Post Job Free
Sign in

Crane Power Plant

Location:
Caloocan, NCR, Philippines
Posted:
June 29, 2020

Contact this candidate

Resume:

Bernardino Abuyen Cajayon

#** ******** **. ******** *********** Tanza Navotas City Philippine mobile no.: +639*********

Philippine mobile no.: +639*********

Landline no.: +632*******

Skype id: Bernard Cajayon

Email Add.: add7k3@r.postjobfree.com

Position desired

•Mobile and Crawler Crane Operator/Heavy lift

Career Objective:

To further enhance my knowledge, skills and competencies as crane operator

To make significant contribution towards the success of the company

To perform the assigned duties and responsibilities efficiently and effectively

To provide myself job satisfaction as well as financial stability.

Summary of Qualification

For more than 20 years of work experience on heavy Industries, like oil and gas plant construction, power plant port terminals, cement plant building.

Enable me to perform jobs with high standards of safety

Can operate mobile and crawler crane.

Personal Data:

Age: 48

Date of Birth: May 20, 1972

Place of Birth: Bongabong, Oriental Mindoro

Gender: Male

Civil status: Married Height: 5’11” Weight:90 kilos Nationality : Filipino

Passport number: P2427220A

Name of spouse: Maureen C. Cajayon

Educational Attainment

Education level: College Undergraduate Course: Education

School: Divine world college of Calapan Location: Calapan Oriental Mindoro Date: 1991

Work Experience

Company: Guzent Inc. Philippines

Position: Mobile Crane Operator, Fork Lift Operator, Light and Heavy Driver

Location: Edsa Quezon City

Duration: June 6, 2020 (ENDO)

Project: Leigthon NLEX Harbor Link R-10 (CAMANAVA Area)

Crane Operated: Grove RT 765E-2 (Rough Terrain 60 Tons

Work Experience

Company: Ejar Saudi Crane and Equipment LLC. Kingdom of Saudi Arabia

Position: Crawler and Mobile Crane Operator

Location: Kingdom of Saudi Arabia (Aramco Gas Project)

Duration: Oct. 31, 2015 – June 27, 2019

Project: Tecnicas Reunidas/Sinopec/China harbour

Jizan Gas Development Aramco Project/ Jizan Port Terminal Project

Crane Operated: Kobelco Cke 1350 Crawler Crane 135 Tons

Liebherr LTM 1200-5.1 All Terrain Crane 200 Tons.

Liebherr LTM 1100 - All Terrain Crane 100 Tons.

Liebherr LTM 1055 - All Terrain Crane 50 Tons.

Tadano GR 500 Rough Terrain Crane 50 Tons.

Project: Fadhili Gas Program Project Jubail K.S.A

Crane Operated: Liebherr LTM 1200-5.1 All Terrain Crane 200 Tons.

Work Experience

Company: Guzent Inc. Philippines

Position: Mobile Crane Operator

Location: Edsa Quezon City

Duration: August 2014 – October 2015

Project: Leighton Hotel Project City of Dreams/Parañaque City Phils.

Crane Operated: Tadano GR 550EX Rough Terrain Crane 55 tons.

Project: Shimizu Philippines/Zama Batangas Factory Project.

Crane Operated: Tadano GR 550EX Rough Terrain Crane 55 tons.

Project: Makati Dev. Project Building Project BGC Staging Area Taguig City

Crane Operated: Kato Rough Terrain 25 Tons

Tadano GR 550EX Rough Terrain Crane 55 tons.

Work Experience

Company: Ejar National Cranes and Equipment LLC.U.AE

Porsition: Crawler and Mobile Crane Operator (Heavy Lift) Location: Doha Qatar/Abu Dhabi, U.AE/Turkmenistan

Duration: June 2011- July 2014

Project: Doodsal Company/Gasco HMT Gas Pipeline Project.Abu Dhab, U.AE

Crane Operated: Liebherr LTM 1350-6.1 All Terrain Crane 350 Tons.

Project: Saipem Company/Shahgas Development Project Abu Dhabi U.AE

Crane Operated: Liebherr LR 1300 Crawler Crane 300 Tons/ Luffing J1B Configuration

Project: Adac Dev. Planning /Abu Dhabi Midfield Airport Terminal Project U.AE

Crane Operated: Liebherr LR 1300 Crawler Crane 300 Tons/Superlift Configuration.

Project: Duha Marine Port Terminal Project Doha, Qatar

Crane Operated: Kobelco CKE 2500-1 Crawler Crane 250 Tons.

Project: Tekfen / Petrofac Turkmen Gas, South Yotolen Gas Field Turkmenstan.

Crane Operated: Kobelco CKE 600 Crawler Crane 60 Tons.

Work Experience

Company: Gama Al Moushegah Arabia Ltd. Kingdom of Saudi Arabia.

Position: Crawler and Mobile Crane Operator

Duration: November 2001 – June 2010

Project: Maaden Sulfuric Acid Plant Proj K.S.A (November 2008-June 2010)

Crane Operated: Manitowoc M-250 Epic Crawler Crane 300 Tons.

Manitowoc Vicon Crawler Crane 150 Tons.

Liebherr LTM 1120/All Terrain Crane 150 Tons.

Project: Tasnee Polythylene Plant Project (Sabic) Judial K.S.A (Aug 2007-Sept 2008)

Crane Operated: Liebherr LTM 1120/,All Terrain Crane 120 Tons.

Project: Yamama Cement Plant Project Riyadh. K.S.A

Shoibah Power Plant Project Jeddah K.S.A (March 2005- June 2007)

Crane Operated: Liebherr LTM 1160/ 2 All Terrain Crane 160 Tons.

Project: Saudi, Fertilizer Plant (Safco) Jubail K.S.A

Berri Gas Plant Aramco Project. Jubail K.S.A (November 2003- Feb 2005)

Crane Operated: Tadano TG 500 E Truck Mounted Crane 50 Tons.

Grove Rough Terrain Crane 25 Tons.

Project: Petrokemya Polythylene Plant Project Jubail K.S.A (November 2001- Oct 2003)

Crane Operated: Grove TM 980 Truck Mounted Crane 80 Tons.

Work Experience

Company: Formosa Plastic/Tridon Corporation Taiwan R.O.C

Position: Pile Driving Crane Operator

Location: Mailao County of Taiwan R.O.C

Duration: April 1996 - December 1999

Crane Operated: P&H Crawler Crane (Trifugal Configuration) 100 Tons.

Hitachi Crawler Crane (Trifugal Configuration) 80 Tons.

Work Experience

Company: P.A Ramos Construction Corporation Philippines.

Location: Las Piñas Metro Manila Phils.

Position: Rigger / Pile Driving Crane Operator

Duration: 1991 – 1995

Crane Operated: P&H Crawler Crane (Selffeeding Configuration) 40 Tons.

JOB DESCRIPTION:

Operate crane under general supervision.

Manipulate or depress crane controls to regulate speed and direction of crane and hoist movement according to written, verbal or signal instructions.

Repair crane as needed.

Inspect crane for safety issues on a daily basis.

Determine if any parts are malfunctioning.

Complete jobs tickets, service quality summaries and all other necessary paperwork.

Lift position and place machinery, equipment or other large objects at construction sites and industrial facilities.

Drive trucks to worksites and unload trucks.

Place blocks and outriggers to prevent capsizing when lifting heavy loads.

Move levers and pedals to rotate crane on chassis to raise and lower crane boom and to raise lower load-line.

DUTIES AND RESPONSIBILITIES

The operator must be certified under local requirements, is in charge of operating the crane. He must demonstrate adequate knowledge of:

Crane Controls

Crane operating characteristics

Crane load chart and manufacturer’s instructions

Acceptable hand signals

Duties Are:

A.Starts up and shuts down crane using proper procedures.

B.Moves the crane

C.Setup the crane, including proper outrigger extension and blocking.

D.Ensure the required radius and/ or boom angle is measured.

E.Ensure the crane is properly rigged for the particulars lifts, including correct gantry height and parts of line.

F.Ensures the crane is in safe operating condition by checking the following:

i.Brakes and clutches are in proper working order and adjustments.

ii.Wire ropes are in good condition and capable of lifting the maximum shown on the load chart.

iii.Periodic operating checks of hydraulic circuits and controls are performed.

G.Operate the crane in a safe manner means of:

i.Brakes and clutches are in proper working order and adjustments.

ii.Wire ropes are in good condition and capable of lifting the maximum shown on the load chart.

iii.The use of taglines to control the load.

iv.Operating in accordance with safe practices when working in the vicinity of live apparatus.

v.Consideration of the effect on wind conditions at the time of the lift.



Contact this candidate