Haitham Haj Ibrahim
Phone: *****--********* In Saudi Arabia
Email: add6yc@r.postjobfree.com
add6yc@r.postjobfree.com
Job Title: Mechanical Superintendent
Summary
Date of Birth: 1-October-1973
Marital Status: Married
Nationality: Palestinian
Current Location: Jeddah, Kingdom of Saudi Arabia.
Work Experience: 1-December- 1992
Language: English reading and writing
Computer Skills: Word, Excel, Power Point, Outlock
Prepare shop and as built drawings and material submittals for approval.
Know and in good relationship with all mechanical suppliers.
Valid Saudi Driving License.
Transferable Iqama.
Qualification: Diploma in Refrigeration and Air Conditioning- Seblin Training Center- Lebanon.
Professional Memberships:
Member – Project Management Institute (PMI)
Professional Trainings
PMP training from Jeddah – Saudi Oger Ltd. – December 2011
FM 200 suppression training from Seffeco in Jeddah.
Environmental Certificate from Kaust.
Experience
1. Modern Architecture Company (MACC) Jun 2020 Up To Date
Yamamah Palace Riyadh
Mechanical Superintendent
Renovation of all Mechanical systems, dismantling and installation of all mechanical systems such as HVAC, Plumbing, sanitary fixtures, irrigation, BMS, FM200, Foam System, firefighting system, swimming pools, fountains, sauna and jacuzzi as per the new project specifications, arrange all new material submittals, shop drawings for the approval, follow the requirements with the private affairs, follow up the subcontractors progress as per the plan, arrange and attend meetings with the consultant,contractors and the maintenance team, testing and commissioning for all systems, prepare the close out documents such as As built drawings, operation and maintenance manual, warranty certificates for all the mechanical systems and equipment’s. handing over the project to the client and to the private affairs maintenance team.
2. Modern Architecture Company (MACC) March 2018 Till May 2020
Sharma Complex – North Project
Mechanical Superintendent
New construction of Royal palace located in Sharma along the coast of the red sea.
Responsibilities:
Follow up the material submittals and the shop drawings with the subcontractors and the approval with the consultant, follow the progress on site if meets with the schedule and the time frame arrange and attend meetings with the mechanical subcontractors, consultant and the maintenance team, coordinate with all departments, Installation of AHU’S, FCU’S, Exhaust Fans, Chillers, ETS room such as chilled water secondary pumps, heat exchanger, water softener, installation of FM200 System, Foam System, firefighting system, Installation of complete BMS system, testing and commissioning for firefighting system, HVAC system air and water balancing for HVAC system, plumbing system, BMS testing and commissioning, complete all close out documents such as As built drawings, operation and maintenance manuals, warranty certificates for all equipment’s and systems. Handing over the project to the client and to the private affairs maintenance team.
1.Saudi Oger Ltd.KSA – JEDDAH
King Abdullah University Of Science And Technology (Kaust) July 2016 Till April 2018
HVAC Supervisor
Responsible of vav department as well as fcu and exhaust fan PPM and RM, attend weekly meetings with client, follow up material status with purchasing department, work on Maximo.
2.Saudi Oger Ltd. KSA – Jeddah Jan. 2015 Till July 16
Aziziah Island Palace 050-P New Modification
Mechanical Superintendent
Modify all Mechanical Equipment's such as all HVAC equipment's, firefighting, gas detection system and plumbing works, installation of chillers, pumps, package unites, AHU'S, exhaust and pressurization fans, laundry machines, planning for all mechanical activities, prepare site management Meetings with subcontractors supervise contractors progress invoices
Coordination with all other activities, follow up material delivery and approval, testing commissioning and trouble shooting.
3.Saudi Oger Ltd. KSA – Jeddah
Bay La Sun –8456 March 2008 Dec. 2014
King Abdullah Economic City- Rabigh
Mechanical Superintendent
Project Profile
With a total development area of 173 km (66.8 sq mi), the city is located along the coast of the Red Sea. This city is considered a commercial hub of the kingdom. The total cost of the city is $86 billion and is divided into six main components: Industrial Zone, Sea Port, Residential Areas, Sea Resort,
My current Job responsibilities are given below:
Estimating material, labor costs, and project timescales
Site Coordination & Site Management meetings.
Assure that Scope of Mechanical works are executed according to applicable Codes & standards.
All Submittal, Material Procurement, Shop Drawings, As Built drawings & Follow up, Testing and Commissioning Schedules & Updating.
Walk thru and Management Visits, Extra Work Claims (VO), Sub- Contractor’s executing Schedules and coordination meetings.
Discussions with sub-contractors and evaluating their Progress.
Making sure project meet Mechanical and construction safety regulations
Provide technical assistance and resolution when Mechanical or engineering problems are encountered in pre-& post execution phases.
Detailing commissioning procedures for Mechanical installations.
Complete installation and Testing & Commissioning for H.V.A.C system (Chilled water pumps, exhaust fans and fan coil unite)
Complete Installation and Testing & Commissioning for Fire Fighting System (Fire Fighting Pumps, FM 200 and foam System)
Complete Installation and Testing & Commissioning for BMS System and (Domestic water system including booster pumps, circulating and transfer pumps)
4.Saudi Oger LTD – Riyadh November 2007 to March 2008
Pension Fund Building
Mechanical Superintendent
Testing and commissioning.
Air Balancing for H.V.A.C system and hand it over to client.
5.ASABBAGH SERVICES FOR ELECTRO- MECHANICAL WORKS December 2005 to 2007
Project Manager of Bilad Bank in East and West Regions.
My current Job responsibilities are given below:
Include all mechanical works of field related projects, negotiating with client and consultants, preparing project schedule, arranging regular meeting(s) that are related to the project works as well as supervision and follow up till handing over the project. Installation of package unites ducted split and chiller system complete with ducting works testing commissioning and started following up the sub-contractors work and invoices till handing over the project. Arranging material submittals as per the project specification arrange shop drawings and submit for approval.
6.CONSOLIDATED CONTRACTORS INTERNATIONAL CO., (C.C.C) 2004-2005
KHAZAKESTAN (Refinery)
Mechanical Superintendent
Heat tracing for gas lines and valves, lighting system, fire and gas system including the installation of all equipments as well as smoke detectors, duct detectors, horn and beckons, and fire marcharing panel
Termination for all fire equipments, testing and commissioning. Installation of package unites, and chillers arrange as built drawings and submit for approval, arrange material submittals as per the project specifications. Prepare project schedule Testing and commissioning.
7.CONSOLIDATED CONTRACTORS INTERNATIONAL CO., (C.C.C) 1998- 2004
OMAN
Mechanical Superintendent
Installation of Lighting and lightning systems, fire and gas system with all required fittings as per approved drawings and specifications. Testing and commissioning. Installation of chillers and ventilation system arrange shop drawings and as built drawings, arrange material submittals and submit for approval, negotiation with client testing and commissioning
8.ANSALDO COMPANY Lebanon MEP Supervisor 1997-1998
My current Job responsibilities are given below: 66 KV Switchgear
Substation and Step-up Transformer: complete with Bus Duct Excitation Transformers installation and charging oil and termination with Circuit Breaker Gas and Steam Turbine. Testing and commissioning with high voltage test. Installing lightning system and terminated to main grounding system.
9.SIEMENS Lebanon MEP Supervisor 1996-1997
My current Job responsibilities are given below:
Installation of 220 KV Switchgear Substation. Circuit breakers, and serge arrestors, vacuum for the breakers and all the bus bars, and charged Sf6 gas, install the equipments and do the high voltage test.
10.CONSOLIDATED CONTRACTORS INTERNATIONAL CO., (C.C.C) 1994-1996
ABU DHABI
Preventive maintenance For HVAC System such as fan coil unites, chillers and exhaust fans, chilled water pumps and firefighting pumps, AHU'S
11.CONSOLIDATED CONTRACTORS INTERNATIONAL CO., (C.C.C) 1992-1994
YEMEN
Preventive maintenance for HVAC system such as fan coil unites, chillers and exhaust fans, chilled water pumps and firefighting pumps and AHU'S.