Ahmed Mohamed Shawky
*****-********@*******.***
6th of October Governorate, Sheikh Zayed
Qualifications:
Bachelors of Civil Engineering / 2001 - Cairo University.
Graduation project: reinforcement concrete
Grade: Very Good
Work Experience:
Mena Group for Contracting (2018-2020):
Project Manager Of (City Central Compound)
o Project (1): Mena City Central Compound / in Dokki – Giza
(19 High Rise Buildings + 3 basements allover project area) o Owner: Mena Group
o Main Consultant: A.C.G (Dr. Hassan Abde latif )
o Soil Mechanics & Dewatering Consultant :
Dr. Mohamed El Nabarawy & Dr. Hossam El Moghazy
o Project Cost: 1.60 Milliards L.E
Andalusia Group for Medical Services (2017- 2018): Regional Manager of Engineering Department
(Construction Projects &General Maintenance):
o Project (1): Antoniadis New Clinics – Semoha /Alexandria o Owner: Andalusia Group
o Consultant: Dar El Handasa (construction) &
Promep (Electro mechanic)
o Project Cost: 45 Million L.E
o Project (2): Maadi New Clinics - Maadi
o Owner: Andalusia Group
o Consultant: Dar El Handasa (construction) &
Promep (Electro mechanic)
o Project Cost: 38 Million L.E
-1-
o Project (3): New Extension 4th floor & Renovation of Andalusia Semoha Hospital – Alexandria
o Owner: Andalusia Group.
o Consultant: Dar El Handasa (construction) &
Promep (Electro mechanic)
o . Project Cost: 57 Million L.E
o Project (4): New firefighting system & Renovation of Andalusia Shlalat Hospital – Alexandria
o Owner: Andalusia Group.
o Consultant: Dar El Handasa (construction) &
Promep (Electro mechanic)
o Project Cost: 15.750 Million L.E
o Project (5): Renovation of Andalusia Hospital – Maady o Owner: Andalusia Group.
o Consultant: Dar El Handasa (construction) &
Promep (Electro mechanic)
o Project Cost: 42.50 Million L.E
Bedayah for Trading & Contracting (2011- 2017):
Regional Projects Manager:
o Project ( 1 ) :.Alfa Feed Factory
o Responsible of: All Civil, Finishing & Electromechanics work o Owner: Alfa Feed Company.
o Consultant: A - Half
o Project (2) : ABB Factory
o Responsible of: part of Project Stages/ Construction-Finishing Electro Mechanics-Networks …etc.
o Owner: ABB
o Consultant: ABB – Engineering Department
o Project (3): PVC Factory.
Responsible of: All Civil, Finishing & Electromechanics work o Owner: ALArabia united Group.
o Consultant: Dr. Haitham El Werdany
-2-
o Project (4): Victoria College Primary Buildings. o Responsible of: Construction-Finishing works. o Owner: Victoria Collage-Maadi.
o Consultant: General Authority for Educational Buildings. o Project (5): Alegria Compound – Sodic.
o Responsible of: Vella's Finishing works.
o Owner & Consultant: Sodic – 6th of October.
o Project (6): Palm Hills Compound.
o Responsible of: Zone C Roads & Finishing works.
o . Consultant: Owners
o Project (7) : Hilton Hotel / Zamalek
o Responsible of: All Project Stages/ Construction-Finishing Electro Mechanics-Networks …etc.
o . Owner: Hilton Hotel
o . Consultant: Moharam - Bakhoom
A.G Est. for Trading & Contracting (2007- 2011): Kingdom of Saudi Arabia
Regional Projects Manager:
o Project (1): Al Zahran Mall / Al-Khobar.
o Responsible of: All Civil works.
o Owner: Haifaa Al Gazira Company (Fawaz Al Hokeir). o Consultant: Haifaa Al Gazirah Company.
o Project Cost: 150 Million S.R
o Project (2): Al Khobar Convention Halls Center /Al-Khobar. o Responsible of: Construction civil works - Finishing works - Networks - Electromechanics. etc.
o Owner: Culture Ministry – Khobar Municipality.
o . Consultant: Khobar Municipality
o Project Cost: 45 Million S.R
-3-
o Project (3): Flood Protection Project -Maray Box Culvert. o Responsible of: Following up all the project stages, needs, subcontractors...etc
o Owner: Al-Kharj Municipality.
o Consultant: Al-Kharj Municipality.
o Project Cost: 14 Million S.R
o Project (4): Al Ehsaa Mall / Al Hofuf (Giant Store). o Responsible of: All Civil works.
o Owner: Haifaa Al Gazira Company (Fawaz Al Hokeir). o Consultant: Haifaa Al Gazirah Company.
o Project Cost: 190 Million S.R
o Technical & Contract Dept.:
o Responsible of: Studding projects tenders, price Quotations Time Schedules, follow up project's needs, schedules, subcontractors, project stages.
Prequalification with Aramco, Petro - Rabigh, STC. o Project (5): Flood Protection Project-Sinaa Box Culvert. o Responsible of: Following up all the project stages, needs, subcontractors...etc.
o Owner: Al-Kharj Municipality.
o Consultant: Al-Kharj Municipality.
o Project Cost: 28 Million S.R
o Project (6): Flood Protection Project (Pipe Lines of 1000mm) o Owner: Al-Kharj Municipality.
o Consultant: Al-Kharj Municipality.
o Project Cost: 26 Million S.R
o Project (7): Flood Protection Project (Pipe Lines of 1000mm) o Owner: Al-Kharj Municipality.
o Consultant: Al-Kharj Municipality.
o Project Cost: 24 Million S.R
o Project (8): Flood Protection Project Riyadh Box Culvert. o Owner: Al-Kharj Municipality.
o Consultant: Al-Kharj Municipality.
o Project Cost: 22 Million S.R
-4-
o Project (9): Omar Ebn ALkhatab School.
o Owner: Ministry of Education.
o Consultant: Al-Kharj Projects Dept. of the Ministry. o Project Cost: 21 Million S.R
o Project (10): Al-Jubail Military Building.
o Owner: Ministry of Defense.
o Consultant: Al-Jubail Projects Dept. of the Ministry of Defense. o Project Cost: 26 Million S.R
o Project (11): Renovation of Strategic Elevated water Tank. o Owner : Ministry Of Interior .
o Consultant: Projects Dept. of the Ministry of Interior. Project Cost: 23 Million S.R
Al Bannaoun Company (2006-2007):
Deputy Project Manager:
o Project (1): Safeir Hotel .
o Responsible of: Finishing works (GRC & GRP).
Owner: Safeir Hotels Group.
Consultant: Dr. sabour.
o Project (2): Dream Land Hotel
o Responsible of: Finishing works. (GRC & GRP).
o Owner: Dr. Ahmed Bahgat Group.
o . Consultant: A. Half Consultant
o Project (3): Dar El Mansoor Palace.
o Responsible of: Finishing works
o Owner: Minister of transportation / Mr. Mohamed Mansour o . Consultant: Orascom Company
o Project (4): A.U.C (American university in Cairo) New Compounds (In New Cairo).
o Responsible of: Finishing works (GRC & GRP).
Owner: (A.U.C) Department.
o Consultant :( A-G) Samsung & American Consultants.
-5-
C.R.C - DORRA GROUP (2005-2006):
Senior Construction Site Engineer:
o Project: Al khamaiel Compound
(Residential buildings / sheikh Zayed - 6th of October) o Responsible of: Construction work (Excavation, concrete works, finishing works, landscape) of 19 residential buildings o Owner: ministry of interior
o Consultant: A.A.W consultant (Dr. Ahmed Abd el wareth)
Arab Contractors Company (Osman Ahmed Osman)
(2002-2005) Bridges Department:
Construction Site Engineer:
o Project (1): Metro Station (Monieb /Giza)
o Responsible of: Civil works (excavation – Rft. Concrete) o Owner: National Authority of Metro.
o Consultant: The Arab consultant engineers (Moharam –Bakom) o Project (2): Essna additional lock and new Essna bridge o Responsible of: the diaphragm wall works around the lock – the excavation and concrete works of the new bridge
o owner: ministry of irrigation
o consultant: the Arab consultant engineers (Moharram – Bakom) o Project (3): Salah Salm cars tunnel (Al Oroba tunnel) o Responsible of: The Entrance of the tunnel (diaphragm wall works – excavations and concrete works)
o Owner: ministry of development, new communities housing and utilities
o Consultant: The Arab consultant engineers (Moharam –Bakom) o Project (4): .Luxor airport
o Responsible of: the finishing works in the new Terminal. o Owner: ministry of civil aviation
o Consultant: The Arab consultant engineers (Moharam –Bakom)
-6-
o Project (5): king Faisal cars tunnel (through pass) o Responsible of: the diaphragm wall works – excavation, concrete and finishing works
o Owner: ministry of development, new communities housing and utilities
o Consultant: The Arab consultant engineers (Moharam –Bakom) o Project (6): Hydrolice- Jacking Pipes of 1000mm (Maadi) o Responsible of: Civil works (excavation – hydro lice jacking) o Owner: Ministry of development, new communities housing and utilities
o Consultant: The Arab consultant engineers (Moharam –Bakom)
General Nile Company for Desert Roads (2001-2002) Construction Department:
Construction Site Engineer:
o Project: El Gafraa schools
o Responsible of: Excavation – Concrete skeleton – Finishing works – land Escape works
o O wner: Ministry of education
o Consultant: General department of educational buildings
Training Courses :
1. Project Management program (PMP) / (2020).
2. AutoCAD / Computiq Training Institution Graded: Excellent. 3. Methods of Constructing & Repairing Bridges / The General Training Institution for roads &bridges. Graded: V. good. 4. Training program for all partitions of Civil Engineering Part (1): (12/2002) Graded: 95% Excellent.
Part (2): (4/2003) Graded: 90% Excellent.
(ITM) Arab Contractors Company (Osman Ahmed Osman)
-7-
Personal Skills :
o Dynamic, results–oriented leader, with strong track record of performance in turn around projects & high-paced & complex Organization structure.
o Recognized as a rapid, effective decision taker. I utilize keen analysis and insights and team approach to drive organizational improvements and implementation of best practices. o Characterized as a visionary and tactician, consistent record of delivering challenging results in growth, revenue, operational performance, and profitability.
o Possessing heavy transaction background including mergers and acquisitions, participated in high level operational intimates including infrastructure designing, process reengineering, turnaround management, and reorganization.
o Additional areas of Expertise include: Strategy planning, managing start-ups.
o Capable of resolving multiple & complex issues (operational, technical, sales, human resources, Legal & financial) o Motivating staff to peak high performance, guiding them towards achievement.
o Capacity building & performance improvement.
Computer Skills :
o Excellent Knowledge in Microsoft Office (Excel, Word ...etc.) o AutoCAD.
o Primavera.
Language Skills :
o Excellent command of both written & spoken English language
-8-