Andrew Schembri – Construction Manager
https://www.linkedin.com/in/andy-schembri-70a6a944/
Email:
add09o@r.postjobfree.com
Permanent Address:
North Saanich B. C.
V8L 6B3
Tel. 778-***-****
Cell 250-***-****
OBJECTIVE
Construction/Site Manager - Qualified to supervise all trades, seek and solicit new work and supervise construction work in progress.
QUALIFICATIONS
Excellent Interpersonal and Communications Skills
Excellent Customer Service and Public Relation Skills
Proven Leadership and Supervisory Skills
Excellent Organizational Skills
Excellent Problem-Solving and Decision-Making Skills
Excel in Multi-Tasking
Strong Skills in Assessing, Planning, Implementing and Evaluating Activities to meet changing requirements
Solid Work Ethic
Promote Strong Team Player concept
CAREER
DEVELOPMENT
Steamfitter/Pipefitter Red Seal
Gas Fitter Alberta Ticket
Project Management 101
Tap Root Accident Investigation
Resolving Conflict
Effective Communication
Time Management
Suncor Related – Journey to Zero (safety excellence course)
St John’s Standard First Aid Certificate
WHMIS Train the Trainee
H2S Alive
Construction Safety Training System (CSTS)
Ethics Training
DISC
Advanced DISC
Leadership for Safety Excellence
LSE certificate of Proficiency
ASE Projects HSE Leadership
Mine Supervisor Certification
Franklin Covey Training
The 7 Habits for Highly Effective Managers
The Discipline of Execution-Maximizing Performance
Speed of Trust
The 4 Disciplines of Execution: Bronze, Silver and Gold Certificates
CWB Courses
Basic Inspection Methods
Introduction to Welding Processes
W59 Workshop for supervisors and Inspector
EXPERIENCE
Gisborne Group of companies Vancouver Jan.-2019 – current
Construction Manager Overseeing all Gisborne activities At Teck EVO Sparwood B.C.
Demolition of older equipment and deteriorated steel and obsolete piping systems
Installation of new reinforcing steel, equipment, and piping systems
Concluding with prep for and 14-day shutdown to bring new systems online
Construction Manager Overseeing all Gisborne activities at Eagle Gold Mine Mayo Yukon
Installation of equipment and piping systems for leaching style process building
March 2018-June 2018 Construction manager
Tradesmen Enterprises Grand Prairie
Cross coverage and assisting Project Manager in daily running of site
September. 2017 - Mar.2018
Self Employed Mechanical / Piping / Constructability Consultant
January 2017- August.2017 Mech./Piping Superintendent
Pretivm Exploration
BruceJack Gold Mine, Construction North of Stewart B.C. Canada
Overseeing Contractors on installation of equipment and support piping
Overseeing and start - up of Mill Piping & Equipment [ Commissioning]
January 2016 -October 2016: Construction Manager /General Superintendent
Aecom at Grand Rapid Pipeline (TCPL) Fort McKay
Overseeing all aspects of construction of Grand Rapids Pipeline Terminal (The initiating Pump Station) and LACT facilities (The custody Transfer facility).Pipe Line tie ins, Supporting Construction, estimating, scheduling and workface planning.
January 2015-January 2016: Construction Manager
Aecom at TCPL Otter Lake
Overseeing all aspects of construction in Reclamation and Installation of a 28.3 MW gas turbine driven compressor package, pie line tie ins, supporting estimating, scheduling and work face planning
May-December 2014: Construction Manager
URS Husky Hardisty East Tank Farm Addition
Overseeing all aspects of construction in Tank Farm Addition, Pipe line Tie In and supporting estimating, scheduling and work face planning
July 2013-April 2014: Construction Manager
URS Flint – CPC Surmont 2 Project
Overseeing all aspects of construction in water treatment and supporting estimating, scheduling and work face planning
October 2012-July 2013: Construction Manager
URS Flint - Christina Lake Regional Project Phase 2B - B Shift
Overseeing all aspects of construction and supporting estimating, scheduling and work face planning
May 2010-September 2012: Construction Manager
Sherwood Park, AB
FFML Modularization Construction
Overseeing all aspects of construction and supporting estimating, scheduling & work face planning.
August 2007-May 2010: Construction Manager
Flint Energy Services Ltd.
Shell Albian Sands Exp 1, Fort McMurray, AB
Main Focus on Tank Farm portion from Aug 07 to April 09, Earthworks to Commissioning overseeing all aspects of execution.
Main Site, Night Shift Construction Manager, May 09 to May 10
$800M project
TRI .54 Project to date 6.7 million man-hours
1900+ manpower peak day and night shift
Scope consisting of upgrading and repairs of existing retention pond. Installation of shallow and deep undergrounds. All piling. All civil and concrete works. Installing pipe racks. Setting of equipment. All piping and electrical requirements supporting systems consisting of Flare stack, Knock Out Drum, TSRU Columns and Exchangers, SRU Exchanger Structure and Columns, Froth Tank, Froth Surge Drum, Electrical Sub station,1ST and 2ND Stage Settlers, Vapour recovery Unit and Inlet Station.