MOHAMMED AATIF UMAIR

Email: add157@r.postjobfree.com

SAP# 80002806

MOBILE: +917*********

PERSONAL DATA

DATE OF BIRTH : June 02, 1979

NATIONALITY : INDIAN

QUALIFICATION : Bachelor of Engineer

GULF EXPERIENCE : 12 Years

TOTAL EXPERIENCE : 16 Years

DRIVING LICENSE : Valid Indian / Saudi Driving License

POSITION APPLIED : Instrumentation and control systems engineer

PROFESSIONAL EXPERIENCE

Oct 2016 Dec 2019

Saudi Aramco (Dhahran EDRC)(PKG#7) QC Supervisor (E,I & C)

Jul 2014 Sep 2016

Saudi Aramco (Rastanura Refinery) QC Inspector Instrument and Control systems

March 2013 – Jun 2014

Saudi Aramco (Juaymah Tank farm) Project Engineer Instrumentation & control systems

Dec 2010 – Feb 2013

Saudi Aramco (Rastanura Terminal south) Instrument & Ctrl system Engineer

Jul 2010 – Dec 2010

Saudi Kayan (Sabic-HDPE) QC-Instrument and control system Inspector

Jan 2008 – Jun 2010

Saudi Kayan (Sabic-Poly carbonate) QC-Instrument and control systems Inspector

Sep 2006 – Dec 2007

Gulf Farabi QC-Instrument Inspector

Feb 2004- Aug 2006

Sol Chemical Industries Junior Engineer

PROFESSIONAL EXPERIENCE:

Oct 2016 to Mar 2019

Client : Saudi Aramco

Company : Khonaini International company Limited

Project : EDRC Package-7.

Location : Dhahran

Position : QC Supervisor (Electrical, Instrumentation and telecommunications)

Job Descriptions

Implement quality control procedures in accordance to project quality control plan.

Responsible for supervising and witnessing the work activities according to quality standards.

witness continuity and Insulation resistance test on low and medium voltage cables before and after cable pulling.

Responsible for supervision and witnesses of work activities related to solo run testing of pump motors.

Responsible for supervision and witness of installation and testing of transformers, package substations, (LV&MV) switch gears and Motor control center(MCC).

Monitoring the ongoing inspections on the site and making sure the QC Inspectors are full time available to perform the Inspections.

Maintaining the calibration log for the measuring equipment’s.

Preparing the two weeks look ahead inspection schedule and submitting it to the client.

Coordinating with client inspection representatives for closing the LBE’s.

Coordinating with QC Inspectors for raising INCR if the work is not as per the standard and specifications.

July 2014 to Sep 2016

Client : Saudi Aramco

Project : 3rd Party System Interconnection Cogeneration Facilities.

Location : Rastanura Refinery

Position : QC Inspector (Instrument and Control System)

Job Descriptions

Ensure that installations of Instruments at Site as per IFC Drawings, Data sheets and Hook up Drawings.

Review SATIP, SAIC, SATR and Method of statement and quality notification documents.

Responsible in preparing RFI and conduct site inspection with client inspector.

Responsible in preparing documentation related to material receiving RFI’s based on inspection levels.

Conducted site visits with designers for finalizing the cable tray routing design.

Coordinate and prepare various documents such as test, inspection reports.

Involved in preparation and review of loop folder, loop check procedure before releasing it for loop check.

Monitor Calibration of Field Instruments as per SAUDI ARAMCO standard procedures.

March 2013 to Jun 2014

Client : Saudi Aramco

Project : Upgrade Fire alarm siren system

Location : Juaymah Tank farm

Position : Project Engineer

Job Descriptions

Involved in installation, pre-commissioning and commissioning of push buttons, heat sensors of booster pumps and fire alarm siren for the entire tank farm.

Coordinating with the PLC vendor for the installation of Input and output modules in the existing switch rack of control room and upgrading the system.

Involved in loop check activities as per standard procedures with all the relevant loop folder documents.

Supervision of Instrument home run cable laying, branch cable laying, testing and termination.

December 2010 – Feb 2013

Client : Saudi Aramco

Project : Upgrade Auxiliary Equipment

Location : Rastanura Terminal South

Position : Instrument and Control system Engineer

Job Descriptions

Involved in Pre-commissioning, commissioning and Startup of two Aramco supplied Atlas Copco Instrument Air compressors of capacity 125 PSIG.

Involved in Pre-commissioning, commissioning and Start Up of two Aramco supplied SPX Instrument AIR DRYERS.

Installation and SAT of new DCS Experion C300 system including server cabinet, system cabinet, network cabinet, console and marshalling cabinets.

Transfer of Nitrogen Storage Tank Signals from one control Room to another control room.

Transfer of Substation and PIB Signals from old control room to new control room.

Responsible on site for the installation, layout and construction based on project technical specifications and Aramco standards.

Involved in Calibration of Field Instruments at Workshop & on site as per approved standard procedures.

Involved in loop check activities as per standard procedures with all the relevant loop folder documents.

Installation and termination of power cables from UPS and NON UPS Panels to the newly installed Marshalling Cabinets

Supervision of FOC cable laying and termination.

Supervision of Instrument home run cable, branch cable laying, testing and termination.

Installation of Yokogawa Transmitters (Pressure, Temperature, Level, Flow).

Responsible For Pre and Final Loop Checking.

Testing and Pre-Commissioning of Smoke Detectors installed inside the Marshalling cabinets.

July -2010 up to Dec-2010

Position : Quality Control Inspector

Client : Saudi Kayan Petrochemical Company

Location : Jubail, K.S.A

Project : HDPE

Job Descriptions

Ensure that installations of equipment’s at Sites conformed to Local and International Standards such as NEMA, NFPA, ANSI, ISA, and were primarily based on the Construction Drawings and Specifications Copies to Construction Manager / Quality Manager.

Review Inspection test Plan, Method of statement and quality notification documents.

Responsible in preparing field inspection notification package and conduct site inspection with client inspector.

Coordinate and prepare various documents such as test, inspection reports, safety approval prior to implement of work.

Involved in preparation and review of loop folder before releasing it to client for loop check.

Monitor Calibration of Field Instruments at Workshop & on site as per approved standard procedures

Di involved in drafting the work procedure for Instrumentation in conformance to Engineering Standards, Engineering Safety guidelines and policies.

Inspe .

January, 2008 – June 2010

Position : Quality Control Inspector

Client : Saudi Kayan Petrochemical Company.

Project : Poly carbonate

Location : Jubail, K.S.A

Job Description

Ensuring the installation per approved drawings & specifications.

Check and review QA / QC Documentation

Review Inspection test Plan, Method of statement and quality notification documents.

Responsible in preparing field inspection notification package and conduct site inspection with client inspector.

Coordinate and prepare various documents such as test, inspection reports, safety approval prior to implement of work.

Verification of completeness and corrections of inspection reports.

Review turnover packages on documents from construction and startup/ commissioning department.

Verified /checked on site if the installation layout on construction is based on project technical specifications and standard practice of work.

Installation of instruments as per approved hook-up drawing.

Calibration of Instruments/ Detectors/ Control Valve & Shutdown Valve (On/Off Valve, Actuators, PID

Controlled Valve, Relief Valve, Temperature, Pressure, Differential Pressure, Flow, Level, Vibration, Detectors, Analyzers, Switches, Alarms and Sensors).

Install, maintains, repairs, overhauls, calibrates and tests a wide variety of industrial instrumentation that record, indicate, control and regulate level, flow, pressure, temperature, position and water analysis.

Standard termination of signal and power cables.

Loop check, bench and site calibration

Sept .2006 – Dec. 2007

Position : Quality Control Inspector

Client : BIN LADEN.

Project : Gulf Farabi Project

Location : Jubail, K.S.A

Job Description

Review Inspection test Plan, Method of statement and quality notification documents.

Responsible in preparing field inspection notification package and conduct site inspection with client inspector.

Coordinate and prepare various documents such as test, inspection reports, safety approval prior to implement of work.

Verification of completeness and corrections of inspection reports.

Review turnover packages on documents from construction and startup/ commissioning department.

Verified /checked on site if the installation layout on construction is based on project technical specifications and standard practice of work.

Preparation of documents & drawings, material inspection, witness calibration of various electronic/ pneumatic instruments & verify against specification & data sheet.

JUL .2003 – AUG. 2006

Position : Junior Engineer

Company : SOL PHARMACEUTICALS LTD.

Location : Karnataka, INDIA

Job Description

Worked as Junior Engineer responsible for maintenance and operation related activities.

Involved in documentation of the shift wise production.

Install, maintains, repairs, overhauls, calibrates and tests a wide variety of industrial instruments.

Co-ordination with the PLC and Instrument vendors.



Contact this candidate