Name: Muhammad Idrees
POSITION: Manager Planning and Control (EPC & Turnaround)
CURRENT LOCATION: JUBAIL, SAUDI ARABIA
HOME LOCATION: PAKISTAN
PHONE NUMBERS: 009**-*********, 0092-345-***-****
E-MAIL: *********@*******.***
BRIEF JOB HISTORY
Period
Employer
Company / Location
Project/Turnaround
Position on Projects/Turnaround
March 2020 to date
SENDAN International Company Ltd.
ARAMCO/SABIC
EPC Projects
Manager Planning & Control
January 2018
to February 2020
FARABI Petrochemical Jubail
FARABI Petrochemical Jubail
Major Projects for Jubail Expansion
Senior Planning Engineer-Major Projects
May 2013 to December 2017
PETROFAC Saudi Arabia Ltd.
SAUDI ARAMCO
SAUDI ARAMCO JIZAN Refinery and Terminal Project
EPC Planning and Control Engineer
Oct 2010 to March 2013
DESCON Engineering QATAR L.L.C
Dolphin Energy Limited Ras Lafan Qatar
3 years 2011/2012/2013 Turnaround & Maintenance Contract of Dolphin Energy Limited
Turnaround Planning Engineer
May 2010 to August 2010
DESCON Engineering QATAR L.L.C
Qatar Petroleum Dukhan Qatar
Turnaround Of FAHAHIL Pumping and Degassing Station.
Turnaround Planning Engineer
Feb 2010 to April 2010
DESCON Engineering QATAR L.L.C
JGC Japan
Ras Lafan Qatar
Shell Pearl GTL Project
Planning Engineer
January 2009 to January 2010
DESCON Engineering QATAR L.L.C
Five Solios France
Mesaieed Industrial city Qatar
QATALUM ( Qatar Aluminum Smelter Project )
Planning Engineer
November 2007 to December 2008
DESCON Engineering QATAR L.L.C
Technip France
Ras Lafan Qatar
Ras Lafan Olefin Project
Area Planner
BRIEF CAREER PROFILE
Thirteen years professional experience at various levels primarily focused on Project Control, Project Management. Involved in various clients on Project like SAUDI ARAMCO, QATAR PETROLEUM, TECHNIP FRANCE, JGC JAPAN, FIVE SOLIOS FRANCE and FARABI petrochemicals.
Excellent Supervisory experience, including setting goals and objectives, Project development, work planning, work planning and organization, budget monitoring and cost control
Material Management / Procurement of Direct & Indirect Mechanical Materials.
Skilled in communicating with people of differing levels of authority and cultural back grounds.
EDUCATIONAL ATTAINMENT:
Bachelor’s in mechanical engineering (78 %) First Division with HONOURS (September 2003 To September 2007)
University of Engineering and Technology Lahore Pakistan
PROFESSONAL EXPERIENCE OF PROJECTS AND TURNAROUND
1SENDAN International Company Jubail
Responsibilities as Manager Planning & Control
Preparation of all Baseline Schedules for all EPC projects. Direct cooperation with the Client and the site team throughout the approval process
Preparation of the Progress Measurement system for all EPC projects
Preparation of the manpower/ quantities histograms for all projects and levelling of the same
Preparation of tender schedules in cases of sophisticated tender requirements
Supervision of all site planning engineers. Review of outputs, continuous guidance and support.
Frequent visits to all ongoing projects for full awareness of each site’s conditions
Monitoring of the progress of all projects against planned and report accordingly
By Focusing on the weak progress/ productivity results and trends, and through close cooperation with the respective project team: identification of the root causes of time slippages, proposal of specific corrective actions, preparation of the respective recovery measures and follow-up of the results of the corrective actions
Directly involved in relevant contractual issues and preparation of EOT claims.
Assign, train & manage project planners
2FARABI PETROCHEMICAL JUBAIL
Responsibilities as Senior/Lead Planning Engineer
Involved in Development of Project Integrated Schedule
Tracking, monitoring and updating project schedule
Perform project progress monitoring duties for Construction & CSU phases including identifying critical activities and reviewing forecasts with progress achieved to date
Report any risk, opportunities and any mitigation strategies to maintain the project completion date
Planning and Risk Monitoring, Trend Analysis, KPIs setting, Forecasting and Performance
Prepare weekly & Monthly Commissioning reports
Prepare and review man-power requirement as per schedule resource loading
Prepare recovery plans when necessary to meet the project deadlines
3SAUDI ARAMCO JIZAN REFINERY AND TERMINAL PROJECT
Responsibilities as EPC Planning & Control Engineer
Familiarize with Engineering Deliverable Register. Loaded Engineering Budget to Engineering Register. Fixed weights for Engineering Progress and invoicing.
Coordination with Engineering Discipline Leads/ Manager to keep Engineering Register Up to date & running as per contract & approved project control procedure.
Familiar with Procurement Tracking Register loaded with Equipment/ Bulks cost/ weight. To keep procurement register aligned with Engineering Register and updated as per latest vendor schedules.
To prepare and present Engineering & Procurement variances and update the schedule accordingly to forecast and analyse and to predict project health / future.
To prepare Construction PMS with construction subcontractor and keep EPC schedule updated and aligned with subcontractor schedule.
Development of Monthly and weekly progress reports for internal and external reporting.
Detailed analysis of Engineering, Procurement and Construction progress.
Mitigation measures report to Management to recover the lost progress.
4DOLPHIN ENERGY LIMITED (RAS LAFAN QATAR)
Responsibilities as Turnaround Planning Engineer
Work closely with Project Manager & Project Team to plan the activities as per given milestones and management requirement, mobilizing the resources, identification of risks, risks managements, build risk register and execution of job.
Generation and Management of Integrated realistic schedule for the turnaround.
Development of Work Breakdown Structure, definition of activities/tasks, establishment of relationship and estimation of durations, identifying necessary constraints and resource loadings.
Monitoring the progress to ensure that turnaround is progressing as planned & targets are being met.
Development of the Turnaround Execution methodology and generating work packs covering technical issues, isolations, advising on manpower and materials aspects of agreed turnaround work scopes.
Perform monitoring and controlling budgeted cost against earned value cost and raising alarms for activities overflowing the budgeted cost.
Preparation of budget for various turnaround projects against the bid value cost, base line budget and start monitoring again the base value cost.
5QATAR PETROLEUM (Fahahil Degassing & Pumping Station, Dukhan-Qatar)
Responsibilities as Planning Engineer
Prepare the complete resource loaded plan for turnaround/maintenance activities using Primavera P6
Calculation of all required resources to complete the job within planned budget.
Prepare complete resource loaded plan for modification works involved during the turnaround using Primavera/ MS planning Software.
Producing the manpower and equipment Histograms and Mobilization plans for the project and generation of corresponding progress S-Curve for the project using Primavera.
Preparation of completed area wise schedule along with the resources like equipment and manpower to expedite the job.
Preparation of method statements, job packs for individual equipment and participate in TRA (Task Risk Assessment) meetings for critical jobs.
6 SHELL PAERL GTL PROJECT RAS LAFFAN QATAR
Responsibilities as Planning Engineer
Involved in updating the schedule on weekly and monthly basis.
Mitigation measures report to Management to recover the lost progress.
Preparation of weekly and monthly reports for submission to client
Mitigation measures report to Management to recover the lost progress.
7 QATAR ALUMINIUM SMELTER PROJECT (QATALUM)
Responsibilities as Planning Engineer
Planning and scheduling the erection of structure in the inside center of fume treatment plant and for the wet scrubber.
Arrange the Sequence of activities for the erection of gas collector ducts and dual ventilation ducts and their supports along pot room
Progress monitoring for fluidization, compressed and venting air piping system
Determines causes of delays and recommend for corrective action or revision of schedules.
Making the extra work claims against any additional work and site modifications.
8 RAS LAFFAN OLEFIN PROJECT QATAR
Responsibilities as Area Planner
Making 3-months and 4-week look-ahead plans for the assigned areas.
Coordination with Field Engineers to clear technical ambiguities in drawings.
Updating Planning Department on activities related to the discipline in Level-III plan
Identifying the updated requirements of Manpower, Equipments and Material etc.
Monitoring and analysing the progress, efficiency and consumption of direct materials.
To help the Site In-charge and supervisors for problems in materials and other resources.
Raising the Technical Queries to the Contractor for ambiguities in the drawings.
Weekly meetings with client/contractor to discuss targets and problems.
PROFESSIONAL TRAINING, COURSES:
1.Two-month professional training course at “DESCON” Engineering in Plants Services & Construction.
2.CTMP (Construction, Technology, Management & Planning) Training at DESCON Engineering Limited Head, Oct 2007
3.Pre-turnaround, turnaround and post turnaround auditing and CPM (Critical Path Management), Apr 2010
4.Life time membership of Pakistan engineering council Islamabad, bearing membership NO. MECH/21117
5.Primavera P 6 Training from Descon Engineering Limited in house primavera training
COMUTER –AIDED ENGINEERING EXPERTISE
PROJECT MANAGEMENT SOFTWARE:
1.Primavera (P6). Proficient in organizing, scheduling, resource loading. Resource levelling, making progress and efficiency reports, S-curve…. etc
2.Ms Office.
3.SAP