS, used standards and project specification.
ü Witness WQT follow ASME-Sec-IX and ASME-B31.3 for low alloy steel Gr.P9/P11/P22/P91
ü Inspections done as per the piping test package/Inspection line check walks before hydro test
ü Witness Hydro test/Cleaning & Flashing/Reinstated. Reviewed ensure Site queries, engineering
ü Modification done, Review the As built drawings. Review package Check P&ID, drawing, certificate Equipment’s,
ü Clear list checked punch list, Review and approval of final document MDR.
Quality control and management/fabrication/Inspections/Structure steel/Follow project specification/ITP
ü Material received inspection, actual material check and marking, reviewed material certificate, Heat number
ü Inspection: Assemble/Fit up/Pre-welding control/during welding/Post welding inspection/NDT-after
Visual inspection apply AWS-D1.1
ü Supervise the subcontractor at site and the erection of steel structure
ü Supervise the steel structure site modifications due to revised drawings and fabrication defect
ü Supervisor Check and solve the field construction technical query
ü Prepare and follow up clearance of punch list.
ü Inspection: Welding repair/Before blasting & painting/Structure steel member part on site release/Foundation.
ü Inspection: Dimension control/Pre-assemble Unit lifting/Bolt & Torque/Painting application.
ü Review and approval of final document MDR.
Period from Apr-2012 to July-2012
Organization: Seadrill Distribution-Singapore
Position: Specialist Construction QC. Superintendent Structure/Welding/NDT
Project name: WEST LINUS Projects<Jack-Up Rig Drilling Unit/Jurong-Singapore>
Client: Seadrill-Singapore/Thailand
Main Duties & Responsibilities:
ü Inspection fabrication fit-up/dimensions check assembly follows ITP project spec. Ref. DNV-OS-C401
ü Inspection material verifies steel plate for special & primary, secondary at Yield stress 500 and above
Visual inspection/dimensions check, mill certificate review report follow offshore standard DNV-OS-C101
Grade NVE36, NVE500/AWS group I&II/NVA36/NVD500/NVD36/AH36/NVD500Z
ü Review procedure NDE reference construction specification acceptant criteria Ref. DNV-OS-C401/AWS D1.1
ü Review & witness procedure PQR/WPS welding follow offshore standard DNV-OS-C401/AWS D1.1
ü Review report mechanical test carbon steel accept criteria follow offshore standard DNV-OS-C401 section -1
ü Witness WQT process MMAW, FCAW welding qualified butt weld in plate position 2G+3G,
Cover all position acceptance criteria follow standard DNV-OS-C401-section.1/ AWS D1.1/SAW qualified-1G
ü Final visual inspection and testing acceptance criteria follow offshore standard DNV-OS-C401
ü Monitor PT, MPI, UT and RT Inspection NDE report follow acceptance criteria offshore standard DNV-OS-C401
ü Co-ordinator/inspection review document requires of fabrication workshop/site NDT reports. Form Contractor
ü Supervise the subcontractor at site and the erection of steel structure
ü Review the received material packing list and check the ability of erection
ü Supervise the steel structure site modifications due to revised drawings and fabrication defect
ü Check the extra work done by subcontractor and sign the time sheet
ü Supervisor Check and solve the field construction technical query
ü Prepare daily and weekly erection status and all required reports
ü Prepare and follow up clearance of punch list.
ü Supervise and management for all of quality control programs and system such as material, welding.
ü Visual & dimensional, Nondestructive testing ensure meet the project, review and approved MDR.
Period from Dec-2011 to Mar-2012
Organization: Samsung Engineering Thailand
Position: QC. Welding Supervisor Inspector LNG Storage Tank /NDT
Project name: PTT/LNG-Project/Thailand<LNG plant>
Client: PTT/LNG Thailand
Main Duties & Responsibilities:
ü Control and management/Fabrication/Inspections/LNG Storage Tank/ project specification & ITP
ü Material received inspection/actual check and marking/reviewed material certificate/Heat number
Apply ASME-II Part-A/B/C
ü Inspection/Fabrication Apply codes API-620/API-650/BS-7777<Part 2&4>ASME-IX and ASME VIII-Div.1
Used material low temperature ASTM A353 and A553<9% nickel>Range -51 to -168 C and
A240 type 304 stainless steel
ü The components for materials/Inner shell used Low temperature/Outer shell Low temperature.
Suspended deck plates and framing used Low temperature/Inner and Outer Bottom plates used Low
Temperature/Annular plates used Low temperature/Anchor straps used Low temperature.
Compression ring used Low temperature/Roof plates & Structure used common carbon steel material.
ü Review procedure NDE for RT/PAUT/MPI/PT/UT reference construction specification/ASME-V and
Accept standard for RT apply ASME-VIII Div.1 paragraph <UW-51<b>/UW-52>
Accept standard for MT apply ASME-VIII Div.1 paragraph <Appendix-6/paragraphs 6-3/6-4 and 6-5
Accept standard for PT apply ASME-VIII Div.1 paragraph <Appendix-8/paragraphs 8-3/8-4 and 8-5
Accept standard for Visual Examination apply API-620 Section 7.15.5.2 and 7.15.5.3
ü Reviewed procedure hydro test/Air test at bottom tank and roof apply API-620
ü Coordinator and inspection review document requires of fabrication workshop & site NDT reports.
ü Perform Quality Control inspections on fabricated
ü Supervise and management for all of quality control & Review and approval of final document MDR.
Period from Oct-2011 to Nov-2011
Organization: Foster Wheeler International
Position: Specialist QC. Welding Supervisor Inspector
Project name: Esso Refinery Sriracha Clean Fuels Project
Client: Esso-Refinery plant-Thailand
Main Duties & Responsibilities:
ü Reviewed Material Mill Certificates/PQR/WPS/NDT method and procedure RT/MPI/PT/UT/PAUT
ü Inspection fabrication and of piping spools follow