EARL TRUXON

215-***-****

Email: adam28@r.postjobfree.com

EXPERIENCE

**** ** ****

SUPERINTENDENT, MILLER CONSTRUCTION COMPANY

Responsible for the on-site coordination and supervision of subcontractors, enforcement of site safety and assuring adherence to quality standards established for projects. Additional responsibilities include site mobilization, coordination and supervision of the work of subcontractors, conducting subcontractor coordination meetings and interfacing with Owner’s and Designer’s field representatives.

2010 TO 2017

SUPERINTENDENT, PROJECT MANAGER, tutor perini building corporation

Responsible for the on-site coordination and supervision of subcontractors, enforcement of site safety and assuring adherence to quality standards established for projects. Additional responsibilities include site mobilization, coordination and supervision of the work of subcontractors, conducting subcontractor coordination meetings and interfacing with Owner’s and Designer’s field representatives.

Responsible for preconstruction meetings and coordination, creating project schedules, review of bid drawings, writing and issuing RFIs, writing and issuing Change Orders, assisting the Superintendent to meet the project schedule milestones, attend Owner and Design meeting to submit issues and provide project updates, submit monthly billing to the Owner, review and submit subcontractor bills for payment.

2002 TO 2010

SUPERINTENDENT, PROJECT MANAGER, keating building corporation

Responsible for the on-site coordination and supervision of subcontractors, enforcement of site safety and assuring adherence to quality standards established for projects. Additional responsibilities include site mobilization, coordination and supervision of the work of subcontractors, conducting subcontractor coordination meetings and interfacing with Owner’s and Designer’s field representatives.

Responsible for preconstruction meetings and coordination, creating project schedules, review of bid drawings, writing and issuing RFIs, writing and issuing Change Orders, assisting the Superintendent to meet the project schedule milestones, attend Owner and Design meeting to submit issues and provide project updates, submit monthly billing to the Owner, review and submit subcontractor bills for payment.

1993 TO 2002

ASSIST. SUPERINTENDENT, ASSIST PM, IRWIN & LEIGHTON, INC.

EDUCATION

MONTH YEAR

AA IN BUSINESS ADMINISTRATIN, EDINBORO UNIVERSITY OF PENNSYLVANIA

Concentration in Construction Management

CERTIFICATIONS

OSHA 30 HOUR

First Aid Certification

PROJECT EXPERIENCE

Key Biscayne Yacht Club / Superintendent

Demolition of existing 25,000 s.f. building. Constructed new 56,000 s.f. building. This challenging project included installation of underground utilities in a low tide environment. Extremely detailed interior work was required to meet the level of quality expectations.

Ft. Lauderdale Airport Terminal 4 Expansion / Superintendent

Expansion and renovation of existing Terminal 4 at Ft. Lauderdale International Airport. This complex project included the addition of 500,000 s.f. and renovations of an active airport terminal The work included extensive underground site utility work and multi-level new construction.

Element Hotel – Philadelphia, PA / Superintendent

51 Story, 770,000 s.f., 755 room dual branded hotel complex.

Philadelphia Family Court – Philadelphia, PA / Superintendent

New construction project that included fourteen floors above grade with structural steel frame and unitized curtain wall system. The construction included three subterranean parking levels of cast in place concrete and one mechanical penthouse level.

Abington House on the High Line – New York, NY / Superintendent

33 story tower with 39 residential rental units, retail space and parking garage.

Rapid Repairs (NY Hurricane Sandy Recovery) – New York, NY / Superintendent – Project Manager

The project included emergency repairs for permanent restoration of heat, power and hot water as well as ancillary repairs to make dwellings watertight to protect residents from further damage. Residential properties ranged from individual single family homes to multi-residential buildings

Resorts World New York – Jamaica, NY / Superintendent

The scope of work for this multi phased project included extensive sitework on 64 acres as well as renovations and new construction totaling 736,000 s.f.. The work was performed at the site of the existing Grandstand area and consisted of a four level casino facility with two gaming levels and an events center on the top level. In addition to the gaming and events center, the project included several dining and entertainment venues including outside terrace dining and entertainment spaces.

30th Street Redevelopment: Main Post Office – Phila., PA / Assistant Superintendent – Field Engineer

Renovations to a 927,000 s.f. Main Post Office to convert it to the new regional campus of the IRS which houses roughly 5000 employees. Project scope included extensive architectural, structural and MEP demolition as part of a complete gut out of the former postal operations space, historic restoration of façade and lobby areas, the addition of 14 new elevators, new grand staircase and new MEP and life safety systems.

30th Street Redevelopment: Vehicle Main. Facility – Phila., PA / Assistant Superintendent – Field Eng.

Renovations of existing USPS Vehicle Maintenance Facility to provide retail, parking and mail sorting facilities. The facility included 90,000 s.f. of space for Postal Service Operations and 95,000 s.f. of parking.

The Oasis – El Paso, TX / Superintendent – Project Manager – Project Engineer

Apartment complex consisting of 502 units, 10 buildings, clubhouse and recreation area

Art Institute of Philadelphia – Philadelphia, PA / Project Manager – Assistant Superintendent

Complete interior and exterior renovations of three buildings including the following:

1610 Chestnut St. – Nine story brick building that contains office and classrooms

1622 Chestnut St. – Twelve story brick building that contains offices and classrooms

2300 Market St. – Seven story brick building that contains culinary classrooms and standard classrooms

The Mews at Princeton Junction – Princeton, NJ / Assistant Project Manager – Field Engineer

Apartment complex consisting of 636 units, 14 buildings, club house with pool, tennis court and playground.

Cabrini College– West Residence Hall – Exton, PA/ Assistant PM – Assistant Superintendent

New construction of a 800,000 s.f., four level dormitory

Princeton University – Princeton, NJ / Assistant Superintendent – Assistant Project Manager

Renovation of nine dormitories to meet the State of New Jersey’s fire code requirements by retrofitting the dormitories with sprinkler systems.

Alcon Laboratories – Glenside, PA / Assistant Superintendent – Assistant PM - Field Engineer

New construction of a 400,000 s.f. facility that contained laboratories and production facilities.