SUMMARY
Senior construction management professional with an in-depth understanding of team-building, planning, and execution, and the management processes required to successfully produce any deliverable. Focused on quality, schedule adherence, and cost control. Construction expert in-house legal counsel, constructability, design coordination, quality, safety and efficient project closeout.
20 years experience recruiting, mentoring, managing and leading construction management teams
Create and execute P6 schedules
Manage construction portfolios of up to 5 projects in excess of $1.2B USD
Direct management of 35 - 150 construction professionals
Oversee construction programs with 2,000 to 12,700 workers
Willing to travel
EDUCATION
Hamilton College, Clinton, NY B.A. Liberal Arts - specialized in Accounting, Teaching, History
LICENSES/CERTIFICATIONS
Florida Certified General Contractor
Florida Certified Home Inspector
Florida Certified Roofing Contractor
OSHA HAZWOPER, OSHA 30, Heavy Equip, Confined Space, First Aid
Mass. Super Unlimited License
PMP Certification from PMI #2078166
SOFTWARE/SYSTEMS
USACE Audits
P6 Project Scheduling
LEED Compliance
Project Management
WORK EXPERIENCE
2019 Executive Consultant Roman Structures Wellington, FL
Legal advisor
Construction industry claims resolution
2018 Vice President Cortland-Multi-Family Builder New Construction Atlanta, GA
7 projects at $40M each, 7 Precast Parking Garages Design through Execution
Created process for constructability reviews with design professionals
Established quality specification and material requirements
Directed QC department, hired and trained staff to execute the QC inspection process
Interacted with all new construction Execution teams
Created a Safety Department for new construction
100% travel
Managed the process from Design through Execution and Commissioning
2016 - 2018 Vice President Saudi Aramco-Azmeel Dammam, KSA
266 Executive Houses $225M
Brought in to salvage residential fast track project in Saudi Aramco
Directed 150 engineers of various disciplines with 2,700 labor workforce
Contract required 6 work days at 10 hrs. per day / 2 weeks of vacation every 6 months
266 Precast and Tilt/Up walls, floors, stairs, roofs with built in utilities
Managed Design Through Execution including Total Site Development, Roads, Utilities
2015 - 2016 Vice President of Operations Mid-Size Estate Builder Alonso Palm Beach, FL
Palm Beach Mansion $32M
Direction and coordination for 4 Project Managers
Streamlined corporate communications
Resolved procurement challenges
2013 - 2015 Project Executive Parsons Corp Yanbu Al-Sinayah, KSA
Public High Rise Structure $225M Royal Commmission HQ/ Governor Offices
30-Story 335’ high 660,000 sf Class A office multi-tower with 3-level parking, 18 elevators, and level 5 interiors
Recruited and trained subject matter experts and field staff of 35
Extreme temperatures, extreme structure
LEED certification
A&E Design/Build, P6 schedule management
Procurement and deliverable deadlines
QA/QC program creation and execution
Total Site Development and Infrastructure
Cast pilings (1850 x 40” x 120 ft.) and heavy foundation
(5000 cy placements weekly at foundation level x 10)
Contract required 6 work days at 10 hrs. per day
Royal commission Authorized Representative (special appointment by the Governor, His Excellency)
2011 - 2013 Senior Project Director USACE-ACI Afghanistan (Helmand Province)
Afghan National Army Base U.S. Army Corps of Engineers $40M
36 buildings and underground utilities in the active war zone
Extreme temps, world-wide workforces, dangerous supply & logistics
Total Site Development and UG Utilities/Design Build
A&E Design/Build management of 3 Prime Contractors and 1,100-man work force
The contract required 6 work days at 12 hrs. per day/ 2 weeks of vacation every 6 months
2004 - 2011 Prime Contractor Roman Structures Jupiter, FL
Jupiter Marina $40M
100% Rehab of seawalls, docks, and site utilities
3 Storage Buildings with 4 story racks for yacht storage
Remediation of hazardous waste spill utilizing 3 options
“Air Sparge”, Microbes, Land farm
A&E Design/Build management
1,500 auger-cast pilings and heavy foundation
Palm Beach Hotel $80M
Major rehab and addition to the hotel included hazardous waste cleanup
100,000 sf new/rehab
60-unit boutique hotel, level 5 finishes
AA&E Design/Build management
Cooling towers, extensive MEP
Restaurant kitchens, major utilities, FF&E
Manalapan Mansion $42M
42,000 sf mansion spanning from the ocean to the intracoastal
A&E Design/Build management
Re-zoning challenges, high-end (class 5) finishes
Major utility and infrastructure - buried HV lines
4-story, extremely difficult concrete structure, emergency back-up power, cooling towers, design on the fly
3 elevators, 500 auger-cast pilings, seawalls, docks, level 5 finishes
REFERENCES
Provided upon request