RESUME
V. Balamurugan
*-****-**********@*****.***
**********@*****.**
Mobile: +965(50995450,98553403)
OBJECTIVE:
Dedication towards the job and making a phenomenal growth that is bilateral to the organization and vice-versa. Never ending thirst to learn and to create new initiatives are my innate behaviors.
ACADEMIC PROFILE:
B. Tech in Civil Engineering –(76.13%)
SRM University, at Tamilnadu (2009-2012)
Diploma in Civil Engineering- (71.54%)
Jaya polytechnic college, at Tamilnadu (2004-2007) Summary of Experience: 12 years in Construction:
5 YEARS- Oil & Gas Refinery Industrial Structures like Longitudinal storage hall(LSH),Substation building, Instrument Building,Sulphur pits. 7 YEARS- Water Supply &Treatment projects/ Reverse Osmosis Plant. CURRENT SUMMARY:- Working as a CIVIL ENGINEER in GOFSCO(Feb2019 To Tilldate) Name of the project: EPF-50 Upgrade to 210 MMSCFD Phase – III, KOC – North Kuwait Client : KOC(Kuwait Oil Company)
Revamp of 50 MBOPD Early Production Facility in North Kuwait, The project envisages enhancing of production capacity of the plant from 175 MMSCFD & 50 MBOPD to 210 MMSCFD & 80 MBOPD.
Scope of work consisted of the installation of Dry & Wet Crude Separators, Pre-heater, Steam Boiler, Stabilizer Column, Side & Bottom Re-boiler, Crude export cooler, Crude export pumps, metering skid, Construction of pipe racks & All supporting foundations, Steel structures erection, all tie-in and assistance to the final commissioning. JURASSIC PRODECTION FACILITIES (JPF) PROJECT Construction of Sulphur pit at Sabriya & East Raudhatain NORTH KUWAIT.(Feb2018 To Feb2019)
Client:- KOC,SCHLUMBERGER
Construction of New Sulfur pits for JPF-1&2 Sabriya & East Rawdatain –Schlumberger.
Sulphur pit 23m length, 9m wide & 6.5 m depth(Under ground pit) total -4nos.
Pit Build with Concrete walls M30 mix concrete supplied by Alkoraf ready mix.
Inside sulphur pit covered with Acid resistance brick (S 50 HF STEULER) 25mm thk Fire lite 2300 VLI and joint pointing filled with( Acid cement AE) 4mm thk and Furadur cement 2mm.
Roof bottom of slab covered with Epoxy 3layer primer plus 2 cover layer(KCH VE)STEULER
Construction of degassing box covered with SS lining inside the pit. Keraflake 6H insulation board 40mm thk filled between wall and SS plate.
Construction of Hydraulic seal pit size(10mx2.5mx1.5m)300mm thk wall.
Schlumberger Reservoir Products FZE entrusted Siirtec Nigi to design and supply two modular Sulphur Recovery Units at Sabriya and East Raudhatain Gas Treatment Plants of the Kuwait Oil Company. The two SRUs will produce 200 t/d of liquid Sulphur each with a recovery of 99.9%
EXPERIENCE PROFILE:
Company : IVRCL LIMITED (Jun2007 - Apr2013)- Assistant Engineer – Civil Execution
As a Junior Engineer (Execution& QS) from June 2007 to July 2009(In Industrial Project) Name of project : 100 MLD Sea water Desalination Plant at Minjur, Chennai. Client : Chennai Metro Water.
Responsibilities : Execution of civil structure of sand filter
Features of sand filter
Type of sand filter : Rapid sand filter
Project value : 510 Crores.
Specialization of sand filter:
Key Focal point for all the levels should be monitor as a micro level error and alignment of filter water distribution pipe and also maintaining the top level of grouting while casting.
Execution of Civil structures of sand filter,Nozzle sleeve mounting should be properly tighten, Filters hydro testing,Distribution pipe clearances & hand over to process team.
After getting the clearance from process team, Conducting BUBBLE TEST for checking of bubble formation uniformly in all the nozzels in a bed.
Get the clearance from Client and start the Media filling after bubble test. Media filled layer by layer and after structure released for Back Washing.
As per procedure Back wash will conduct 8 times and if necessary do additionally also get the Clearance from client.
Client RA bill & sub contractorbill preparation
Quantity surveying, reconciliation of mateials
As an Asst. engineer (Execution& QS) July 2009 - June 2010. Name of project : TSUNAMI HOUSING PROJECT.
Responsibilities : Construction of Tsunami house of 1463 nos, Internal roads,Drainage,Sewerage line.Project value :80.00 Crores.
As an Asst. engineer (Execution & QS) from June 2010 to Dec 2011. Name of project : Hoggenakkal water Supply & Fluorosis Mitigation project Package-1 for TWAD Board (Funded by JICA).Project value : 220 Crores. Responsibilities:
Laying of 600mm dia & Up to 150mm dia – 60 KM Ductile Iron pipe line for treated water transmission up to Sump and OHT. Also MS Pipeline 1500 dia –12 KM from Intake to Water treatment Plant,Water Treatment Plant to Booster Pumping station,BPS to Master Balancing reservoir (240LL).
Checking of Trench formation level.
Checking of Bedding 300mm thick 6mm size aggregate.
Setting Out of pipeline alignment at hilly and dense Forest region.
Excavation & Blasting for Deep hill cutting (24mtr) Height for a length of 300Mtr and width of 40 mtr.
Construction of Thrust Block,Anchor block, Valve chambers, Pump Houses & Sumps.
Hydro Testing of DI, MS, HDPE & PVC pipe line – Also Air test for MS every lap joint using Pressure Gauge.
Specialization of sand filter:
Worked as Site Engineer in the Execution Department
Key Focal point for all the beam level, perforated slab erection and alignment also maintaining the top level,Grouting,support plates fixing and Nozzle fixing with level. Penstock with Actuator erection.
Execution of Civil structures of sand filter,perforated slab casting -936 No’s including 86,500no’s Nozzle sleeve mounting,Filters hydro testing,Distribution pipe clearances & hand over to process team.
After getting the clearance from process team, Conducting BUBBLE TEST for checking of bubble formation uniformly in all 78 perforated slabs in a bed.
Get the clearance from Client and start the Media filling after bubble test. Media filled layer by layer and after structure released for Back Washing.
As per procedure Back wash will conduct 8 times and if necessary do additionally also get the Clearance from client.
As an Asst. engineer (Execution & QS) Dec 2011 to Mar 2013 Name of project : Hogenakkal water Supply & Fluorosis Mitigation project - Package-2 for TWAD Board (Funded by JICA).Project value : 220 Crores. Responsibilities:
Laying of DI & HDPE pipe for Internal Transmission Main (ITM) and Internal Network (INW).
Around 200km for a 350 Habitation and construction of Elevated Master Balancing Reservoirs.
Construction under my supervision of tanks (Capacity of Tanks – 30kL,60kL,1.00L.L to 6.00L.L)
Sump capacity – 10KL,30KL,1.00L.L,5.00L.
Sump capacity – 10KL,30KL,1.00L.L,5.00L
Company : LARSEN & TOUBRO LTD (L&T)- (Mar2013 - Dec 2014) Designation : Engineer (Water Pipeline)
Name of project: TCMC (Thoothukudi City Municipal Corporation Water Supply Project Package-1&2 (Funded by JICA). Project value : 108 Crores. Responsibilities:
Laying of DI & MS pipe for Internal Transmission Main(ITM)
Total 35km (10.85 km 1100mm dia, 24.15km 1200mm dia)
Checking of Trench formation level.
Checking of Bedding 300mm thick with sieved soil.
Setting Out of pipeline alignment parallel National highway.
Excavation & Blasting for the entire 35km stretch.
Construction of Thrust Block, Valve chambers, Pump Houses & Sumps.
Hydro Testing of DI, MS pipe line – Also Air test for MS pipe line every lap joint using Pressure Gauge.
Company : DAELIM INDUSTRIAL CO(Jan2015 - Feb2018)- CIVIL SUPERVISOR Name of the project: SHFP(SULPHUR HANDLING FACILITIES(REVAMP & NEW) at MAA refinery (KUWAIT)- Project value : 147,309,710.00 KD CLIENT:- KNPC(KUWAIT NATIONAL PETROLEUM COMPANY)
Responsibilities:
CIVIL/BUILDING INSPECTOR.
Quantity surveying.
Construction of Civil structures like LSH(LOGITUDINAL STORAGE BUILDING-26880Sq.m.
Preparing of Sub grade using grader to maintain slop like a V-shape (one side 5degree and another side 11degee).
Every 100sq.m area conducting FDT(field density test) for sub grade compaction with 95% of proctor value.
Sloped reinforced paving inside the Longitudinal storage hall 60mx 280m filled with M30 grade concrete supplied by NBTC ready mix concrete.
Construction of Civil structures like ELECTRICAL SUBSTATION, INSTRUMENT BUILDING, CONVEYOR PEDESTALS, ROAD, DITCH, STRUCTURAL PEDESTALS WITH BOLT.
Performed well under my supervision working inside cellar area(confined space permit required) for substation and instrument building for cable pulling and trying work.
All the substation and instrument building build with concrete walls
Insulation inside the building covered with brick wall 115mm thk and 40 mm thk thermal insulation board fixed anchor support.
Floor covered with 3layer primer and 2coat of thick layer epoxy coating gray green colour. Computer Knowledge : Ms-Office & Auto Cad
Additional Skills : Inter Personal Skills, Communication skills,Project Handling Skill, Client meeting discussion skills, Civil Structures & Building skill, Working on dead line etc.
PERSONAL PROFILE:
Father’s name : K.R.Vadivel
Date of Birth : 01.06.1988
Nationality : Indian
Passport Number : S2349246 (valid up to 05/12/2027) Languages Known : English, Hindi, Tamil,Malayalam,telgu Permanent address: No : 23/289 Labour Colony,Guindy, Chennai-600032. Declaration:
The information given above is true to the best of my knowledge. Any further information Will be provided as and when needed.
V.BALAMURUGAN