RODERICK ARILLAS
B** L* Camella-Glenmont Subd. Brgy. Sauyo, Quezon City. Philippines 1116
Home Phone: +632********, Mobile Phone: +639*********
addxy3@r.postjobfree.com
PROFESSIONAL PROFILE
Mechanical Engineer with 18+ years of experience Construction and Design of Oil, Gas & Chemical plants, LNG plant, Power plant. Looking to leverage my knowledge and experience into role as Mechanical Piping Engineer, Field Piping Engineer, Construction Piping Supervisor, Quality inspector for Piping, Mechanical and Tanks.
PROFESSIONAL EXPERIENCE
Bechtel
Wheatstone LNG Project-Onslow, Western Australia, Australia
Field Piping Engineer
September 30, 2014 – March 2018 (3.6 yrs.)
Client: Chevron
Coordinate and communicate with the module yard in Tanggu, China to oversee module forecast delivery dates, discuss technical information, safety issues, material ship loose items and carry over works.
Module joint inspection with Australian quarantine inspection service (AQUIS) on carrier heavy transport vessel when arrived in Australia
Send visual inspection invites to all parties involve client, contractor and SMP subcontractor to do a receipt and detailed walk down to verify and validated carry over works, non-conformance, pipe preservation using Cortec, survey target points prior to module fit up and final alignment.
Coordinate between design and stick-built spools production team concerning design information and issues to ensure our end product meets high level of quality.
Receive award recognition for resolving issues with stick-built spools priorities and delivery schedule dates with first KPI’s which is Inlet pipeline downstream connection offshore pipeline.
Receive award recognition for resolving issues with module piping shoe sliding plate.
Receive award recognition from client for a planned and executed with 6 field piping engineers to lead flare punch walkdown leading to a minimal punch list and released for pneumatic testing and blowing successful without any leakage.
Raised FMR’s to ensure adequate consumables to support KPI construction schedules
Generate and raised RFI/FCD/NCR and back charge notice.
Responsible for visual receiving inspection of piping and equipment
Understand, review and approved piping hydrotest packs, blow packs, piping work packs
Witness piping hydro/pneumatic, blowing activities and enforce strict adherence to safety guidelines
Assign to Borescope inspection team to review videos photos of pipe cleanliness category 1, Cortec condition and make necessary judgement to hydrolase blasting, mechanical cleaning and manual Cleaning.
Reviewed and approved Piping Work Packages (WP) documents
Participate and responsible on Construction Sub-System walkdown and Mechanical Completion (MC) Sub-System walkdown. Raised, Verified and Closing of Punchlist items of Mechanical Completion (MC) Sub-System walkdown prior to commissioning
Bechtel
Borouge 3 Project–Al Ruwais, United Arab Emirates
Piping Site Construction Supervisor (PMC)
October 01, 2011- September 04, 2014 (3 yrs.)
Client: Abu Dhabi Polymers Company Ltd - BOROUGE
Construction Supervisor-Piping as part of Project Management Team role, responsible for monitor and oversee EPC Contractor piping and pipeline construction, quality and safety activities in compliance with Company Project Contract and Specification.
Piping and Pipeline Construction progress monitoring, 3 weeks look ahead and day to day activities for piping on all phases of work performed by EPC Contractor areas.
Submit daily/weekly piping stick built and production reports to construction manager for the Company Management Meeting
Responsible for final Company review, comments and approval of EPC Contractor’s and Sub Contractor Method Statement (MS) and Field Material Requisition (FMR)
Monitor surveillance and inspection on site construction activities to ensure that discipline related activities, including material and equipment receipt, storage and installations are accomplished in full compliance with the CLIENT HSE procedures, Method Statement, applicable specifications and standards
Understand, review and approved piping hydrotest packs, blow packs, piping work packs
Monitor TIE-IN activities connection to GASCO and Takreer
Participate and responsible on Construction Sub-System walkdown and Mechanical Completion (MC) Sub-System walkdown. Raised, Verified and Closing of Punchlist items of Mechanical Completion (MC) Sub-System walkdown prior to commissioning
GS Engineering & Construction
Green Diesel Project-Ruwais Refinery –Al Ruwais, United Arab Emirates
QC-Mechanical/Piping/Tank Inspector
March 23, 2010- September 30, 2011 (1.7 yrs.)
Client: Abu Dhabi Oil Refining Company-TAKREER
Responsible for quality inspections on piping, mechanical equipment Static and rotating
Responsible for quality inspections on all storage tank floating and cone roof
Review, Surveillance, Hold and Witness all inspection activities as per ITP in piping, mechanical and tank
Interfaces with engineering, construction and vendors regarding quality issues
Initiate and provide SOM (Site observation memo) & NCR (Non-conformance report) to subcontractor to verify and record the implementation and effectiveness of corrective/proposed action taken
Mechanical alignment inspection
Witness, review and approved piping hydrotest packs, blow packs
Witness, review and approved storage tank floating and cone roof hydrotest package
Assistance on final QC Dossier documentation during final handover
Bechtel
OGDIII Onshore Gas Plant Project – Habshan, United Arab Emirates
Field Piping Engineer
October 12, 2008- October 30, 2009 (1.1 yrs.)
Client: Abu Dhabi Gas Company-GASCO
Field Piping Engineer and at the same time QC Piping Inspector on OGDIII. Responsible for process piping on train 1 and 2 Gas Dehydration / NGL Unit
Responsible on all pipe and pipe support regarding substitutions, technical and site issues, solving technical queries from contractor, making Work Order (WO) for Direct-hire work, and back charging subcontractor
Answers contractor request for information (RFI), technical direction on subcontractor supervisor and craft, made substitution on shortage material on pipe, fittings, flanges, pipe support to mitigate schedule, raised field material requisition (FMR), approved material warehouse request (MWR) for piping and pipe support
Production of as-built drawings on piping, P&ID and pipe support revision thru Field Change Notice (FCN)
Creating hydrotest packages for direct-hire works
Calculation of stored energy on FL & FLC line for pneumatic testing, test blank on compressor and pipe thickness
Responsible for all quality inspections on piping as per ITP
Punch listing for Pre/Posttest walkdowns to verify outstanding items
Witnessing and acceptance of pressure testing, Flush-Air blowing, Bolt torqueing and tensioning
Mechanical Completion (MC) Sub-System walkdowns with Client operation team, PMC, TPI inspector and contractor commissioning team prior to ready for commissioning and start-up
Ensuring system completion dates and project milestones are met as per schedule,
Use Bechtel Standard Application Programs (BSAP's) like Bechtel Procurement system (BPS), Info works, Teamwork’s and Smart plant review (SPR)
Bechtel
Khursaniyah Gas Plant Project – Eastern Province, Kingdom of Saudi Arabia
Field Piping Engineer
February 25, 2007- August 7, 2008 (1.6 yrs.)
Client: Saudi Aramco
Field Piping Engineer on Khursaniyah Gas Project. Responsible for piping on train 1 and 2 LPDGA Unit.
Solving contractor’s technical queries, rerouting/redesigning lines and supports in field
Issuing of day work orders/site instructions and liaising with Lead Piping Field Engineer and Superintendent on all engineering matters
Production of as-built drawings on piping, P&ID and support revision thru Field Change Notice (FCN)
Assists field material procurement in inspection and receipt of piping materials, review and approved material requisitions of field warehouse requisition. Coordinate and interfacing with other discipline
Approve material substitution on pipe, fittings and flanges to mitigates shortages
Check that all project documents that are maintained in the site and pipe shop are the latest revision before commencement of work
Continuously check and review the changes status during the work
Familiar with Saudi Aramco Standard, Procedure and Material system specification. SAES, SAEP&SAMSS
Use Bechtel Standard Application Programs (BSAP's) like Bechtel Procurement system (BPS), Info works, Teamwork’s and Smart plant review (SPR)
Knowledge and understand Bechtel's Standard Work procedure processes (SWPP) like U/G, A/G pipe, pipe supports, pipe system cleanliness, pressure testing of pipe, insulation
Daewoo Engineering & Construction Co.Ltd.
Sakhalin II- LNG/OET Plant Project- Sakhalin Island, Russia
Piping Engineer
June 13, 2005- December 22, 2006 (1.7 yrs.)
Client: Shell
Piping Engineer on Sakhalin II - LNG/OET Plant Project. Responsible for Pipe Fabrication on process train 1 & 2
Monitor and supervise the inspector’s quality activities to ensure compliance to the relevant inspection and test plan. Check that all project documents that are maintained in the pipe shop are the latest revision before commencement
Coordinate inspection activities discuss and resolve where possible problems relating to quality with company
Prepares inspection and testing report for air soap test of reinforcing pad and hydrotest for first spool of the equipment. Assign qualified welder in fabrication shop area based on Welder Procedure Specification (WPS), ASME IX and B31.3
Check Daily production report for welding, RT, PT, MT & PWHT
Site experience of working with Welders and Construction Crews in the field and pre-fabrication yard
Measure and report production welding work in progress on a regular day to day basis
Hyundai Engineering & Construction Co.Ltd.
South Pars Field Development Phase 4 & 5 Onshore Gas Facilities- Assaluyeh, Busher, Islamic Republic of Iran
Piping Engineer
November 28, 2003- January 21, 2005 (1.2 yrs.)
Client: Eni group Agip Iran BV.
Piping Engineer on South Pars Phase 4 & 5 Project. Responsible for Supervision for clearing punch list item prior to pressure testing and reinstatement for final client acceptance.
Issuing of day work orders/site instructions and liaising with Area Piping Manager on all test packages and progress matters. Carrying out visual weld inspections, punch listing of complete systems prior to release of testing, witnessing and approving pressure tests, flushing ensuring applicable standards and specifications are adhered to during construction activities. Issuing daily/weekly of welding report, hydrotest packages reports to QA Manager
Measure welding work, painting works & Insulation work in progress at site and do the reporting on a regular day to day basis
Pre and Posttest walkdowns to verify outstanding items
Understand, review and approved piping hydrotest packs, blow packs, piping work packs
Hitachi Ltd.
Oil, Gas and Power Project- Ibaraki, Japan/ Makati, Philippines
Mechanical Piping Engineer
January 06, 1999- November 20, 2003 (4.11 yrs.)
Client: Hitachi Power and Hydroelectric Division.
Piping Mechanical Engineer on Thermal Power Plant. Responsible for production of isometric drawings from general arrangement drawing (GA). Producing As-Built drawings of isometric, P&ID, pipe support, GA’s and equipment drawing.
Interference checks and design review of all piping and equipment drawings to ensure quality, adherence to specification, resolving technical queries. Directly involve for 5 no. of piping engineer ensuring weekly progress and schedules are met.
Prepares project planning, detail schedule, workloads, manhours and team performance to Project Manager
Train cadet piping engineer on how to make isometric drawing from piping general arrangement drawing
Attend project orientation, site inspection on production of steam/gas turbine and generator plant.
Site visit of Hitachi fabrication plant for thermal power plant projects
Technical meeting with Japanese engineer for project work schedule for preparing detailed piping fabrication and isometric drawing on main steam and high-pressure piping.
Understand & review Piping Layouts, Isometric, Hydrotest packs, Piping MTO's (Valves, Pipes, Fittings and Flanges) and Technical Reports
EDUCATION
Technological Institute of the Philippines. Manila
Bachelor of Science in Mechanical Engineering.1997
ADDITIONAL SKILLS
AutoCAD Rel.14. Microcadd Technologies.1999
PDMS by Aveva.Zabeel Intenational.United Arab Emirates 2013
Microsoft Office
Smart plant review (SPR)
LICENSES AND CERTIFICATIONS
Registered Mechanical Engineer (RME). PRC 1998
Employment that utilize my education and professional skill and offer advancement opportunity that will continue to accumulate knowledge.
I hereby certify that the above information is true and correct to the best of my knowledge and belief.
Sincerely,
Roderick Arillas