July 2019- November 2018
B.B.E Hydro
Keeyask Project
Split lake Man.
Earthworks Surveyor
Duties and Responsibilities include all aspects of earthworks
Surveying for the construction of a hydro dam.
Topographic Surveys for Quantity purposes.
Layout of neat lines and grades for each lift of dykes and coffer dams.
.
April 2019- June 2019
TeraNorth Construction
Detour Gold mine
Construction Surveyor
Duties and Responsibilities include all aspects of construction
Surveying relating to the building of a tailings pond dam.
Topographic Surveys for excavation for dam foundation.
Layout of neat lines and grade setting for the lifts of the tailing pond dam.
July 2017- November 2018
Bird Heavy Civil.
I.O.C Wabush NL
Survey Tech.
Duties and Responsibilities include all aspects of construction
surveying.
Topographic Surveys
Survey calculations and preparing survey reports, using Autocad
Various layout including Drill holes, road layout, and layout for the construction of 150M of multi-plate culvert.
January 2017- July 2017
Pennecon Heavy Civil Ltd.
St. John's NL
Survey Tech.
Duties and Responsibilities include all aspects of construction
surveying for the Maritime Link Project and Switchyard and converter
station at Soldiers Pond.
Topographic Surveys
Installation of bases for transmission structures.
As-built surveys for bases for transmission structures.
Ground prep surveys for pre-cast concrete structures.
Layout of pre-cast concrete structures.
Survey layout for various ground work. ie: slopes, grades and engineered break lines.
October 2014- Present
EPCO Services Ltd.
St. John's NL
Dimensional Control Tech.
Duties and Responsibilities include all aspects of Mechanical
surveying, and Industrial Surveying.
Fit Up and As-Built surveys on offshore modules
Fit Up and As-Built surveys for offshore piping spools
Survey calculations and preparing survey reports, using Autocad
April 2014 – October 2014
H.J O’Connell’s.
Lower Churchill Project -Soldier’s Pond
Survey Tech.
Duties and Responsibilities include all aspects of construction surveying,
.
Site topo, original ground, sub-grade and Final
Layout and As-built Switchyard and Converter station pads
Grade setting for Common placement and final grades
Layout and As-Builts of ditching.
July 2013 - April 2014
Edwards and Associates Ltd.
Lower Churchill Project - Muskrat Falls
Survey Foreman (Working)
Duties and Responsibilities include all aspects of mechanical construction
Surveying and Industrial Surveying.
Calculations and Layouts for Industrial tanks, vessels,
Site Grading
Layout and As-built for forms and Pedistals
Grade setting for Top of Concrete
Bolt setting, and Bolt projections
Firewater line layout and As-built
June 2013
Edwards and Associates Ltd.
Long Harbour Project
Crew Chief
Duties and Responsibilities include all aspects of mechanical construction
surveying, and Industrial Surveying.
Calculations and Layouts for Industrial tanks, vessels,
Site Grading
Layout and As-built for forms and Pedistals
Grade setting for Top of Concrete
Bolt setting, and Bolt projections
Firewater line layout and As-builts
Layout and As-Builts of underground piping .
August 2011- June 2013
D.F.B Driver
Long Harbour Project
Crew Chief
Duties and Responsibilities include all aspects of mechanical construction
surveying, and Industrial Surveying.
Calculations and Layouts for Industrial tanks, vessels, pipeline valves
Site Grading
Layout and As-built for forms and Pedistals
Grade setting for Top of Concrete
Bolt setting, and Bolt projections
Firewater line layout and As-built
Layout and As-Builts of underground piping .
March 2011 – August 2011
William Doyle and Assoc.
St.John's NL
Surveyor
Duties and Responsibilities include
Full topographic surveys for sub divisions.
Water and sewer and private septic fields.
Location Certificates
Cutting Line and Road Reserves, Locating, Laying Out, and setting Survey Markers.
Experienced in using Topcon Total Stn, and Topcon G.P.S.
Sept 2009 – Dec. 2010
Hawco King Renough Ltd.
St.John's NL
Surveyor
Duties and Responsibilities include
Full topographic surveys for sub divisions.
Water and sewer and private septic fields.
Location Certificates
Cutting Line and Road Reserves, Locating, Laying Out, and setting Survey Markers.
Experienced in using Lieca Total Stn, and Lieca G.P.S.
October 2008- Sept 2009
EPCO Services Ltd.
St.John's NL
Surveyor
Duties and Responsibilities include all aspects of Mechanical
surveying, and Industrial Surveying.
Fit Up and As-Built surveys on offshore modules (well heads)
Fit Up and As-Built surveys for offshore piping spools
Survey calculations and preparing survey reports, using Autocad
August 2008- October 2008
Sand's Surveys 2000 LTD.
Fort McMurray AB
Crew Chief
Duties and Responsibilities include all aspects of Construction
surveying and Industrial surveying
Pile layout and Cut offs,
Site Grading
Layout for forms and Pedistals
Grade setting for Top of Concrete
Bolt setting, and Bolt projections
Firewater line layout and As-builts
Layout and As-Builts of underground piping for Manholes and Catch
Basins.
May 2008-July 2008
Foresite Geomatics Limited
Fort McMurray AB.
Crew Chief
Duties and Responsibilities include all aspects of Construction
surveying, and Industrial Surveying.
Industrial Pile layout and grade setting,
Set Plates and Grid Lines
March 2006- May 2008
H.C.S Focus
Fort McMurray Ab.
Crew Chief
Duties and Responsibilities include all aspects of mechanical construction
surveying, and Industrial Surveying.
Calculations and Layouts for roads, buildings, pipe lines, water and sewer.
Industrial Pile layout and grade setting.
Calculations and Layouts for Industrial tanks, vessels, pipeline valves, and Elbows
Experience with Lieca Total Stations and Trimble GPS
September 2005- March 2006
Atcon Construction
Fort McMurray Ab.
Grand Falls N.B
Crew Chief
Duties and Responsibilities include all aspects of Construction
surveying:
Water and Sewer at C.N.R.L Horizon Project, layout and grade setting for catch basins, manholes, and underground pipeing.
Highway Construction, Layout of centerlines, road shoulders, slope stakes, and quantity surveys.
April 2003- September 2005
Thompson Conn Limited
Halifax, Nova Scotia
Crew Chief
Rod Man
Duties and Responsibilities include
Full topographic surveys for sub divisions.
Water and sewer and private septic fields.
Location Certificates, Dept soundings, Static and RTK G.P.S surveys
Cutting Line and Road Reserves, Locating, Laying Out, and setting Survey Markers.
Experienced in using Geodimeter 610, and Leica G.P.S,
August - November 2002
C&T Enterprises
Mary's Harbour NL.
Surveyor
Duties and Responsibilities include:
Bridge construction, running line,
Alignment and grade setting of abutments,
General carpentry and construction work
May - Nov 2001
Department of Works And Transportation
Mary's Harbour NL.
Engineering Aide 1
(Temporary Engineering Aide 2)
Performed survey duties during the construction of the Trans-Labrador Highway. Some of the duties and responsibilities include:
Road construction, Crew chief over four workers,
On site trouble shooting, finding and fixing problems on construction site, Original & Final cross sections, Grade setting
Level, Transit and Total station work.
Supervised the upgrading of the town’s roads in Mary’s Harbour, Labrador. Recorded contractors hours, supervised the digging of and installation of culverts.
Provided mediation between Mary’s Harbour Town Council, Contractors, & Department of Works, Services & Transportatio
May – Nov 2000
Work’s, Services & Transportation
Mary’s Harbour, Labrador
Engineering Aide I
Performed survey duties during the construction of the Trans-Labrador
Highway. Some duties and responsibilities include:
Original & final cross sections, running line & cutting line, cutting curves, Installing B.C’s, E.C’s, & P.I”s,
Crew Chief work
May - Nov 1999
Work’s, Services & Transportation
Mary’s Harbour, Labrador
July - Nov 1998
Labourer 2
(Temporary Engineering Aide 1)
Duties & Responsibilities include:
Road Construction, Original & Final Cross Sections, Grade Settings, Installing B.C’s, E.C’s & P.I’s,
Running Line & Curves, Power Saw work, Cutting Line and Curves and some Rod Man Work
EDUCATION
Construction Surveying
College of the North Atlantic
Happy Valley - Goose Bay Campus
September 1997- June 1998
Graduated High School
St. Mary’s All-Grade School
Class of 1996
Mary’s Harbour
Skills
Trained in project management with some minor experience
Trained in quantity estimating with some minor experience
Experience in mediation, and supervision
Experience in using Surveying Instruments. G.P.S, Total stations and Laser Scanners
Some experience in Drafting, Plotting and Legal Land Surveying
REFERENENCES
Boyd Humby
Human Resource Manger
Bird Heavy Civil
St.John's, NL.
Wayne Pretty
President
EPCO Services
St.John's, NL.
(709) 753 - 7100
Tyler Mahaney
Survey Co-Ordinator
Allnorth Consultants
Rainy River, Ont.
506-***-**** (C)