Education

BSc, Mechanical Engineering, Technological Institute of the Philippines, Manila, Philippines, 1984

Professional Affiliations

Planning & Scheduling Professional (AACE) - PSP Certified (#1334)

ASME - American Society of Mechanical Engineers - Member

AACE - Association for the Advancement of Cost Engineering - Member

Summary of Experience

Over 25 years of experience in a project management environment - from proposal preparation, planning / scheduling, project cost control, thru project engineering, estimating, and project controls for EPC project execution, FEED(FEL) & BEP package preparation, detail engineering, procurement, construction management, construction and steel shop fabrication exposure for petrochemical, refinery, power, oil & gas, mining and infrastructure industry.

As Lead Planner Scheduler - prepare/develop Primavera (P6) and MS Project Schedules for Baseline and IPA issues, periodic progress update of Primavera Project Schedules from FEL (define), detail engineering phases, and EPC schedules during project execution and for proposals issues; project periodic physical progress measurement and reports utilizing project deliverables' Earned Value and excel-based physical progress measurement tools.

As Cost Engineer - initial project budget set-up and coding, prepare project monthly cost report, cost control-monitor expenditures and commitments, forecast assessment/estimate to complete, cash flow forecast, cost estimation, tracking of trends and change orders; monthly physical progress reports preparation for engineering, procurement and construction, utilizing in-house developed physical progress measurement tools and customized graphs and curves as per project or client's requirements.

As an estimator- material take-off and cost estimation, conversant with construction drawings from P&IDs, plot plans, piping plans and piping isometrics, civil and steel drawings, electrical one-line diagram, equipment GA drawings, architectural plans, instrumentation data sheets and specifications, vendor drawings and very good knowledge on basic and detail design engineering and documentation.

Relevant Experience

Hatch Ltd,Calgary – Various Clients/Projects assignments:

Mar to May-2020 – Project Planner Scheduler to Roquette Pea Project Construction Site assignment (Portage La Praire, MB), weekly earned value progress measurement for various MPEI/Buildings contracts,

Sep to Dec-2019 – Project Planner Scheduler to Rio Tinto Kemano T2 Tunnel Project Construction Site assignment (Kemano, BC), P6 weekly earned value progress measurement for main lump sum contract, in-charge of weekly construction progress report preparation and issuance and all other planning/schedule tasks.

Jun to Aug-2019 – Lead Planner Scheduler at Hatch Calgary home office responsible for proposal schedules preparation, remote support for various on-going FEL engineering projects across NA offices (i.e., Goldcorp Ecotail FEL3 project, Port of Vancouver RBT2 Early engineering Project in Vancouver, BC)

May-2018 to May-2019 – Planner Scheduler to City of Calgary Green Line LRT Project - during conceptual study / early engineering phase; downtown core tunneling various options & strategies (twin bore/single bore) P6 scheduling; land acquisition schedule set-up, control and monitoring utilizing P6.

Jan to Apr-2018 – Planner Scheduler to Hecla-Copper-Silver Mining Project (Estimate & Schedule Updates) - project schedule development for issue to Client evaluation and reference, and for various project & proposals at Calgary Office. Planning/scheduling part-time support for on-going projects across NA region, i.e. Goldcorp Century FEL2/3 Project in Timmins ON.

Jul to Dec-2017 – Goldcorp-Ecotails Project FEL3 Phase - precious metal mining project executed at Hatch Vancouver Office to assist client Investment Committee to decide whether to proceed or not in the project execution (EPC) – in-charge of the FEL2/3 Project Schedule development/set-up, bi-weekly progress updates of the EP feasibility schedule to support periodic progress reporting for Client and internal reporting, and development of Level 3 EPC execution Schedule.

Apr to Jul-2017 – Kazmin-Aktogay Project FEL3 Phase - Copper Smelter mining project executed at Hatch Mississauga office aimed to assist Client's Investment Committee to decide whether to proceed or not in the project execution (EPC), in-charge of the FEL2/3 Project Schedule development/set-up, weekly progress updates of the EP feasibility schedule to support periodic progress reporting to Client and internal reporting, and the development of Level 3 EPC Execution Schedule.

Apr-2015 to Mar-2017 – PennEast Pipeline Co (Spectra+UGI), PennEast Pipeline Project, Pennsylvania-New Jersey, United States, Lead Planner/Scheduler; Project planning & scheduling (remote support from home office) during the detail engineering and project permitting phase, for level 3 project schedule from set-up, maintenance and bi-weekly progress updates which is integrated to level 1 construction and commissioning schedule; Obtain biweekly updates from the team and clear communication for impact of remaining scope's forecast completion dates to critical path to project management and to responsible discipline leads; Timely evaluation of physical progress. Periodic re-forecasting, as required, of time to complete remaining work utilizing Primavera P6.

Jan to early Mar-2015) – MH-Keeyask GS Project Detail Engineering Phase - $6.5 billion hydro-electric generating station project-Hatch Winnipeg is undertaking the E-Scope - Assisted to finalize and issue Baseline Engineering Schedule, weekly progress updates of the engineering schedule to support periodic progress reporting to client and internal reporting.

Oct to Dec-2014 – KGMH Victoria Project FEL3 Phase - a multi-billion copper-nickel mining project-Hatch Sudbury undertook the early engineering work - Assisted to finalize and issue FEL3 Schedule, weekly progress updates of the engineering schedule to support periodic progress reporting to client and internal reporting.

Aug to Sep-2014 – Early engineering phase (small projects) - Petrochad Krim Project FEL2) – Planner Scheduler, project schedule set-up and development, periodic weekly progress updates and issue weekly schedule reports for Internal and Client’s Project Progress Monthly Reports attachments; Planner Scheduler for various proposal preparation at Hatch Calgary home office (small projects and proposals) - Responsible for proposal project schedule set-up and development; Any other Planning and Scheduling functions to support project controls department and other on-going project requirements;

Nov-2013 to Jul-2014 – Mosaic-K3 Potash Mine Project, Esterhazy, SK, Canada, Lead Planner Scheduler, Project construction site assignment - biweekly progress updates of the project integrated schedule to support periodic progress reporting; Generate and issue periodic (biweekly and monthly) schedule reports for Internal and Client’s Project Progress Monthly Reports attachments; Weekly Progress Updates of Level 4-5 Detail Schedule of the Shaft Sinking Sub-Contractor – by obtaining actual progress input from Sub-contactor’s supervisors/project controls staff, update the same to P6 schedule – Then provide Sub-contractor's Project Team the “3 week look-ahead schedule” reports, overall shaft sinking schedule weekly update and other reports, as required to support weekly progress review meeting with Hatch PMT. (The Shaft Sinking Contractor was doing the bulk of the project construction scope.); Attend weekly coordination meetings of all on-going Sub-Contract Construction works, analyze Sub-Contractors schedule performance and provide feedback or flag Hatch PMT for any slippage on their schedule or performance that impacts Critical Path or overall project completion; Any other Planning and Scheduling function to support project requirement.

Apr-2013 to Oct-2013 – Canexus-NATO Unit Train Loading Project- FEL3 & 4, Bruderheim, AB, Canada, Lead Planner Scheduler. Assigned at home office during the detail engineering phase, then moved to project site for 7 months during the construction / pre-commissioning phase of the project - for set-up, maintenance and weekly progress updates of the project's integrated-level 4 construction schedule; Responsible for the planning and scheduling of project activities to client or project requirements utilizing Primavera ver. 6.82; Estimating of project activities, time/labor/cost. Clear communication of the scope and required tasks to each discipline involved; Timely evaluation of physical progress. Periodic re-forecasting, as required, of time to complete remaining work. Recommend resource loading and utilization with consideration to the critical path.

Mar to May-2013 – CNRL-OPP & HT Train 4&5 - EDS, Fort McMurray, AB, Canada, Lead Planner Scheduler. Planning / Scheduling of project activities to client or project requirements utilizing Primavera P6.82; Estimating of project activities, time/labor/cost. Clear communication of the scope and required tasks to each discipline involved; Initial set-up of level 3 project schedule, schedule basis, baseline issue and periodic update (weekly and month-end), what-if analysis and maintenance; Timely evaluation of physical progress. Periodic re-forecasting, as required, of time to complete remaining work; Recommend resource loading and utilization with consideration to the critical path. Relied on extensive experience and judgment to plan and accomplish goals

Oct-2012 to Feb-2013 – Suncor-Voyaguer Hydrogen Plant Restart Project, Fort Mcmurray, Alberta, Canada, Lead Planner Scheduler - Planning and scheduling of project activities to client or project requirements utilizing Primavera P6; Periodic evaluation of physical progress and reporting of cost and Earned Value. Re-forecasting, as required, of time and cost to complete remaining work; Prepare completion and close-out report of EP work scope.

Career History

Oct-2012 to May-2020 Hatch Ltd, Calgary, Alberta, Canada. Lead Planner/Scheduler

2011 - 2012 Technip USA, Inc., Claremont, California, United States. Principal Planner/Scheduler

2005 - 2010 Jacobs Engineering Group, Cypress, California, United States. Lead Planner/Scheduler/Cost Engineer

2004 - 2005 Technip USA Corporation, Claremont, California, United States. Project Controls Specialist

2002 - 2003 The Site Development Studios, Costa Mesa, California, United States. Project Engineer/Project Controls Assistant

1995 - 2001 JGC Philippines, Manila, Philippines. Project Engineer to Lead Project Engineer

1993 - 1994 Promet Fabricators Sinderian Berhad, Johor Bahru, Malaysia. Project Engineer

1992 - 1993 Foster Wheeler (Pacific) Ltd, Jurong, Singapore. Piping Superintendent

1990 - 1992 Jurong Engineering Ltd, Jurong, Singapore, Singapore. Project Engineer

1989 - 1990 Belleli Saudi Heavy Industries, Jubail, Saudi Arabia. Designer / Estimator

1985 - 1989 Atlantic Gulf & pacific Co of Manila, Manila, Philippines. Cadet, Jr Engineer to Engineer II