HAROLD E. JOHNSON

**** ************ ****

Charleston, South Carolina 29414

Cellular: 843-***-****

E-mail: add3dx@r.postjobfree.com

SUMMARY OF QUALIFICATIONS:

Profile:

Extensive training and experience in various aspects of Project/Site, and Facilities operations management, including quality assurance/quality control, HVAC/R and mechanical engineering support…

Experienced: in managing budgets, coordinating capital expenditures and controlling operational costs; on-site project/building layout; cost controls; materials ordering/expediting; negotiating change orders; preparation of status reports; and all aspects of industrial/ commercial mechanical construction, and refrigeration.

Proficiency: Interpreting blueprints, (P&ID’s), engineering drawings and specifications; HVAC/R pneumatic and DDC controls; energy management systems; Plant commissioning; rotating equipment, i.e. pumps, etc.; OSHA/EPA regulations, federal/state, county and local building and fire code compliance.

Competent: in scheduling, directing and coordinating multifarious construction disciplines to achieve desired results, and ensuring adherence to safety, quality craftsmanship and completion schedules.

Knowledgeable: ISO 9001-14001 standards; SAP; TPM; 5-S procedures; and SAP computer system; trend and failure analysis; CMMS (Computer Maintenance Management Systems); AS 400; MS Windows XP; MS Office Suite (Word, Excel, PowerPoint, Access, Outlook), Microsoft project.

Established: mechanical, technical, organizational, leadership, administrative, communication, problem resolution, time management and customer service/relations skills…Motivated team leader and player.

EMPLOYMENT HISTORY:

May 2018 Project Site Manager/ Superintendent

Present Structural Associates Inc. DLA/DFSP Repair two 18" fuel receipt lines, and pipe supports. Chas. SC, USACE

This is a Joint Base Charleston, USACE project to repair two 18” jet fuel “A” receipt lines. This encompasses abrasive blasting, painting, and new concrete pipe supports with HDPE rests, for 3.9 miles of pipe work and supports.

My duties were overseeing all environmental permits and interaction with base civil engineering, SCDHEC, and our outside contract engineering for SWPPP and wetlands permits.

Ensure that any necessary licenses and permits are obtained; and that they are properly displayed with a copy in the project files prior to commencement of related work.

Ensure that the project prime contractors maintain as-built documentation.

Oversee and manage all subcontracts for the project, staffing, work assignments, job site organization, and overseeing job site safety.

Responsibility for planning, coordinating, evaluating, and scheduling the work to ensure that required standards of quality, schedule, cost goals, and contract compliance are met. Assure all work is installed in accordance with contract documents. Proficiency in all divisions of work, methods, materials, scheduling and cost control.

Also responsible for interaction with Naval Weapons Station base utilities, dig permits, all contract security issues, and with DFSP fuel support and fuel transfer.

Evaluate the necessity and accuracy of all contractor change order proposals; and prepare Statements of Work and any modifications or change orders as may be required. Receive submittals and reviews for completeness and determine whether the project staff, Design Engineer, or the Architectural/Engineering (A/E) performing construction phase services should review and provide comments and recommendations for acceptance of the submittals, for the USACE.

Demonstrate and adhere to all work safety policies, and procedures including OSHA and any local authorities governing requirements, to include US Gov (EM-385)

December Project Site Manager/Superintendent/ QC

May 2018 Kear Civil Corp. DFSP Fuel Containment, Charleston SC, Contract US Army Corp of Engineers

Plan, manage, coordinate, and execute the fueling facility project from the field, while providing administrative expertise to the entire project team.

Oversee and manage all subcontracts for the project, staffing, work assignments, job site organization, and job site safety.

Direct field personnel to achieve a safe and conforming completion of this project. Stay on schedule, within budget, and comply with the specifications, drawings and regulations.

Prepare proposed technical approach and cost relation the Quality program implementation. Prepare inspection requirements, and testing plan. Prepare targeted field forms.

Implement the field 3-phase Quality Control process in accordance with USACE construction quality management for contractor training.

Also responsible for internal distribution of all project related documentation for review and revisions as required. To include orchestrating the internal resources needed for project execution, (i.e. Materials, Document Control, QA/QC, Fabrication and Engineering.)

Evaluate the necessity and accuracy of any contractor change order proposals; and prepare Statements of Work and any modifications or change orders as may be required. Receive submittals and reviews for completeness and determine whether the project staff, Design Engineer, or the Architectural/Engineering (A/E) performing construction phase services should review and provide comments and recommendations for acceptance of the submittals. Track the timeliness of submittals due from the contractor, their review, and response/return.

Demonstrate and adhere to all work safety policies and procedures including OSHA and any local authorities governing requirements, (EM-385)

2016 to 2018 Project Manager/Lead Systems Engineer

AHT Systems, Charleston S.C. General Contracting, Commercial Build

Ensure safe practices are used in the execution of project work

Ensure that an appropriate safety and accident prevention plan is implemented on each project contract; reviews, monitors and coordinates project safety issues with the Construction Support Division.

Responsibilities include, but not limited to, site work, all concrete installation, structural steel, all masonry work, roof work etc...

Experience working in occupied buildings.

Responsibility for planning, coordinating, evaluating, and scheduling the work to ensure that required standards of quality, schedule, cost goals, and contract compliance are met. Assure all work is installed in accordance with contract documents. Proficiency in all divisions of work, methods, materials, scheduling and cost control.

Ensure appropriate supervision and quality control inspections of all work. Coordinate the work of multiple subcontractors and lead subcontractor meetings on a regular basis. Also, responsible for resolving construction issues to maintain productivity of subcontractors.

Evaluate the necessity and accuracy of any contractor change order proposals; and prepare Statements of Work and any modifications or change orders as may be required. Receives submittals and reviews for completeness and determines whether the project staff, Design Engineer, or the Architectural/Engineering (A/E) performing construction phase services should review and provide comments and recommendations for acceptance of the submittals. Track the timeliness of submittals due from the contractor, their review, and response/return.

Prepare responses to Requests for information (RFI) for questions related to engineering. Evaluates proposed submittal substitutions with engineering implications; makes recommendations to the Project Engineer.

Ensure that any necessary licenses and permits are obtained; and that they are properly displayed with a copy in the project files prior to commencement of related work.

Ensure that the project contractors maintain as-built documentation.

March 2015 Site Manager/Project Manager

to Feb 2016 Hamon Deltak, CCPP, Heat Recovery Steam Generator, (HRSG) Sabic Plastics, Mt. Vernon, In.

Scheduled, managed, and coordinated all aspects of the new construction of a modular HRSG, start up and commissioning. This was a single wide, modular unit behind twin 85 Mw GE gas turbine, or a combined cycle power plant.

Coordinated estimating and pre-construction efforts, oversee project requirements, and benchmarks.

Managed labor requirements and productivity, generate tracking reports.

I also developed solutions to cost challenges, tracked and reported safety metrics.

Communicated progress to management, also responsible for internal distribution of all project related documentation for review, and revisions as required. To include orchestrating the internal resources needed for project execution, (i.e. Materials, Document Control, QA/QC, Fabrication and Engineering.)

Accountable for ensuring optimum customer service, and satisfaction, project operations safety, and completing project in a timely manner, and within budgeted guidelines.

This project was completed on time and on budget.

October 2014 Site Manager/Field Engineering

to Feb. 2015 TAS Energy, Houston Texas, Paisley Geothermal Power Plant, SV Electrification, Paisley Oregon

Managed, and coordinated all phases of new construction, commissioning, and startup of a small 3.6 Mw ORC, Binary power plant. Refrigerant used was 134a, with water condensing.

This is a single unit power plant with a single output. Overall responsible for management of a $40 million project.

My responsibilities encompassed installation of all contract mechanical, (piping, duct work etc...) work, Turbine expander (BNI), gear boxes, also plant condensing to include all structural, installation of modular skids and associated piping, through plant commissioning, startup and close out.

My role was to establish, and maintain professional relationships with owners, architects, engineers, subcontractors and suppliers and managing the field labor force and negotiations with subcontractors.

My other responsibilities were for overseeing the administration and execution of assigned project, and contractors in a safe, profitable and timely manner and within customer specifications and expectations.

Duties were to assume shared customer interface for engineering, deliver and construction issues with TAS Sr. Project Management.

Managed the installation and implementation of all plant controls, PLC, HMI screens. Confirm and demonstrate functionality of processed controls, working with onsite controls engineers to completion and turnover to end user.

Also responsible for internal distribution of all project related documentation for review, and revisions as required. To include orchestrating the internal resources needed for project execution, (i.e. Materials, Document Control, QA/QC, Fabrication and Engineering.)

Demonstrate and adhere to all work safety policies and procedures including OSHA and any local authorities governing requirements.

2013 - 2014

Site Manager/Field Engineer

2010

TAS Energy, Houston, Texas Patua Geothermal Power Plant, Gradient LLC, Fallon Nevada,

All TAS Energy work is common to the others detailed in this resume. I have also managed many international projects for TAS Energy as well during my tenure with this organization.

Site Manager/Field Engineer

TAS Energy, Houston Texas, Neal Hot Springs, Geothermal Power Plant, US Geothermal Inc. Vale Oregon.

2007 to 2010 Project Manager/Field Engineer

TAS Energy, Houston Texas, Imperial Irrigation District Gas Turbine Power Plant, Niland, California

Directed and managed the installation of turbine inlet cooling for two GE 50 Mw gas turbines. Responsible for all construction and pipe installation, also refrigerant handling and transfer. This was a plant chiller retrofit, all equipment was FES. Two 2500-ton chillers in series, approximately 80, 000 lbs. of refrigerant R-22

Managed construction project, including ordering and expediting of materials and equipment; supervising of trades personnel; maintaining personnel/safety training records, employee payroll time sheets, cost analysis, etc.; preparing/submitting project status reports to corporate management.

Read blueprints, (P&ID’s) to determine location, size, capacity, and type of components needed to build refrigeration system.

Schedule work with customer and initiate work orders, house requisitions and orders from stock.

My role was to establish and maintain professional relationships with owners, architects, engineers, subcontractors and suppliers and managing the field labor force and negotiations with subcontractors when necessary. Managed up to 25 employees to include sub-contractors.

Managed the installation and implementation of all plant controls, PLC, HMI screens (proprietary). Confirm and demonstrate functionality of processed controls, working with onsite controls engineers to completion and turnover to end use.

2000 - 2007

Site Manager/Project Safety Manager – Robert Bosch Corporation, Fluor Enterprises, North Charleston,

South Carolina.

Provided contracted plant maintenance support services to the Robert Bosch corporation, including all mechanical, i.e. plant HVAC, refrigeration equipment, chilled/hot water system and controls, seven (centrifugal and screw type) chillers up to 2000 tons each.

Supervised assigned tasks and coordinated a workforce of approximately 40+ maintenance technicians.

Maintenance and repair of all plant refrigeration equipment to include many large cascade systems.

Accountable for maintenance of all plant buildings, including electrical systems/components, switchgear design loads, per NEC, all pump and motor wiring loads, etc…plumbing and infrastructure repairs, and ensuring compliance with applicable national, state, county and city building and fire codes.

Managed procurement of equipment/parts; implemented preventive maintenance program; and oversaw, as the Project Safety Manager, installation and quality assurance aspects of all steam and water piping.

Accountable for managing and monitoring a $10 million annual budget, capital expenditures/operating costs; soliciting bid proposals and selecting contractors and vendors for capital improvement projects.

Completed: Florida Community College, Associate of Science: Refrigeration Technology –

Jacksonville, Florida

Attended: University of Florida, Mechanical Engineering, (Completed 118 Credit Hours) Gainesville, FL

Completed: South Carolina State, and NASCLA, (14state) General Contracting License, Charleston SC

2016 to present.

Completed: South Carolina State License for Construction Management. Charleston SC 2016 to present.

Completed: CEPSCI, DHEC, SWPPP Storm Water pollution Prevention Plan, Certification for erosion

prevention & sediment control inspector # 13996 Clemson University

Certificate: HVACR Efficiency Improvement –CEU’s -- Auburn University, College of Engineering – 2004

Certificate: TPC Training Systems, Study in HVACR – 2003

Certificate: Trane, Centrifugal and Screw, Chiller Operation and Maintenance Courses – 2003

Certificate: Maintenance Management Course – Auburn University, College of Engineering

Certificate: OSHA 10 Construction Outreach Training Course 2013

Certificate: OSHA 30 Construction Outreach Training Course 2018

Certificate: CPR/First Aid Training Course 2018

Completed: 6,000 Hour Apprenticeship with Boilermaker & Ironworker Union # 687

Member: NFPA (National Fire Protection Association) Current member - 2009 to current