CECILIO ABU ABANTO

Block * Lot **, Brighton Street cor. Mayfair Street,

Avida Residences San Isidro, Batangas City 4200 Philippines

Contact No’s.: 0063-928-***-**** (PHI) or 0063-928-***-**** (PHI)

Email Address: addiam@r.postjobfree.com or addiam@r.postjobfree.com

APPLIED AS: Senior CADD Draftsman Detailer or any suitable position to my experience.

EDUCATIONAL BACKGROUND:

College : Batangas State University (BSU), Batangas City

Formerly Pablo Borbon Memorial Institute of Technology (PBMIT)

S.Y. 1990 – 1992

Course : Drafting Technology

GOVERNMENT EXAM:

Third Class General Drafting (Passed)

Manpower Youth Council

P. Herrera Street, Batangas City Philippines

06 August 1992

SEMINAR AND TRAINING ATTENDED:

Seminar on Supervisory Development Program

MMG Yanbu Camp II,

Yanbu, Kingdom of Saudi Arabia

04 September 1998

In-house Training for Micro Station Second Edition (SE)

MMG Head Quarters

Dammam, K.S.A.

28 April 2006

Seminar for Fabrication Management System (FMS)

Ersai Site Engineering Office

Kuryk, Kazakhstan

30 November 2011

Safety Training for Rigging Supervisor

Bureau Veritas

Certificate Serial No: BV.DOA.16.IVS.124.81/Rigging Supervisor/201116/RGS-07

Valid up to: 20 November 2019

QUALIFICATION:

A multidiscipline Senior CAD Designer Draftsman Detailer, Field Engineering Technician, (AA) Field Engineer (Piping & Structural) and Rigging Engineer. Having a technical knowledge on manual drafting and mostly operating on Computer Aided Design i.e. AutoCAD Release 14, AutoCAD 2002, AutoCAD 2005 to AutoCAD 2018. Design and As-Built of all discipline regarding construction drawings i.e. Detailing, P&ID, Piping Plan, Isometric Drawing, Spooling, Weld Mapping, Dia. Inch & Material Take-off, Structural Detail Fabrication & Erection Drawings including Material Take-off and Rebar Arrangement Drawings for Miscellaneous Civil Works including Rebar Bending Take-off. Prepare medium and critical lifting/rigging plan and elevation drawings for miscellaneous lifting erection. Supervise the fabrication of Piping pipe spools and miscellaneous structures for erections and have technical knowledge on preparation of Piping Test Packages prior for system testing. A computer literacy in Microsoft Excel, Microsoft Word, Microsoft Outlook, Lotus Note & Adobe Nitro PDF and able to work with less supervision.

YEARS OF EXPERIENCE:

20 Years & 8 Months Total Experience - Experience in various capacities on the field of Constructions and Projects in Saudi ARAMCO, Sasref, SABIC, Yanpet Plant, Fertilizer Plant, Petrochemical Plant, Desalination Plant and in Qatar Petroleum.

12 Years and 8 Months - Experience in Kingdom of Saudi Arabia with Mohammad Al-Mojil Group.

3 Years and 9 Months - Experience in Kazakhstan with Saipem ENI Group – Ersai LLC.

4 Years and 3 Months - Experience in Qatar with Qatar Engineering & Construction Company WLL.

PERSONAL INFORMATION:

Name : Abanto, Cecilio Abu

Address : Block 4 Lot 11, Brighton Street corner Mayfair Street,

Avida Residences San Isidro, Batangas City 4200 Philippines

Contact No’s. : 0063-928-***-**** (PHI) or 0063-928-***-**** (PHI)

Date of Birth : 06 August 1973

Place of Birth : Aplaya, Bauan Batangas

Height : 5' 6” (167cm)

Weight : 174 Lbs. (79 Kgs.)

Civil Status : Married

Nationality : Filipino

Religion : Roman Catholic

Passport No. : P6819776A

Date Issued : 17 April 2018

Valid Until : 16 April 2028

WORK EXPERIENCES:

Company - QATAR ENGINEERING AND CONSTRUCTION COMPANY WLL (QCON)

Address - Street 48 Gate 27 Salwa II Industrial Area P.O. Box 24491 Doha, Qatar

Period - 22 December 2012 to 31 March 2017

Project Assigned:

Qatar Engineering and Construction Company WLL

Maintenance Supply Department (MSD) and

Rapid Response Team (RRT)

Salwa II Industrial Area, Doha Qatar

From: 01 March 2015 to 31 March 2017

Position: Field Engineering Technician / Field & Rigging Engineer (AA)

Duties and Responsibilities:

Responsible for the preparation of medium and critical lifting/rigging studies plan and elevation drawings for miscellaneous lifting erection (shutdown & projects).

Conduct site survey and proper coordination and communication to project in-charge or site personnel to have proper arrangement on the specified job requirements.

Prepare scale drawings in AutoCAD of all types of company’s crane for future use and reference.

Responsible for the preparation of shop fabrication detailed drawings for structural including material take-off in accordance with the company materials specifications and standards.

Responsible for the preparation of Isometric drawings for additional lines as per client requirement and project standard.

Perform Weld Mapping, Spooling and Dia. Inch take-off prior for fabrication.

Perform materials take-off for Structural and Piping Isometric drawings prior for material ordering.

Conduct daily site monitoring activities for all piping and structural works and prepared daily progress report and submitted to Planning Department and Construction Manager.

Assigned in shutdown maintenance works at NGL-4 plant as acting Rigging Engineer (December 2016 to February 2017).

Project Assigned:

Qatar Petroleum Halul Island (Offshore)

Marine (MRO) Department

Doha Qatar

From: 22 December 2012 to 28 February 2015

Position: Field Engineering Technician

Client: Qatar Petroleum

Duties and Responsibilities:

Responsible for the preparation of design and fabrication/shop detailed drawings for all disciplines including material take-off in accordance with the company materials specifications and standards.

Conduct site dimensional survey as per the requirements.

Conduct proper coordination and communication to Qatar Petroleum MRO Supervisor or QCON Supervisor to have proper arrangement on the specified job requirements.

Conduct daily site monitoring activities for all works and prepared Daily Progress Report (DPR) and submit to Qatar Petroleum (QP) Department Supervisor.

Assist and provide solution for any discrepancies and queries of construction.

Responsible for Weld Inspection Master Control Sheet (WIMCS), Inspection and Testing Certificates for MPI, UT, DPI and Hydro test.

Supervise the miscellaneous fabrication works i.e. pipe spools, pipe supports, fabrication and modification of new and existing platforms.

Supervise the fabrication of Piping pipe spools and miscellaneous structures for erections.

Responsible to As-Built issued shop drawings for any changes made.

Responsible to prepare Completion Certificate for every work orders job completed and bring to department head who requested the job for their signature.

Responsible to update Daily Consumables, Daily Time Sheet, Manpower List and Work Order’s Log.

Responsible for the monitoring of expiring Qatar Petroleum Access Pass, H2S and HUET ID’s of every employee.

Responsible to update and maintained all files for incoming and outgoing documents to and from QCON main office and MRO Department.

Assigned in shutdown maintenance works at Qatar Petroleum PS-3 platform to assist Halul-36 workboat (April 2013 to June 2013).

Company - SAIPEM ENI GROUP (ERSAI LLC)

Address - ERC Holdings-SAIPEM ENI GROUP (ERSAI LLC), Republic of Kazakhstan

Period - 17 August 2008 to 16 May 2012

Project Assigned:

Kashagan Experimental Programme

Republic of Kazakhstan

From: 17 August 2008 to 16 May 2012

Position: Senior CADD Draftsman

Client: Agip Kazakhstan North Caspian Operating Company

Duties and Responsibilities:

Responsible for the preparation of piping isometric shop drawings including weld mapping, spooling & material take-off for each spool in accordance with the company piping material specifications & standards.

Responsible for the preparation of structural shop drawing details i.e. structural steel platforms, handrails, walkways, stairs, pipe racks and pipe supports prior for fabrication, showing the general arrangement & connection details for welded & bolted connections, together with the welding table/mapping and material take-off for each structural member.

Responsible for the Progress and Status Report of isometric and structural fabrication drawings.

Responsible to update Drawing Log and checking of latest received client drawings revision prior for the revision and preparation of fabrication drawings.

Conduct proper coordination and communication to client and construction or site personnel to have proper arrangement on the specified job requirements.

Responsible to prepare As-Built drawings and Traceability of all piping isometric and structural fabrication drawings.

Supervise and assist the project document controller to issue the fabrication and client drawings to construction/site personnel and update the project drawing register.

Company - MOHAMMAD AL-MOJIL GROUP

Address - P.O. Box 11, Dammam 31411 Kingdom of Saudi Arabia

Period - 23 October 1995 to 24 June 2008

Project Assigned:

Ju’aymah Gas Plant Expansion Project

Saudi Arabian Oil Company

Ju’aymah, Kingdom of Saudi Arabian

From: 27 November 2006 to 24 June 2008

Position: Lead Sr. CAD Designer/Draftsman and Test Package Coordinator

Client: Tecnicas Reunidas Gulf Co. (TRG)

Saudi Arabian Fertilizer Company

Expansion Project (UHDE / SAFCO-IV)

Jubail, Kingdom of Saudi Arabia

From: 26 July 2004 to 26 November 2006

Position: Sr. CAD Designer/Draftsman and Test Package Engineer (AA)

Client: Thysenn Krupp UHDE Arabia Ltd.

JUPC – General Construction Package-2 (K035)

Utilities and Offsites

Jubail, Kingdom of Saudi Arabia

From: 15 July 2002 to 23 April 2004

Position: Sr. CAD Designer/Draftsman

Client: Fluor Daniel Arabia Ltd.

JUPC – U&O Site Preparation (K003)

Temp. Utilities, Roads, Fencing & Warehousing

Jubail, Kingdom of Saudi Arabia

From: 08 December 2001 to 15 July 2002

Position: Sr. Draftsman

Client: Fluor Daniel Arabia Ltd.

Saudi Yanbu Petrochemical Corporation

YEP Polymers Expansion Project

Madinat, Yanbu, Al-Sinaiyah K.S.A.

From: 09 August 1998 to 25 April 2000

Position: Jr. Draftsman

Client: Mitsubishi Heavy Industries Company (MHI)

Mohammad Al-Mojil Group

Engineering Department (Main Office)

Dammam, K.S.A.

From: 14 June 1998 to 07 August 1998

Position: Jr. Draftsman

Saudi ARAMCO Abqaiq Plants Control System

DCS Modernization Project-LSPB-2

Abqaiq, K.S.A.

From: 08 March 1997 to 13 June 1998

Position: Jr. Draftsman

Client: Saudi Parsons Arabian Co. Ltd.

Methanol Plant

Ar-Razi III Project

Jubail, K.S.A.

From: 19 January 1997 to 05 March 1997

Position: Draftsman

Client: Mitsubishi Heavy Industries Company (MHI)

Al-Khobar Power and Desalination Project

Aziziyah, Al-Khobar K.S.A.

From: 17 November 1996 to 13 December 1996

Position: Draftsman

Saudi Basic Industries (SABIC)

Petrochemical Plant

UOC Mechanical Erection Services

Jubail, K.S.A.

From: 23 October 1995 to 14 November 1996

Position: Draftsman

Client: Brown & Root Saudi Ltd. Co.

Duties and Responsibilities:

Prepare design, layout and detailed drawings for Civil/Structural, Electrical/Instrument and Mechanical/Piping works as per Project Standard.

Prepare approved drawings for construction from client, particular for fabrication and field erection.

Conduct actual survey and daily site monitoring activities for any work discrepancies and prepare Site Engineering Request (SER) and/or Site

Query for modifications and clarifications.

Finalize the proposed design and forward it to the immediate Supervisor.

Assigned at MHI Project Management Team for the preparation of design, plan layout and detailed drawings of structural steel prior for fabrication.

Prepare rebar arrangement drawing and rebar take-off for miscellaneous civil works.

Prepare Isometric drawings for additional lines as per client requirement and project standard.

Perform Weld Mapping, Spooling and Dia. Inch take-off prior for fabrication.

Perform materials take-off for Civil/Structural, Electrical/Instrumentation and Mechanical/Piping works prior for reconciliation.

Assigned at Saudi Aramco Project Management Team (SAPMT) to As-Built all Electrical and Instrumentation works i.e. ILD, P&ID, SAMA and Interconnection Diagram.

Supervise and prepare Piping Test Packages prior for system testing, piping systems hand over walk downs and punch listing/clearing.

Prepare Pressure Test Diagram (P&ID) drawings for the involve lines to be included on pressure testing.

Conduct proper coordination and communication to the Counterpart or Project Management Team (PMT) to have proper arrangement on the specified job requirements.

Perform As-built activities of all Civil/Structural, Electrical/Instrument and Mechanical/Piping works from and for until the duration of the project.

I hereby certify that the above information is true and correct to the best of my knowledge and belief.

CECILIO ABU ABANTO

Applicant Signature



Contact this candidate