Post Job Free

Resume

Sign in

Instrumentation And Control Specialist

Location:
Houston, TX
Posted:
July 08, 2020

Contact this candidate

Resume:

Ognjen Sucur

Instrumentation And Control Specialist

Address: ***** ********* ******* ***, ************, Louisiana, 70769

Phone: 713-***-****

E-mail adefwl@r.postjobfree.com

LinkedIn https://www.linkedin.com/in/ognjen-sucur-270941ab

Industrial Instrumentation & Controls Technician

Maintenance/Turnaround Professional

Dedicated Instrumentation Technician with 12+ years of experience of calibration, install and repair of instrumentation. Disciplined and hardworking team player with proven history of fast and detail-oriented work.

Experience includes troubleshooting, diagnostics and service on diverse instrumentation. Able to configure components for optimal performance. Talented repairer with an organized and systematic approach.

Skills

Strong written and verbal communication skills

Excellent

Dependable and reliable

Excellent

Safety knowledge

Excellent

Strong team player

Excellent

Documentation

Excellent

Calibration

Excellent

Testing and troubleshooting

Excellent

Work History

2019-08 - 2019-12

I&C Specialist

Stronghold, Cheyenne, Wyoming

Complete site Shutdown, Turnaround and Startup

Removed old and damaged instruments

Calibrated new and old instrumentation before installation or while in service

Completed tear-down of existing structures and prepared for new construction

Maintained positive relationships with all customers

Installed, aligned, and tested new equipment

2019-04 - 2019-06

I&C Specialist

Emerson, Memphis, Tennessee

Log in the Valero network, to get P&ID's, Location Drawings and Specification Sheets to print out in the office

Review documentation and location before heading out to the field

Inspect, Verify and Calibrate all AMS Instrumentation with a Fluke 754 according to specification sheet

Download and save all instrumentation specifications to the Fluke 754

Upload all data connecting Fluke 754 to computer that is connected on Valero's Network

Document Pass or Fail after upload

2019-01 - 2019-03

I&C Specialist

Marathon Oil, Malabo, Africa, Equatorial Guinea

Use P&ID's, Location Drawing and Specification Sheets

Disconnected GE Bently Nevada

Reconnected GE Bently Nevada

Verify all GE Bently Nevada connections for proper communication, calibration inside the DCS as well as inside the control room

Four GE Frame 5 Turbines turnaround

2018-01

I&E Technician

Turner Industries

Use P&ID's, Location Drawing and Specification Sheets

Log in network for updated Specification Sheets, P&ID and Location Drawings to print out in the office

Responsible for installation, calibration and testing of all instrumentation

2017-01

Marathon, I&C Commissioning & Startup Technician

Texas City, Texas

Use P&ID's, Location Drawing and Specification Sheets

Check and Inspect all Instrumentation and Controls after installation

Verify Calibration and specifications

Go inside operations building to plan all job tasks and to properly verify functionality and specifications of all instrumentation/controls

2016-06 - 2016-10

Commissioning & Startup Technician

CF Industries, Sioux City, Iowa

Build P&ID's, Location Drawing and Specification Sheets using the computer. For the new addition to the plant. Everything done according to CF Industries specifications.

Log in CF Industries network, update all new data.

Print all documentation for the specific instrument or loop at the commissioning office

Build a folder with all printed documentation and specifications for the particular instrument or loop at the commissioning office

Communicate with CF Industries personnel on which folders are finished

Check and Inspect all Instrumentation and Controls after installation

Verify Calibration and specifications

Check vibration transducers & RTD thermocouples for proper installation and connections on steam turbine generators (G.E 7Fa)

Test functionality of all controls, trips, fails of turbine

Sign off paperwork that everything is tested and ready

2016-01 - 2016-05

Commissioning & Startup Technician

CVR Entergy, Coffeyville, Kansas

Use P&ID's, Location Drawing and Specification Sheets

Responsible for location, tagging, pulling instruments from the field

Calibrating all instrumentation removed from the field in our calibration office

Returning and loop-checking all instruments pulled while in contact with operations, including some on the spot calibrations as needed

2015-08 - 2015-11

Lead I/C Commissioning Engineer

Calumet, San Antonio, Texas

Use P&ID's, Location Drawing and Specification Sheets

Expansion project with all Fieldbus instrumentation

Log in the Fieldbus control computer to function check connections and communication with specific instruments

Responsible for all connections of fieldbus leading to the brick and instrumentation

Checking all specifications downloaded into the instrument

Function checking all work done

2015-05 - 2015-07

I&C Commissioning & Startup Technician

LEPA Power Plant, Morgan City, LA

LEPA Power Plant Start Up and Commissioning

Performed pre-commissioning inspections of instrumentation systems to insure client specifications are met prior to system acceptance from construction on GE LM6000 Gas Turbine Generator and the Siemens Steam Turbine Generator

Maintenance and commissioning in systems such as potable water, High pressure and low pressure systems, boiler feed water, Chemical Feed, Fuel Gas, Steam Turbine generator, Cold Circulating water, waste water

2015-03 - 2015-05

Maintenance Technician

Shell, NORCO, LA

Full plant maintenance while Shell was on strike

Responsible for functionality of all work done and communicating with the main I&C Supervisor of Shell

2014-10 - 2015-01

Instrument Technician

Valero, Chalmette

Responsible for installation, calibration and testing of all instrumentation during turnaround

2014-08 - 2014-09

Instrument Technician

Green Diesel, LA

Testing all instrumentation damaged from fire for functionality and calibration, pulling damaged instruments and getting calibration data for new installs in our calibration office

Replacing/calibrating all damaged instruments

Verifying loop wiring and all points to the house with operations

2014-07 - 2014-08

I&C Commissioning Engineer

Placid Refining, Port Allen, LA

Checking wiring and calibrations installed by technicians

2014-04 - 2014-06

Instrumentation Technician

Dow Chemical, St.Charles, LA

Responsible for full maintenance in Olefins 1 & 2

Worked side by side two Dow Chemical employees

2014-01 - 2014-03

DCS Technician

Methanex, Geismar, LA

Checking all DCS cabinets and functionality

Checking PLC programing

Checking PLC Modules/Cards

2013-09 - 2013-12

Maintenance Technician

Precision Engineering, Corpus Christi, Texas

Maintenance of all instruments in correlation to every furnace within the whole site

Responsible for support in utilities area that included steam turbines generators and gas turbine generators (G.E

6b and 7Fa)

2013-05 - 2013-09

Turnaround & Maintenance Technician

Dow, LA

Responsible for tagging, pulling and location of instrumentation before cleaning

Returning instrumentation, calibration and loop-checking all instruments pulled

Daily maintenance PM's

Weekly Ph Calibrations site wide

2012-04 - 2012-07

Maintenance Technician

DuPont, LaPlace, LA [Plant assist]

Responsible for full maintenance in all units working side by side DuPont employees., Maintenance & PM's of all instruments and control devices

Maintenance & PM's on furnaces within the whole site

Maintenance & PM's on turbines

2011-03 - 2011-07

Shell

Turner Industries Group LLC, NORCO, LA

Site wide Maintenance Technician

Conducted troubleshooting procedures and root cause analysis to determine causes of problems

Kept shop area and equipment clean, organized and maintained

Responded to problems with processing and production equipment and completed timely repairs

Used information in technical diagrams, schematics and manuals to understand operations and make successful repairs

Supported technicians in equipment maintenance and repair

2010-11 - 2011-03

Instrument Technician

Valero, NORCO, LA

Responsible for installation, calibration and testing of all instrumentation for turnaround

2010-01 - 2010-07

Maintenance Technician

Valero, Memphis, TN

Responsible for plant wide maintenance working side by side with Valero employees

Meet every day with instrumentation group for all work orders to be assigned

Daily PM's

Weekly gas detector checks and maintenance

2009-07 - 2010-01

Instrument Technician

Dow Chemical, Plaquemine, LA

Maintain, repair & replace site-wide gas detectors

PM's on site-wide Ph systems

2009-01 - 2009-05

I&E Technician

Marathon, Garyville, LA

Tested fire eye's and vibration switches

Allen Bradley Control Logix PLC

Education

2006-09 - 2008-06

Associates: Instrumentation & Control Systems

ITI Technical College - Baton Rouge, LA

2001-08 - 2005-05

High School Diploma

Redemptorist High School - Baton Rouge, LA



Contact this candidate