SATHEESH KUMAR V
Electrical & Instrumentation Supervisor (Onshore& Offshore)
Mobil No: +971-*********, +971-*********, +91-994*******
E-mail id: adclrb@r.postjobfree.com
Professional Experience Profile: I Have More than 22 years of experience in various aspects and knowledge in Electrical & Instrumentation, EPCC work, Involved in Construction of Oil Gas platform and supervising the Electrical and Instrument work. I also involved in several countries; local and overseas projects hold various senior positions in the Electrical & Instrumentation Construction.
I was involved in various mega projects, such as Ports, Oil & Gas onshore/offshore, Power Station, Solar Power Station, polymer company, LNG project Construction and installations. I’m able supervising to construct, procurement activities and hand over and Maintenances.
CAREER HISTORY
Present Employer : NATIONAL PETROLEUM CONSTRUCTION COMPANY (NPCC),
Abudhabi, UAE. (Part of SENAAT Abu Dhabi)
Role : E & I Senior Supervisor
Duration : From 29th Sep 2015 to 15st March 2019
PROJECTS UNDERGONE
UM LULU PHASE II FULL FIELD DEVELOPMENT PROJECT PACKGE 2, ADNOC (Onshore& Offshore)
I worked as part of team achievement (NPCC) completed the construction of one of the world’s largest offshore oil platforms – the Umm Lulu Gas Treatment Plant (ULGTP) for ADNOC. ( weighing 32,000 metric tons (MT)
EIGHT SAFANIYA SLIPOVER Platforms with Associated Pipelines and Cables,
SAUDI ARAMCO
DUTIES AND RESPONSIBILITIES
Electrical Supervision of Installation of 66 KV & 33 KV Gas Insulated Switch Gears. Installation of 33 KV, 6.6KV (MV) & 415V Switch Gears Transformer, Bus duct, Cable, IRP Panel, LDB, UPS Panel & Battery Bank Installation. All Glanding Termination, Testing, Plant Lighting system. All kinds of Electrical and Instrumentation Installation, Testing. Overall in charge for all instruments support, JB frames, System cabinet frames, system cabinet panel erection, instrument installation for total project, Instrument cable pulling, Glanding & Termination, Loop check, Tubing for Instruments, Instrument Earthing System, As Build & Testing. Site Surveys for new instrument cable rout, preparation of as-built drawing and documents, hook-up drawing, instrument cable trench layouts, cable routing layout, control room- layouts, JB wiring diagram, cable block diagram, and instrument loop diagram and install PLC panel and UPS. Preparation of MTO for instrument works. Laying of instrument control, digital, analog cable and gladding. Termination of instrument cable to PLC side and field JB side and connecting to PLC to DCS.
Install new instrument and install instrument process hook-up, loop checking and testing pre commissioning and commissioning activities of all instruments systems. Attend meeting with contracts, consultants and vendors to review progress on weekly or more frequent basis as required.
DUTIES AND RESPONSIBILITIES
Instrument project involved the Installation of instrumentation, fire& gas, paging intercom system, Installation of all instrument junction boxes, DCS Marshaling cabinets, SIS panel, operator work station, shut down consoles, engineering work station, installation of field instruments, system cabinets, tray work, instrument calibration,Instrument airline .instrument stanchion, Primary cable laying,Secondary cable laying, and doing the technical query also with clients .attending the meeting with the client for clearing the technical problems and weekly meeting attending with client for the progress
Discussion of the project from instrumentation department. Supervising & directing of supervisors while fabrication & erection activities of JB, Panel base frames, Cable tray supports, Instrument Stanchion support, Air manifold, Impulse tubing with corresponding fittings from tapping point using corresponding drawings and As build preparation for fabrication & Installation. Supervising & directing of supervisors while fabrication & erection activities of JB, Panel base frames, Cable tray supports, Instrument Stanchion support, Air manifold, Impulse tubing with corresponding fittings from tapping point using corresponding drawings and As build preparation for fabrication & Installation( hookup. P&ID, Loop checking of cables & Start up System.
1)ALKOMED ENGINEERING (BAHRAIN& CYPRUS Europe Country)
Contractor : BAHRAIN PETROLEM COMPANY & TATWEER PETROLEUM
Project : water treatment plant BAPCO Petrochemical
Duration : 2012 to 2015may 6th
Project : VASILOKO POWER & DESALINATION PROJECT CYPRUS Europe Country (2012to 2013)
Designation : Electrical& Instrumentation supervisor
2) GULF CONSOLIDATED CONTRACTING COMPANY (Saudi Arabia)
Owner : Saudi Aramco
Project : SAUDI ARAMCO BERRI GAS PLANT.
Duration : 2010 to 2011
Designation : Electrical& Instrumentation supervisor
3) TECNIMOUNT ICB PVT LTD, HEAD OFFICE: VIAIE MONTE GRAPPA, 3-20124 MILLAN, ITALY
Projects : ABU DHABI POLIMER PROJECT
Duration : 25.05.2009 to 2010
Designation : Electrical& Instrumentation supervisor
Owner : Abu Dhabi Polymer Company LTD BOROUGE
Main Contractor: Tecnimount S.P.A
Sub-Contractor : Tecnimount ICB /The project PP / PE Plant
4) TECNIMOUNT ICB PVT LTD, HEAD OFFICE: VIAIE MONTE GRAPPA, 3-20124 MILLAN, ITALY
Projects : Kingdom of Saudi Arabia
Duration : 28.03.2007 to 30.04.2009
Designation : Electrical& Instrumentation supervisor
Owner : Tasnee Petrochemical Polymer Company Limited, Jubail
Main Contractor: Tecnimount S.P.A
Sub-Contractor : Tecnimount ICB/ the Project H.D.P /L.D.P, Plant
5) MITSUBISHI HEAVY INDUSTRIES LTD. JAPAN
Sub-Contractor : Bahwan Engineering Co. LLC (Sultanate of OMAN)
Projects : Sohar Fertilizer Project .OMAN
Duration : September 2006
Designation : Electrical& Instrumentation supervisor
Owner : Sohar International Urea & Chemical Industries S.A.O.C.
Main Contractor : Mitsubishi Heavy Industries Ltd.
Sub-Contractor : Bahwan Engineering Co. LLC.
The plant comprises with two trains – Urea Granulation and Liquid Ammonia.
6) DOOSAN HEAVY INDUSTRIES, KOREA
Sub-Contractor : Bahwan Engineering Co. LLC (Sultanate of OMAN)
Projects : Power & Desalination Project. OMAN
Duration : October 2005 – September 2006
Designation : Electrical& Instrumentation supervisor
Client : Sohar Power Company.
Main Contractor : Doosan Heavy Industries.
Sub-Contractor : Bahwan Engineering Co. L
LC. Using 3 Gas turbines and one steam Turbine for electricity generation and 4 unit of Desalination.
7) CHIYODA – FOSTER WHEELER & COMPANY LLC, JAPAN
Sub-Contractor : Bahwan Engineering Co. LLC (Sultanate of OMAN)
Projects : Qalhat LNG Project, OMAN
Duration : January 2003 – September 2005
Designation : Electrical& Instrumentation supervisor
Owner : Oman LNG LLC
EPC Contractor : Chiyoda – Foster Wheeler & Company LLC
Sub-Contractor : Bahwan Engineering Company LLC.
Qalhat LNG Train -3 Project is expansion of Oman LNG Co. LLC Train-1 and Train
9) PROJECT: BPCL KOCHI INDIA REFINERY
Duration : September 1996
Summary : Instrumentation & Electrical work
10) USHA ISPAT IAN PLANT MAHARASHTRA
Duration : September 1997 – August 2000
Summary : Instrumentation & Electrical work
11) TATA POWER PLANT PUNE
Duration : September 2001 – August 2002
Summary : Instrumentation & Electrical work
Leading the work crew as a supervisor holding the responsibility to complete the job with company standard “HSE” policies & STD HSE practices as per the strict Shell safety norms of Petroleum Development. Supervise and approve construction activities and co-ordinate various aspects of project construction including inspections, calibration, installation, testing and laying of optical fibre / copper cable network for instrumentation and telecommunication system, receiving information, materials submissions and working drawings from contractors and processing documentation as required. Supervise prepare Punch list for finished work prior to hand over to client by contractor and ensure the same is cleared to Client satisfaction to carry out other similar or related duties such as advising and assisting contractors foreman in carrying out work to recognized standards, approving the construction methods. To supervise work in accordance with established procedures, contract specifications and specialized Instrument engineering trade standards. Supervising participate in checking detailed drawings and other documentation and co-ordinate mobilization of EPIC Contractor personnel at site. Supervising to Installation of instruments as per AFC drawings. Preparing as-built drawings and test packs as per site deviations etc.…
Schedules, assigns, plans, and monitors the activities of Instrument personnel performing a variety of Instrument works within the approved Project schedule.
Maintain documentation necessary to verify that the work performed meets contractual requirements.
Installation of all type of Instruments, analysers, panels and JBs.
Installation of impulse piping, copper tubing, S.S tubing and for instruments.
Job includes fabrication and installation of ladder and perforated trays and trenching.
Cable laying and termination of signal and power cables, Knowledge fibre optic splicing
Worked in vendor skids like gas metering, air compressors, sea water supply system, and portable water and Demine water system.
Installation activities such as wiring in auxiliary room and field junction box and instruments. Installation activities in Siemens Gas turbine, Alstom Steam Turbine.
Supervision of installations, wiring, impulse and air tubing for process and utility area.
Worked in close coordination with construction contractor to ensure that all the instruments have been installed as per the hook-up drawing and P&ID. Corresponded with Vendor on technical matters to ensure that corrective action is taken whenever necessary. Other duties comprised compiling work packs, completion dossiers overseeing final construction, hook up, com thorough knowledge of the practices, methods, equipment, materials, and tools of the
Instrument trade.
Project involved the Installation of instrumentation, fire& gas, paging intercom system, Installation of all instrument junction boxes, DCS Marshaling cabinets, SIS panel, operator work station, shut down consoles, engineering work station, installation of field instruments, system cabinets, tray work, instrument calibration,Instrument airline .instrument stanchion, Primary cable laying,Secondary cable laying, and doing the technical query also with clients .attending the meeting with the client for clearing the technical problems and weekly meeting attending with client for the progress
Supervision of Installation of 66 KV & 33 KV Gas Insulated Switch Gears. Installation of 33 KV, 6.6KV (MV) & 415V Switch Gears Transformer, Bus duct, Cable, IRP Panel, LDB, UPS Panel & Battery Bank Installation. All Glanding Termination, Testing & Commissioning, Plant Lighting system. All kinds of Electrical and Instrumentation job for LNG Loading Arms Qatar Gas Berth No: 4 & 5 Installation, Testing & Commissioning. Overall in charge for all instruments support, JB frames, System cabinet frames, system cabinet panel erection, instrument installation for total project, Instrument cable pulling, Glanding & Termination, Loop check, Tubing for Instruments, Instrument Earthing System, As Build & Testing. Site Surveys for new instrument cable rout, preparation of as-built drawing and documents, hook-up drawing, instrument cable trench layouts,
Electrical supervisor – Supervise a team of multinational industrial electrician in performing various types of job as per company’s scope of work. Job includes, ensuring the safety of all subordinates, layout of various types of conduit (RSC, IMC, and PVC coated pipes) both overhead and underground. Installation of cable trays of different sizes and heights. Control panel mounting/installation and cable layout prior to termination. Wiring and cable termination according to schedule Also include installation and wiring of low voltage systems. Cable termination and equipment testing. Rectify problems found during preliminary testing. Conduct final test of all the system prior to approval and acceptance of the client/customer.
EDUCATIONAL QUALIFICATION
SSLC, Electrical 2year, Instrumentation Diploma (Diploma certificate attested from UAE embassy)
PERSONAL INFORMATION
Languages Known : English, Hindi, and Malayalam
Given name : SATHEESHKUMAR
Surname : VISWANATHANPILLAI
Date of Birth : 22-05-1974 Place of Issue : MUSCAT
Date of issue passport : 09-08-2017
Date of expiry Passport : 08-08-2027
Passport No : Z3372656
Nationality : INDIAN
Adress : Sateesh Kumar. V, Vazholilkezhakathil, Kollakadavu pot, Mavellikara via, Alappuzha Dist., Kerala, INDIA, pin-690509
DECLARATION
I hereby declare that all the above mentioned information is true to the best of my knowledge.
Thank you
SATHEESH KUMAR V
Abu Dhabi
: