SARVESH KUMAR
Mobile: +971*********
E-Mail: adccip@r.postjobfree.com
Planning Engineer
CAREER GOAL
To work with a progressive organization in which I can contribute my technical skills and experience to enhance my own productivity at the same time achieving the organizational objectives with the attribute of time, quality and discipline
ORGANISATIONAL EXPERIENCE
July 2019 – till date: Bin Sari Specialized Technologies/JPAC Technologies Pvt ltd., (Oil & Gas Division), Abu Dhabi, UAE
Planning Engineer.
Project Name : EPC for replacement of OGD-II & 0 ageing network in BAB field)
(Ongoing)
Client : ADNOC
Consultant : Litwin PEL
Contractor : AL-asab general transport and contracting company.
Responsibilities:
Prepare baseline schedule.
Work Break down structure.
90 Days Look Ahead Schedule.
3weeks Front End Schedule.
Planning Package
Planning & Progress measurement Procedure.
Project Calendar.
Support existing autonomy software by learning and documenting the existing Path Planning algorithms.
Responsible to create, update and maintain data using Primavera 6 software for project planning, scheduling, monitoring and control
Adapt to changes in the working environment, managing competing demands to make the best use of time and resources
Monitor engineering design progress, material and equipment procurement, construction and testing and commissioning status
Work in conjunction with the Planning Manager and project leader in the development of overall project procurement strategy, sequencing, phasing and logistics
Reviewing the planning and scheduling of work on current projects to ensure that activities are effectively planned, resourced and completed
Assists with project controls activities including tracking cost and developing schedules. Develops spreadsheets as requested.
Responsible for day to day document management work load.
Support technical project team and other department.
Responsible for all Documentation and feeling.
Prepare monthly and weekly quality report in co-ordination with quality engineers and assuring safe transmission to its point of distribution.
Co-ordination with quality auditors and providing all necessary details and information required for transparent result and evaluation.
Coordinate construction activities with all relevant parties.
Preparation of weekly productivity report.
Attend weekly progress meeting and discussed critical issue and their improvements.
Updated the actual progress and all related information & comparison analysis.
May 2016 – June 2019: Unistal systems Pvt ltd (New Delhi)
Major Projects Executed:
Project-01:
Project Name : Jaipur to Panipat Naphtha Pipeline Project (JPNPL)
Client : Indian Oil Corporation limited
Contractor : Corrtech International Pvt ltd
Project-02:
Project Name : LAYING, TESTING & COMISSIONING OF 18” DIAMETER BORERI TO CFCL-III,
GADEPAN (BGPL)
Client : GAIL India Limited
PMC : Tractable Engineering Pvt ltd.
Contractor : Mastek Engineering Pvt Ltd
Project-03:
Project Name : KG Basin Pipeline Project, Kakinada
Client : GAIL India limited
Contractor : Kalptaru power transmission Pvt Ltd
Responsibilities:
Prepare baseline schedule.
Work Break down structure
90 Days Look Ahead Schedule
3weeks Front End Schedule
Planning Package
Planning & Progress measurement Procedure
Project Calendar
Working Schedule for engineering & Procurement activities along with progress measurement & reporting system (EDDR – Engineering Document Deliverable Register, PDDR – Procurement Register).
EDDR- Detailed listing of all engineering deliverables covering all drawings, Data sheets, Standards, Specifications, Method Statements, MTO, Material requisitions, technical reports, studies etc. prepared separately for each area/ unit / disciplines.
Detailed Procurement Register indicating Baseline plan, Vendor Schedule, Forecast and actual completion dates
Working Schedule for Construction works along with Progress Measurement & Reporting system.
Progress S-Curve (Area wise/ Phase wise/ Discipline wise etc.)
Manpower Deployment Schedule and Histograms
Construction Plant / Equipment Schedule and construction register.
Submit Daily, Weekly and Monthly Progress Report to Client.
Monitoring of Day to day activities.
Approval welding procedure Qualification.
Welder Qualification Test as per Spec.
Preparing all Pipeline and Piping Job Procedure.
Checking each and every material of the quality and the quality reports.
Preparing and maintain all QC reports like fit up, Bending, Visual. Welding parameters reports, field joint coating, lowering, etc.
Raising MTO(s) for all materials required to additional materials for hydro test etc.
Material receiving inspection.
Ensure that only approved welding procedures are followed & welders are qualified.
SOFTWARE SKILLS
PCMS (Pipeline construction management system)
EDMS (Electronic Document management system)
Primavera P6 Portfolio enterprise management.
PDMS
Advance Diploma in Piping Codes, Standards and specification.
EDUCATIONAL QUALIFICATIONS
2016 Bachelor of Technology in Mechanical Engineering – India
University : Punjab Technical University
Professional Certification
ASNT NDT LEVEL II- Penetrate Testing (PT)
ASNT NDT LEVEL II- Magnetic Particle Testing (MPT)
ASNT NDT LEVEL II- Radiographic Testing (RT)
ASNT NDT LEVEL II- Ultrasonic Testing (UT)
IT FORTE
Designing Tools : AutoCAD 2016
Operating System : Windows Vista, Windows 2007, Windows XP, Window 8 & 10
Packages : MS-Office 2007, 2010, 2013 (Word, Excel, PowerPoint & Outlook
TRAININGS ATTENDE
H2S awareness
Fire Risk Assessment
PERSONAL DETAILS
Date of Birth : 10th Feb 1995
Permanent Address : AT- Bniyachhapar, po+p.s- Gopalpur, Dist. - Gopalganj, State- Bihar
Present Address : Abu Dhabi, UAE
Nationality : Indian
Passport Status : Passport No: P2242492
Languages Known : English, Hindi and Bhojpuri
DECLARATION:
I hereby affirm that all the information furnished above is the best of my knowledge.
Place: Habshan
Date: 27/02/2020 Signature:
(Sarvesh Kumar Rai)