PP. Venugopalan

PETROFAC INTERNATIONAL LTD

Post Box-23467

Sharjah

United Arab Emirates (UAE)

Mobile : +971-**-*******

aden6t@r.postjobfree.com

To,

The HR Manager

Subject: Application for the post of PRINCIPAL DESIGNER - ELECTRICAL Dear Sir,

Having 31 years of experience in EPC projects and detail design jobs such as Proposals, Detail Engineering and Field Engineering for Onshore and Offshore Oil and Gas field and Petrochemical fields. Up to April 2020 working in Petrofac International Ltd. Sharjah (UAE). I have an extensive experience of preparing drawings and documents, Inter discipline co- ordination (IDC), Reviewing drawings, Layouts & documents, Scheduling, Man power estimate, Mentoring group of Designers in the office and satellite offices, Model review with other disciplines (Internal) and Model review with Client for 30%, 60% and 90%, Review of bulk material (Vendor drawings) and Subcontractor Drawings & Documents, Co-ordination for As- Built documentation work in project site.

I am working in Engineering office during detail Engineering stage and working in site as a Field Engineer for Construction activities for Aramco, Kuwait Oil Company, Qatar Petroleum, BP Khazzan, Oman, PDO project site and Co-ordinate with Sub contractor activities. Well versed with international standards such as IEEE, BS, NEMA, Shell DEP standards, ARAMCO, PDO, ADNOC, GASCO, QP, OXY & TOTAL standards etc. I have worked with Oil & Gas Client Projects, Saudi Arabian Oil Company (ARAMCO), Abudhabi National Oil Co. (ADNOC), British Petroleum (BP), Kuwait Oil Company (KOC), Kuwait Petroleum Development Oman (PDO), Qatar Petroleum (QP), OXY Qatar, Brunei Shell Petroleum (BSP), Brunei LNG (BLNG) and Kuwait Oil Company (KOC). Attached please find my resume which are self-explanatory. Thanks and Regards,

(PP. Venugopalan)

Page 2 of 7

POSITION : PRINCIPAL DESIGNER - ELECTRICAL

N A M E : PP. VENUGOPALAN

PASS PORT NO. : Z3725602 Valid up to 2027

PRESENT ADDRESS : PETROFAC INTERNATIONAL LTD.

Post Box.-23467

Sharjah,

United Arab Emirates (UAE)

PERMANENT ADDRESS : Parambai, Alencode P.O

Neyyoor, Kanyakuamri Dist.

Tamil Nadu, India-629802

CONTACT Tel./Email : 009**-**-******* / aden6t@r.postjobfree.com TELEPHONE (India) : 0091 948-***-**** (India)

NATIONALITY : INDIAN

MARITAL STATUS : MARRIED

DRIVING : UAE Driving License

DATE OF BIRTH : 20 MARCH 1967

EDUCATION

1986 : Diplomo in Electrical Engineering

: AUTOCAD-2018, MicrostationV8, SPR, NAVIS

MS Office

WORK EXPERIENCES : 31 Years

Nov. 2008 to Apr 2020 : PETROFAC INTERNATIONAL LTD., SHARJAH, UAE

Oct. 2005 to Nov.2008 : ELECTROWATT-EKONO(B) Sdn Bhd., BRUNEI DARUSSALAM (BSP & BLNG Jobs)

(Feb-Dec’07 Seconded to) : FOSTER WHEELER Brunei (BLNG Jobs) Jan. 2005 to Oct. 2005 : TECHNIP MIDDLE EAST, QATAR, (QP & OXY jobs) Nov. 1998 to Jan. 2005 : ELECTROWATT ENGINEERING., MUSCAT, OMAN

(PETROLIUM DEVELOPMENT OMAN Jobs)

Sep. 1993 to Nov. 1998 : DAR AL-RIYADH CONSULTANTS LTD. AL-KHOBAR, SAUDI ARABIA (ARAMCO Jobs)

Aug, 1988 to Sep. 1993 : M.N. DASTUR & CO. LTD. (Consulting Engineers) Chennai, India

Jun. 1987 to Aug. 1988 : COROMANDEL STEELS LTD.

Chennai, India

Jun. 1986 to Jun. 1987 : RICHARDSON & CRUDAS LTD.

Chennai, India

Page 3 of 7

WORK EXPERIENCE:

November 2008 – Apr 2020 : PETROFAC INTERNATIONAL LTD. Sharjah, UAE Principal Designer - Electrical

Worked as a Principal Designer/field Engineer for Proposals, Conceptual and Detail Engineering Projects for Oil and Gas, Petrochemical field in various jobs of Saudi Aramco, Abudhabi National Oil Co., Qatar Petroleum, Zakum Oil Field development Company (ZADCO), Kuwait Oil Company, Kuwait National Petroleum Co., Petroleum Development Oman project for various projects. Job involves to preparation of BOQ estimation for Tender Submission, Scheduling, Planning, Model review with other discipline (Internal) and Client 30%, 60% and 90% and distributing works and Mentoring Designers, Lighting Calculation, Preparing and Checking Electrical drawings for HV, LV, UPS, Lighting/Heat Tracing SLD’s, Cable Trench/Tray, Lighting, Earthing, Heat Tracing, Cathodic protection layouts and Cable Schedule. Review of construction drawings and Sub Contractor drawings/documents Preparing of Technical Spec. for DB’s, Tray, Lighting Fixture, Poles and Bulk materials, Bulk materials request and Review of vendor dwg. Such as JB’s, Power & Convenience Sockets, Lighting fixtures, Poles etc. Co-ordination with Client Engineering, Operation dept. and Sub contractor for building works such as substations, Control buildings and operation building workConstruction Drawing As-built works etc. List of job is detailed as below: a) Project: Qusahwira Onshore Brown Field Project (EPC) Client: Abudhabi National Oil Co. (ADNOC), Abu Dhabi, UAE b) Project: Majnoon Field Development Project, Central Processing Facility Ph-2 (EPC) Client: Shell Iraq, Iraq

c) Project: Jazan Refinery & Marine Terminal Project (EPC) Client: Saudi Aramco, Saudi Arabia

d) Project: Clean Fuels Project (EPC), Mina Abdullah Refinery Client: Kuwait National Petroleum Company (KNPC), Kuwait e) Project: Upper Zakum field development Project (EPC) Client: Zakum Offshore development Co. (ZADCO), Abu Dhabi, UAE f) Project: Central Processing Facility (CPF) in Khazzan Oil field, Oman (EPC) Client: British Petroleum Company (BP), UK

g) Project: Rabab Harweel Project, Oman (EPC)

Client: Petroleum Development Oman (PDO)

h) Project: Effluent Water Injection Phase-I & Sea Water Injection Phase-II (EPC) Client: Kuwait Oil Company (KOC), Kuwait

i) Project: Acid Gas Removal at Dukhan (AGRP)

& NGL-1&3, Gas Sweetening Facilities, Messaieed (SRU) (EPC) Client: Qatar Petroleum (QP) Qatar

j) Project: Karan Utilities and Co-Generation Project (EPC) Client: Saudi Aramco, Saudi Arabia

October 2005 – Nov. 2008 : ELECTROWATT EKONO (B) Sdn. Bhd. (POYRY)

(Feb’07 to Dec’07 Brunei Darussalam

Seconded to Foster Wheeler) Lead Designer Electrical Worked as a Lead designer for various Conceptual and Detail design Projects for Brunei Shell Petroleum and Brunei LNG plant. Co-Ordinate with Client for site survey, discussion and Subcontractor Dwg./document review, Material request, As-built preparation and preparation of Job Estimation to the client, Planning, Checking of Electrical drawings, LTG. Calculation, distributing works and Mentoring designers, Preparing Technical Page 4 of 7

specification for DB’s, bulk materials, Bulk material requests & Review of vendor doc. for bulk Materials, Ltg. fixtures & JB’s, Ltg. poles. HV&LV SLD, Cable trench/Tray, Lighting, Earthing layouts, Cathodic Protection layout, Cable schedule & Materials requests, SAP entry to the electrical material etc., List of job is detailed as below:

Emulsion Pumps installation in Train 1 & 2 for Seria Crude Oil Terminal (DD) : New 3 nos. 75kW Emulsion pumps installing in train 1&2. New LV switchgear compartment install in existing LV SWBD. in substation-5, revising of 415V SLD, Motor Inter connection Diagram, Equipment layout etc. Maersk RIG Feed Pump installation (DD) :

New feed pump installing for Centrifuge pump skid in B level deck. Using space feeder in 440V LV SWBD & Revising equipment layout, interconnection diagram etc. BLNG Power Plant & Cooling Water Renuvenjation Proj. (DD) (Seconded to Foster Wheeler): New switchgear bldg. cable routing & tray arrangement and new 33kV, 11kV GIS & 415,240,110V panels Installation, New FAR control bldg. for Total Electrical Network Monitoring Control System (ENMC) arrangement and installation. Vendor dwg (ABB,Simens,GE). review of Inter connection, Schematic Diagram & Cable Schedule. Extn. of LV panels, I/O cabinets & RTU’s and 33kV,11kV,415V,240V,110V SLD’s, Schematic Diagram for Swgr. bldgs.,GTG & STG and other areas. Champion-7 platform Fire Water upgrade Project (DD) : Installing new 185kW fire water pump in CPEP-7 platform, 2 X 75kW jockey pumps in CPWA Platform and 254V AC supply for fire water pump Control Panel P-700, Installing new Battrey Charger and DB CPLQ-7, 254V AC power supply to the battery charger in CPLQ-7 and lighting, junction box and DB relocated in CPEP platform extension area. Overall Modification of LV Switchboards, Installing new control panel for fire water and Jockey Pumps etc.

SEWJ-19 platform Solar Power System upgrade Project in (DD) : For SEWJ-19 installing new solar power system installed on existing drilling platform powered to RTU and Down hole monitoring system for new oil wells, Installing new solar control panel and battery arrangement etc. BLNG Instrument Air Compressor K-5711 Project (DD) : Installing new LV vertical panel in existing LV switchgear space in switch house no. 1 for powering to new instrument air compressor K-5711 related works etc. BLNG BOG Compressor Project (DD) :

For BLNG installing new 1.5MW Compressor, Modification of 11kV spare feeder in existing 11kV Switchboard SLD, Schematic Diagram, Block Diagram etc. Harmonic Filter Design Panel & Power Factor Panel Upgrading in AMPA-6 Platform (DD) : Installing Two new Harmonic Filter Panels in Ampa-6 platform for existing 440V switchboard. Installing new 440V withdrawable units for the incoming supply of Harmonic Filters and Upgrading the Power Factor Panel in AMPA-9 For Lube Oil Pump Motors and Seal Oil Pump Motors SLD, Block Diagram, Eqpt. layout, Cable schedule & MTO etc.

Integrated Gas Terminal (IGT) Project in BLNG/BSP (FEED) : Installing a new 2X500kVA Transformer and LV Switchgear in new containerised control room for powering to new motors, UPS, 24V DCDB, Lighting DB, Instrument panel supply and other power supplies, the incoming supply for transformers from SWH-14. single line diagrams for Switch house no. 14 (BLNG), Main LV SLD, 24V DC, 240V AC, Utility data sheet, Over all Plot plan, Equipment layout for containerised substation and overall and containerised control building & MR etc. Fiscal Metering station (FMS) Project in BLNG/BSP (Conceptual) : Installing a new LV Switchgear in new containerised control room for powering to new motors, UPS, 48V DCDB, Instrument panel supply, Lighting DB and other power supplies, the incoming supply for transformers from DEB. Main single line diagrams, Utility data sheet, Over all Plot plan, Equipment layout for substation layout for overall and containerised control building & MR etc.

JAN. 2005 TO OCT. 2005 : TECHNIP MIDDLE EAST, QATAR POSITION : Senior Designer Electrical

Page 5 of 7

1. Worked on the various Frontend design (FEED) and Detail design (DD) Projects for QATAR Petroleum

& OXY. Job involves Site Engineering support to subcontractor, Preparation for as built drawings/documents and preparation of Electrical drawings & Documents. List of job is detailed as below:

a) CLUSTER-1,2 & 3 (DD) : For Dukhan field 3 New 33kV/415V Substation Switch Room, Transf. Room, 33kV, 415V & 110V SLD, Block diagram, Motor Inter connection Diagram, Eqpt. layout, Cable trench,Cable routing, Earthing, Cable schedule & MTO etc. b) ZIKREET 33kV S/S (DD) : Exist. 33kV OHL modification and New 33kv Substation Switch Room, Transf. Room, 33kV, 110V SLD, Eqpt. layout, Cable trench, Cable routing, Earthing, Cable schedule & MTO etc.

c) CONTROL BUILDING (DD) : New Multi storied Control building located at Halul Island for Qatar Petroleum, OXY & Total for new 415V Switch board incoming supply from Exist. 33/415V S/S, Extn. Of exist. 415V switchgear room, for new control bldg. LV, 110V, AC UPS SLD, Electrical & HVAC Eqpt. Room Layout, Battery room Layout, New command center & Radio room Layout, Lighting, Small power layout, Earthing, Lightning Protection, Cable Trench, Power Cable routing Layout, Cable schedule and MTO etc.

d) PS-1 OFFSHORE ESP Installation (DD) : HV SLD, Block diagram, Cable routing in existing ladder on main deck, Sub Sea Cable routing to main switch room to new ESP locations in near by Exist. Platforms, Cable schedule, and MTO etc.

NOV. 1998 TO JAN. 2005 : ELECTROWATT ENGINEERING., MUSCAT, OMAN POSITION : Senior Designer Electrical

2. Worked on the various Detail design(DD) Projects for Petroleum Development Oman (PDO). Job involves Construction Site Engineering support to sub contractor, preparation as built drawings/documents and preparation of Electrical drawings & Documents in Engineering office. List of job is detailed as below: a) YIBAL & AL-HUWAISAH OHL(DD): 33kV Over head lines routing for ring system, pole configuration, MTO, Over head line profile, OHL Route for Oil well’s. Oil Wells ESP hook Ups, layouts & Yibal-A,B,C,D Gathering Stn. to Yibal Power station OHL Inter connection etc. b) Yibal 10.4MW Solar Compressor Auxiliaries: HV&LV SLD, New LV Panel Installation, Motor Inter connection Diagram, Eqpt., Cable,Trench, Earthing layout for Switch room &comp. Area etc. c) YIBAL WATER INJECTION PROJ. (DD) : HV & LV SLD, Existing HV,LV Panel Extn., HV

(6.6kV) LV motor Inter connection Diagrams, Pump house extesion, Cable trench, Cable routing, Earthing, Equipment, Lighting Layouts, Cable Schedule & MTO etc. d) SUWAIHAT LP FLARE For Blower Installation (DD) : SLD, Dual&single speed motor Inter connection Diagram, Switch Room Modification, LP Flare & Blower area Eqpt. layout, LV Switch room to Blower area Cable trench,Cable routing, Earthing, Cable schedule & MTO etc. e) AL-HUWAISAH Switch Room Modification(DD): 6.6kV,415V,110V SLDs, HV, LV Panel Extn. New UPS System installation, Battery room, Switch room, Control room modification, HV & LV motor Interconnection diagram modifications, MTO & Cable schedule etc. f) RIMA DEEP WATER DISPOSAL(FED&DD): 33kV OHL feeding 2x5000kW Motor Primary(33kV) & Secondary SLD, 33kV Switchrack Elev.&Section, HV(11kV) & LV motor intercnnection diagrams, Scada I/O list, Switch room, Cotrol room & DWD pump area overall layout for Eqpt., Cable trench, Cable Routing, Earting, lighting layout, Cable schedule & MTO. g) Nimir,Yibal,Bhaja,Rima area Oil wells Cathodic protection (DD): SLD, Equipment layout, Cable, Cable Trench, Earthing layout to CP Stns. & details for Single & double rectifier units. h) Zauliyah, Wafra &Al-Huwaisah water injection& ESP Well Hook-Ups(DD): HV&LV SLD, Pump house & VSD panel room layout, Transformer & Pump house area, Equipment,Cable Trench, Earthing layout, Cable schedule & MTO etc. Existing Gas lifted wells converted to Elctrified wells. (ESP well) Hook-Up's For SLD, Cable,Trench,earthing layouts for various araes in Yibal, Al-Huwaisah,Bhaja. i) Chemical injection & Demulsifier skids: LV SLD, Motor intercnnection diagrams, Equipment, Cable,Trench, Earthing, Cable schedule & MTO etc.

j) ZAULIYAH ELECTRIFICATION(FED & DD): HV(33/11kV),LV&110V DC SLD, Anzuz-Zauliyah 33kV OHL routing(60km), 33kV Switch Rack plan, Elev. & Sections, Switch room & Control room layout, Anzuz Switch rack modification, Scada I/O list, Cable routing etc. Page 6 of 7

k) Yibal Greenfield Proj.(DD): Installation of 2 Production Separators for Oil/Water Transfer Pumps

(3x90kW), Water Transfer Pumps (4x110kW), Aux. Motors, MSV Skids & A3 Switch room for HV &LV SLD, Motor Inter connection Diagrams, Wiring Diagrams, Cable trench, Cable routing, Earthing, Equipment, Lighting Layouts, Cable Schedule & MTO etc. l) Nimr Large FWKO Proj.(DD): HV(33&6.6kV), LV&110V DC SLD, Adding 2 nos. of 33kV panel, 2 Transformer & VSD Panels to Emulsion Pumps & 8 nos. 22kW for Drain vessel pumps. Motor Inter connection Diagrams, Cable trench, Cable routing, Earthing, Equipment, Lighting Layouts, Cable Schedule

& MTO etc.

m) Harweel Oil Field Developments (132kV S/S & Prod. Stn.(FED): New two 132kV OHL from Marmul & Haima west to New 132kV Switch yard, 11-132/11kV Tfrs. For Gas Plant & 132kV Substation Power to Main Oil Pant & Gas Injection Plant, 33kV GIS Switch room, C&R Pnls, Scada, F.O. Pnls, HV(132, 33 & 6.6kV), LV&110V, 48V DC SLD, Adding Scada, F.O., C&R Pnl.& 132kV Switch yard Extn. In Exist. Marmul & Haima west.. 4x1.2MW Oil Export pumps in Marmul Prod. Stn. For New OHL from 33kV GIS in Haima west to 33kV Sw.rack For 33/6.9kV Unit Tfrs.,33/415kV For LV board & CCR. SLD’s Layouts, etc. (Electrical Distribution by Electrowatt & Process By AMEC UK) n) Marmul Central Devlopment(FED): New 1.2MW Compressor unit, New LV Switch room, 2 seperator units, 6x1MW Pumps fed from 6.6kV Sw.Room, 6.6kV Extn. 13 MSV’s at Marmul Gath. Stns. A,B,C&G. SLD’s, Over all, Eqpt. & Switch room layout, Etc.

o) Al-Khalata Water Injection(FED): New 33kV Pnl. installed in Marmul 132kV S/S and OHL to 33kV Switch rack in Al-Khalata, New 6.6kV Substn. 2x16/20MVA Tfr. Fed to 6.6kV Sw.gear for 6x2MW Water Inj. pumps, 2x1250kVA Tfr. Fed to New LV Switch board. HV, LV&DC SLD’s, Over all Layouts, Eqpt. Layout & Switch room layout, Pump Layout Etc.

Sep. 1993 TO Nov. 1998 : DAR AL-RIYADH CONSULTANTS AL-KHOBAR, KSA

POSITION : Designer Electrical

Duties & Responsibilities:

Preparation of FEED & DD Electrical drawings for Saudi Aramco’s Projects for Sedgum Gas Oil Separation Project, Rastanura Refinery Upgrading Proj. Saudi Aramco Shell Refinery Projects. Kero Max project. Expansion & upgrading of Production stations, Substations & Switch yard areas, and Existing CCR modifications, Plant modifications and Gathering Stations works in Aramco’s Oil Fields, And expansion of Various Projects for Saudi Aramco & Petrochemical company’s in Saudi Arabia, such as: a. Key one line and single line diagrams

b. Motor schematic diagrams and wiring diagrams

c. Signal diagrams, Motor Inter connection Diagrams d. Plant lighting and Power wiring, Cable trench layout & sections, Bill of materials e. Substation layout, underground cable layout, cable tray arrangement & sections f. Equipment & Control Room Layout Modifications, Switchgear room layouts and sections, Power distribution area layouts, switch yard Modifications, plant general layout etc.

Aug. 1988 to Sep. 1993 : M.N. DASTUR & CO. LTD.

Chennai, India

POSITION : Senior Draftsman Electrical

Duties & Responsibilities:

1 Preparation of all types of Electrical drawings for various projects such as: a. HV & LV Single line diagrams, Wiring diagrams and Motor schematic diagram. b. Inter-plant cabling, cable trench details, cable schedules and Bill of materials. c. Plant lighting, earthing, power wiring, switchgear room layout, control room layout, main receiving substation layout plant general layout, etc.

d. For administrative buildings, power plant and blower house, turbo generator building, blast furnace, steel meltshops, light and medium merchant mill, coke oven by-product plant, air separation plant, cold and hot rolling mill, etc.

e. Preparation of motor schematic, Panel board wiring diagrams, block diagrams, etc. 2. Worked on the following projects:

a. COMINCO BINANI ZINC LTD. e. J.K. INDUSTRIES LTD. b. SALEM STEEL PLANT f. KUDREMUKH IRON ORE CO. LTD. c. COCHIN MINERALS & RUTILE LTD. g. SOUTHERN IRON & STEEL CO. LTD. Page 7 of 7

d. PRAKASH INDUSTRIES LTD. h . TAMILNADU MAGNESITE LTD.

June 1987 to Aug. 1988 : CORROMANDEL STEELS LTD., Chennai, India POSITION : Draftsman Electrical

Duties & Responsibilities:

1. Preparation of Electrical drawings for various projects: a. HV & LV Single line diagrams, Cable trench & Power cable routing, Earthing layout, plant general layout, Cable Tray arrangement and sectons, Equipment layouts, Switch gear room and panel board arrangements, cable schedules and bill of materials for various projects.

June 1986 to June 1987

COMPANY : RICHARDSON & CRUDDAS LTD., Chennai, India POSITION : Draftsman Electrical

Duties & Responsibilities:

1. Preparation of Electrical detail drawings for Visakhaptnam Steel Plant and Kerala News Print Project. Chemical Pants etc.

a. HV & LV Single line diagrams, Power & Trench layout, Earthing layout, Bill of materials etc. Pump house layout, chiller plant layout and arrangements, water treatment plant Equipment layouts, Routing, Earthing, switch Room layouts & bill of materials, etc.