Post Job Free

Resume

Sign in

Mechanical Engineer Plant

Location:
Karachi, Sindh, Pakistan
Posted:
October 29, 2019

Contact this candidate

Resume:

R E S U M E

Personal:

Name SHAKIL AHMED KHAN

Age 52 years

Health Excellent

Height 6.0 Ft

Weight 90 kg

Permanent Address House # C-11 /6, Afnan Duplex Houses, Block 3A Gulstan-e-Johar

Karachi Pakistan.

Phone # 0092 – 342-***-****

0092 - 345-***-****

E-mail Address adapio@r.postjobfree.com.

Education: M.S in Mechanical Engineering from Wayne State

University, Detroit Michigan, USA (1990 – 1992).

B.S in Mechanical Engineering from M.U.E.T, Pakistan

(1983 -1988)

Experience:

07/2011 – Present Joint Manager in Attock Cement Pakistan Ltd

Carried out Responsibilities of field repair & maintenance of

Crushers, Stackers, Recalimers & Raw mill (VRM & Ball Mill).

Carried out responsibilities of Plant conditioning monitoring system

of both lines & maintenance planning & scheduling of each area.

Carried out responsibilities of field repair maintenance / Inspection /

Lubrication & Maintaince master schedule of major equipments.

Carried out responsibilities to implement Plant Management Maintenance System (PMMS)

9/2010 – 04 /2011 Head of Planning & Design in SPCC (Tehama Plant) KSA.

Carried out responsibilities Material procurement and fallow up all

Spare parts [Foreign & Local] of the plant. Including Indent. Purchase

Order & Inspection of spares through Oracle system.

Carried out responsibilities of Plant conditioning monitoring system

& Plant essential modification through planning & design

Carried out Responsibilities of field repair & maintenance of

Equipments & other relevant activities.

Carried out maintenance planning & scheduling of each area [Major

Equipments.} With coordination of other depts.

.

12 /2005 – 07/ 2010 Mechanical Engineer

Saudi Cement Company Hofuf Plant, KSA

* Carried out responsibilities of field repair maintenance of Kiln, cement

Mill & packing plant.(PM&CM task )

* Carried out responsibilities of field repair maintenance, Inspection,

Lubrication & Compressor maintenance of whole Plant.

* Implementation of total lubrication Management at Hofuf Plant

Including, Lubrication Lab, and Filtration unit (Mobile/stationary)

Oil & grease dispensing System

* Carried out Maintenance Planning of each Parents

Machines/Equipments, Including Spare parts Procurement.

* Carried out responsibilities for area Inspection jobs of all equipments

(daily/Weekly Monthly) and maintained the check list of every equipment.

06/2001 – 12/ 2005 * Carried out responsibilities of Plant Management Maintenance

System (PMMS) for Implementing (AS400) with Pro part – I /11

at plant site.

* Implementation of AS400 to record all P.M. & C.M

(Activities) planning in plant through work order, Labor Entery, man-

Hours & Issuing Spares also recorded in same work order of specific

Machine to get total maintenance Cost of specific equipment &

Running hours of parent machine has been recorded in system

* Work on Oracle inventory management for Move order /purchase

Order.

04 /1997 - 06/2001 Sr. Deputy Manager (Repair & Maintenance / Inspection)

Dadabhoy Cement Industries Limited Karachi.

* Carried out repair maintenance of Crushers, Raw mill Area, Cement Mill

and packing plant.

* Carried out Maintenance Planning & scheduling of each Parents

Machine/Equipments,Including Spare Procurement (Local/Foreign)

* Carried out Inspection Schedule of all Equipments & check list of all

major equipment (Daily/Weekly/Monthly)

* Supervise the complete monitoring system Including

Inspection & maintenance schedule, & record keeping of

Equipments

10/1992 - 04/1997 Project Engineer MAS Associate Private Limited

* Project planning & Co-ordination of Lucky Cement Complex

having two lines of 2000 tons / day in respect of foreign & local

Equipments, material procurement & fabrication jobs etc.

* Carried out inspection of manufactured & fabricated

Equipments in Pakistan.& China,

* Carried out Erection, Commissioning & test run of each equipment

(Individually /group wise).of the plant

* Project Planning & coordination of ESP. & modification of

BMR project of Grabwal Cement Company in respect of

Equipments materials procurement (local / foreign

Equipments) Fabrication erection, commissioning & test run

01 /1992 - 10 /1992 Mechanical Engineer Ford Motor Company, Michigan

USA.

* Studied design related problem and developed various

Solution worked on HaiperMash and Finite element Methods.

02/1988 - 08 /1989 Production Engineer Dadabhoy Cement Industries Limited.

* Monitoring the production of each area / section of the plant

From crusher to packing plant .Also responsible for repairing

& trouble shooting of all equipments.

Computer skills:

Operating system. UNIX, MS DOS, SUN, AS400 work station,

Soft ware. Prolog, Turbo prolog, Stanjan, Expert system,

Oracle inventory Management, Excel. Window

98 /2000, & Window XP, MS Word,



Contact this candidate