CURRICULUM VITAE
Said Mahmuddin
Date of Birth : Aceh, January 28-1963
Sex : Male
Personal status : Married
Citizenship : Indonesia
Address : Depok Mulya 1 Blok I/7 Beji.Depok
Email : ****.********@*****.**.**
Mobile : +62-822-****-****
Formal Education
Bachelor of Mechanical Engineering
Work Experiences
1988-1989 Exxon Mobil Arun Field. (Onshore)
Planner Duties And Responsibilities
oPrepare Outage Schedule
oAudit Materials Incoming-Outgoing
oAudit Reliability Factor
1989-1994
Lead Process Engineer Paper Mill Power Plant 2x18MW (KKA)
Duties And Responsibilities
• Project s Review (Utility) :
oTechnical Aspect
oCommissioning Procedures
oPerformance Guarantee/Acceptance Test
• Operation and Maintenance
oReview OM documents
oPrepare SOP and Maintenance schedule
oManage/supervise OM activities
oStudy/Improve Availability Factor & NPHR
1994-2000
Senior Mechanical Engineer Pulp & Paper Power Plant 1x27 MW, 2x63MW, 3x125MW (RB,BFB,CFB)
& Operation Lead (APRIL GROUP/RIAU PULP & PAPER)
Duties And Responsibilities
• Project Review (Power Side) :
oReview QA/QC documents
oReview commissioning documents
oJoint Commissioning Gas Turbine MHI 3x5MW
oJoint Commissioning/start-stop for BOP and Main equipments such as RB, BFB, CFB and STG
• Operation and Maintenance
oReview OM documents
oStart-stop BFB boiler and operate to performance test(commissioning phase)
oStart-stop CFB boiler and operate to performance test(commissioning phase)
o Supervise operation of power plant
oPrepare SOP and Maintenance schedule
oManage/supervise OM activities
oStudy/Increase Thermal Factor
oPlant assessment
oTechnology Sourcing/Optimazation And Plant Modified.
2000 - 2007
Commissioning Engineer Foster Wheeler Services (BFB & CFB boiler) Overseas Projects
(Tainan & Taichung Cogen/Taiwan, Dagang/China), Indah Kiat/Indonesia
Duties And Responsibilities
•Projects & Commissioning:
oPrepare /set up commissioning Documents
oSet up O&M manual
oSet up Commissioning Time Frame/Activities
•Commissioning Activities:
1.Check available drawings and PI & D
2. Check installed logic/Operation philosophy and make sure protection system’s its should be safe to operate
3. Check auxiliaries/fans including boiler feed pumps system ready for trial run
4. Check main equipment such as pressure parts. Safety valve/PRV. Combustion Chamber/bed nozzles. Refractory lining. ESP. Etc.
5. Make sure feed water/boiler water available
6. Make sure fuels and bed material/sand available and limestone if required
7. Power available and trial run to start filling water and bed material.
8. Start refractory cure/drying out and acid cleaning if possible together with refractory curing
9. Start steam blowing as per steam requirement
10. Retuning combustion system as per fuels and air ratio
11. Start-stop as per plant condition
12. Check all conditional of main equipment for ready to 72 hours reliability run
13. Ready to continue operate for performance test/PG
14. Performance guarantee as per contract and environment aspect as per word bank standard or local standard
oUpdate Commissioning Documents As Performance test/ PG
oAfter Sale & Services :
oTechnical Advise for plant outage
oOutage Assessment & Report
oSupervise Pressure Parts Replacement
April – Sept 2007
Commissioning Engineer Cilegon CCGT 740MW (PLN) M701F/MHI 2x270MW, 2xHRSG
Duties And Responsibilities
•Project & Commissioning:
oJoint review commissioning Documents
oJoint review O&M manual
oSet up Commissioning Time Frame/schedule
oJoint Commissioning Activities
oUpdate Commissioning Documents As Per PG Test
2007- March 2014 Makmur Sejahtera Wisesa (CFPP 2x30MW/CFB) IPP ADARO POWER
Chief Mechanical Eng Duties And Responsibilities
• ISBL Project
oVendor Assessment/Bid Selection
oReview Design & Engineering Docs and Plant Concept
oJoint Review Construction Docs & Commissioning Procedures
oPrepare Regulation Documents & Environment Aspect
oSurveillance FAT/OEM
oSurveillance construction activities
oReview acceptance test report
• OSBL Project :
oPrepare Tender Documents For WTP & Water Transmission
oVendor Assessment/Bid Selection
• Operation & Maintenance
oPrepare/set up 1 Year strategy & 5 years PDCA
oPlant assessment and report
oDealing Resource Services & Vendors
2014 – 2015 Korea Wester Power (KOWEPO) SUMSEL-5. CFPP 2 X 150MW/CFB
Engineering Affairs Manager Duties And Responsibilities
Review O & M Documents/SOP
OJT O & M Staff
Prepare/set up 1 Year strategy & 5 years PDCA
Prepare maintenance schedule documents
Risk assessment of engineering issues
Prepare Regulation Documents (HSE & CSR)
Technology Sourcing/Optimazation And Plant Modified.
2015 – at Present Feedback Infra Power (Overseas Projects)
Technical Advisor Duties And Responsibilities
Prepare Commissioning Documents
Prepare O & M Documents
Prepare Start-up Procedure (SOP)
Commissioning coordinator for 2 x 10 MW/Grate boiler (Stalled project - Tembilahan/Indonesia
Plants assessment/due diligence for 12 power plant projects stalled around Indonesia/government power plant (Grate boilers and CFB boilers)
Assessment for GE Jenbacher gas engines (Maxpower, Sumatera, Sorong/Indonesia and Myanmar plant)
FS for new plant – renewable/solar – Tanjung pinang/Indonesia