Post Job Free

Resume

Sign in

Engineer Civil

Location:
Riyadh, Saudi Arabia
Salary:
25000 SR
Posted:
August 12, 2020

Contact this candidate

Resume:

Career Summary Statement

Thirty (**) Years of diverse experience in the civil engineering fields since graduation, and out of which more than ten (10) years are in the management of construction of projects .

Responsible for managing, and project's activities during construction from initial stage until completion and hand over .

To seek a new job to work in a dynamic environment work, where I will use my expertise in both management and construction field,while strictly adhering to management of project cost, project scope, project time schedule, safety requirement and quality standards.

Professional Experience

Construction Manager Date Feb,24,2019–Feb,24,2020

United Engineering Construction Company

Riyadh Saudi Arabia

Responsible for managing the project of KAFD Area 2 buildings at King Abdullah Financial District (KAFD).

Supervising construction teams of multidiscipline subcontractors, suppliers, engineers, employees and workers on site to maintain, inspect, and safe operation by third parties of all tower cranes, service elevators, temporary lifting, main riding equipment, making buildings safe, scaffolding inspection / removal and buildings survey.

Duties:

Oversee all project activities both on-site and off-site & making sure they are completed as per the project’s scope, schedule and manage project resources, handle sub-contractors, and coordinate with field operators, to ensure the project objectives achievable within time frame, cost budget, and quality .

Obtain approvals and any required permits for new activities.

Create and monitor a safe / secure job site environment.

Prepare project reports for project manager and client

Project Manager Date Jan,10 2016–Jan,10,2019

United Engineering Construction Company

Al Kharj Saudi Arabia

Responsible for managing and construct the project of Centre of cars maintenance, administration building, eight warehouses of steel structure, gas station, calibration building and all services buildings in General Corporation of Military Industrial (MIC),with a total value (95,992,092.60 SR).

In charge of delivering the project against agreed scope, budget cost, time schedule, quality, doing this whilst planning of all project activities and during supervising, managing the constructions teams of multi-discipline subcontractors, suppliers, engineers and constructions workers.

Duties:

Plan and follow up the preparation of detailed baseline schedule, and its update through periodic revisions.

Provide resources for each phase of project, and manage the project's construction teams, subcontractors, suppliers to ensure that objectives of project are accomplished within prescribed time schedule frame, budget cost, and quality.

Ensure of proper flow of shop drawings from the submission stage to consultant until the approval stage.

Create & monitor a safe/secure jobsite environment.

Establish and maintain relationships with the owner, and consultants, and identify and resolve all variation orders and claims, and review project billing for presentation to the Client.

Prepare project reports for higher management and client.

Project Manager Date Aug,01, 2014–Jan,01,2016

Saudi Salco Contracting Company

Al Kharj Saudi Arabia

Fully responsible for planning, managing, construction and delivering the project of Four administration buildings, two Industrial complexes, four warehouses of steel structure and all services buildings in the General Corporation of Military Industrial (MIC),with a total value (97, 523, 20.56 SR) .

Duties:

Provide the project with all required resources according to the time schedule, and manage the project's construction team, project resources and sub-contractors and suppliers and ensure that are executing all project's activities under the clauses of the contract's items, project scope, cost and safety, quality standard.

Create & monitor a safe/secure jobsite environment

Build relationships with the owner, and consultants, and identify

Create and maintain comprehensive project documentation.

Prepare project reports for higher management and client.

Projects Technical Engineer Date Oct,01, 2013–Aug,01,2014

Saudi Salco Contracting Company

Riyadh Saudi Arabia

Responsible for pricing of the company's tenders in the Riyadh region, preparing the technical files for tenders, follow up the cost of running projects, projects progress,time schedules, and assist to resolve technical issues relating to projects construction.

Duties:

Follow up the preparation of detailed baseline schedule of ongoing projects, and its update through periodic revisions.

Coordinate with projects managers to estimate the cost of projects at the initial stage of construction.

Coordinate with projects manager to resolve construction issues and control the project’s cost during construction, and ensure delivering the project within time schedule.

Construction Manager Date June,01,2012–Oct,01,2013

Saudi Salco Contracting Company

Al Khobar Saudi Arabia

Responsible for construction of Air Separation Plant at sea water treatment plant in Aramco in Al Qurraya for Air Liquide Middle East-Saudi Arabia

Duties:

Manage and oversee day-to-day the project's construction and plan ahead to prevent problems and resolve any emerging ones.

Direct and supervise on site the project's construction teams, and determine appropriate construction's methods and obtain all necessary permits for new activities.

Create & monitor a safe/secure jobsite environment

Review the work progress on daily basis

Ensure quality construction standards.

Project’s Technical Manager Date Jan,15,2011–June,01,2012

Saudi Salco Contracting Company

Al Kharj Saudi Arabia

Responsible for planning, tracking, and scheduling submittal the all technical documents of project of Light ammunition factory in the General Corporation of Military Industrial (MIC) with a total value of (40, 000, 000.00 SR )

Responsible for managing project’s technical issues from initial to completion to ensure that all project’s documents prepared in compliance with applicable project's scope, project’s specification and quality standards.

Duties:

Ensure that all project's documents are conducted in compliance with project’s applicable specification, scope of works.

Convert project’s requirement into technical solutions.

Manage project’s scope and technical issues along.

Manage the day to day planning, preparing, tracking, scheduling submittal of project’s design issues, shop drawings, materials selection and submittals, sub-contractors and suppliers to obtaining the approval of the client and project's consultant.

Projects Manager Date Jan,01,2010–Jan,01,2010

Terrassement Gine Et Travax Petrolies

Al geria

In charge with the responsibility for the administrate and delivery the company’s projects of different types (Water supply pipe lines, gas pipes line, infrastructure projects) against the budget cost, scope of works, and time schedule frame .

Duties:

Follow up the projects planning stage of projects including the mobilization, provide resources, time schedule, projects budget and the submittal of materials and shop drawings.

Coordinate with the projects managers for update and critical projects construction issues discussion to formulate a viable solution.

Provide projects objective advice with aim for quality and on-time project delivery.

Monitor projects risks to identify potential problems and proactively, and identify solutions to address them in advance.

Managing client expectations by ensuring the delivery of the project.

Prepare project reports for higher management.

Self Employed Engineer Date Oct,01,2008–Jan,01,2010

Syrian Engineers Association

Homs Syria

I worked as structural civil engineer, and resident engineer on some building projects, in my private engineering office under the supervision of Syrian engineers Association in Homs in Syria with special focus on the design and construction of residential buildings.

Duties:

Coordinate with the accredited architects by Syrian Engineers Association in Homs in Syria, in order to prepare engineering designs for residential buildings.

Visit projects sites during construction to monitor progress, and consult with contractors

Ensure that the constructions works on the site are conformity with the required designs and standards.

Project Manager Date Feb,01,2008–Oct,01,2008

Advanced Construction Company

Jeddah Saudi Arabia

Responsible for Deba sea port's Extension project’s activities, which included the mountains excavation works, asphalt roads and downloads yards, street lighting poles.

Duties:

Plan the project and prepare the detailed baseline schedule, and its update through periodic revisions.

Handle the sub-contractors and provide resources for each phase pf project according to the time schedule requirement, and also manage the project constructions teams at site to ensure that the objectives of project are accomplished within prescribed time frame and budget cost.

Ensure of proper flow of shop drawings from the submission until the approval stage

Control the Constructions works to be within the time frame and allotted budget

Create & monitor a safe/secure jobsite environment

Establish & maintain relationships with the owner, and consultants, and identify & resolve all variation orders & claims, and review project billing for presentation to the Client

Prepare project reports for higher management and client.

Pre Cast Concrete Factory Manager Date Aug, 01, 2006–Feb, 01, 2008

Rapid Construction Company

Homs Syria

Responsible for managing the complete production processes of pre cast concrete, which include the all structural elements of school’s buildings, universities buildings, pre cast bridges and factories in Syria.

Duties:

Plan, follow up, and manage the production processes in the factory which include modification of concrete mouldings, steel reinforcement fabrication, pouring concrete, finishing and curing.

Coordinate, and consult the designer engineer relating to some technical issues arise during the production processes.

Ensure the quality of per cast concrete elements and secure proper safe storage.

Create & monitor a safe/secure jobsite environment

Coordinate with procurement to provide factory requirement.

Regional Projects Manager Date April,01,2005–Aug,01,2006

Arabian Buildings Support & Rehabilitation Company

Makkah Saudi Arabia

Responsible for the complete execution of projects waterproofing, concrete repair and rehabilitation of school’s projects in Makkah, Taif and south of Saudi Area.

Duties:

Plan, organize, manage the projects activities, and ensure that projects achievable within cost budget, time schedule, and quality and provide manpower and materials for projects

Create & monitor a safe/secure jobsite environment

Meet with clients to resolve their complaints.

Prepare projects progress reports for the higher management.

Projects Pricing & Bidding Engineer Date April,01,2003–April,01,2005

Arabian Buildings Support & Rehabilitation Company

Riyadh Saudi Arabia

Responsible for the pricing the company’s projects and tenders, preparing the tenders technical submittals.

Duties:

Estimate company’s projects cost and prepare technical submittals for tenders.

Projects Execution Engineer Date Aug,01,2001–April,01,2003

Arabian Buildings Support & Rehabilitation Company

Riyadh Saudi Arabia

Responsible for the complete day to day execution of projects waterproofing, concrete repair activities in Riyadh in Saudi Area.

Duties:

Supervise the company's projects and follow-up of site engineers in order to achieve the company's monthly productivity and meet with customers to solve projects problems as well as allocate the necessary labor and materials to execute the projects without problems and obstruction and control the cost of projects, progress, and quality.

Create & monitor a safe/secure jobsite environment

Prepare projects progress reports for the higher management

Self Employed Engineer Date Jan,01,1998–Aug,01,2001

Syrian Engineers Association

Homs Syria

I served as structural civil engineer, and resident engineer on some projects, under the supervision of Syrian engineers Association in Homs in Syria with special focus on residential building construction.

Duties:

Coordinate with some architects in order to prepare engineering design drawings for some residential buildings as well as visiting projects sites during constructions works in order to follow the progress and ensure that the constructions works are carried out according to design drawings and to buildings specifications standards.

Project Site Engineer Date Oct,01,1996–Jan,01,1998

Arab Union Contracting Company

Damascus Syria

Responsible for the complete execution of steel petroleum tanks at Mahrukat Company in different locations in Syria.

Duties:

Follow-up maintenance works for the interior surfaces of the steel petroleum oil tanks that include sand-blasting cleaning works, maintenance and examination work for tank floor welds, epoxy paint work and water testing.

Site Engineer Date Nov, 01, 1989–Oct, 01,1996

General Company of Homs Refinery

Homs Syria

Civil engineer in the maintenance department in Homs Refinery

Duties:

Follow-up of maintenance works for production units that include paints, maintenance of the inner liner of distillation ovens, as well as maintenance of refinery buildings such as paints, plumbing, heating and cooling, as well as maintenance works for steel petroleum oil tanks .

Education

Al Baath University

Bachelor Science of Civil Engineering

Homs - Syria

Sept, 01, 1982 - Oct, 17, 1989

Awarded Certificates

Audit Quality Interne (ISO 9001, 2008) – June 2010

Scaffold Awareness Workshop –July 2019.

Languages

Arabic : Native language

English : Very good in writing, reading, listing, speaking and verbal communication

Professional Associations

Practitioner Civil Engineer in Syrian Engineers Association since 1990

Civil Engineer Member in Saudi Council of Engineers.

Personal Skills

Capability to work within busy environment, and to work under pressure situation.

Project team leader ship and ability to function with fast paced team oriented.

Task scheduling and scheduling capability.

Strong verbal communication.

Powerful negotiator

Areas of Expertise

Primavera

Turbo Project professional

Ms excel, word, power point

Abdul Karim Shullar

Riyadh Saudi Arabia-Al Rabie District-Al Awabi Street

Email: ade9x2@r.postjobfree.com

Mobile No: (+966)-056*******



Contact this candidate