Professional Experience

CCIII

FST Technical Services

Key Responsibilities:

oManaging Tool Install scope for the 5053-foundry project.

Project Superintendent

Greenland Enterprises

Key Responsibilities:

oDirect day-to-day work for all-site construction on a new 37/mil. Boiler Plant / RO Water System addition. Scope included ground up structure, steel, electrical, mechanical systems/equipment, security, controls, HVAC, TPO roof, emergency generator, site improvements including blast proof fences and walls. Demolition of existing boiler plant and retrofit to RO water plant, locker rooms, showers, maintenance working area.

General Superintendent – Basebuild / CM Services

Marketech International Corp. USA

Key Responsibilities:

oSupervising all basebuild process system scopes that include subtabs, fabs, mains, sub main and lateral installations including steel, lateral racks, chemical systems, and all utility systems (Waste systems, Ultra-pure water systems, CCTV/Barcode, and all associated systems). Direct field staff; facilitate all work efforts including overseeing and directing 12 Superintendents.

Senior Superintendent – Process Systems CM Services

EXYTE

Key Responsibilities:

oSupervising all process scopes that include subfabs, sub main and lateral installations including white steel, lateral racks, chemical systems, and all utility systems (exhaust, waste, specialty gas; bulk gas, ultra-pure water, process cooling water, and lighting). Direct field staff; facilitate all work efforts including overseeing all Process Specific Work Systems (PSSS) for the entire buildout. Most laterals built via OSM/PPMOF techniques.

Project Coordinator (PM)

AMTS

Key Responsibilities:

oManaging Tool Install scope and staff of four CCs.

Process Superintendent

Hoffman Corp.

Key Responsibilities:

oSupervised all MOD3 subfab sub main and lateral installations including white steel, lateral racks, chemical systems, and all utility systems (exhaust, waste, specialty gas; bulk gas, ultra pure water, process cooling water, and lighting). Directed field staff; facilitating all work effort including overseeing all Process Specific Work Systems (PSSS) for the entire buildout. Most laterals built via OSM/PPMOF techniques.

Key Achievement:

oSemiconductor Facility Project, Hillsboro, OR: Was able to supervise all scope what’s been seen to have multiple supervisors through my career.

Area Superintendent

World Wide Professional Solutions, Portfolio of Sites, United States

Key Responsibilities:

oDirect all field operations, manage contracted construction firms, and oversee process quality assurance programs for an f42 project site. Apply LEAN/LPS principals to reduce waste and ensure project profitability. Develop and resent reports regarding project milestones to C-level leadership team.

Key Achievement:

oOcotillo Campus Project, Chandler, AZ: Streamlined and accelerated field operations; completed an aggressive build-out of a key component of a $7B project three months ahead of schedule.

oSemiconductor Facility Project, Malta, NY: Recognized for outstanding leadership/depth of experience; promoted to Area Superintendent.

Process Superintendent

SKANSKA USA

Key Responsibilities:

oSupervised all MOD2 subfab lateral installations including white steel, lateral racks, chemical systems, and all utility systems (exhaust, waste, specialty gas; bulk gas, ultra-pure water, process cooling water, and lighting). Directed field staff; facilitating all work effort supporting Process Specific Work Systems (PSSS) and LEAN/LPS project standards. Coordinated all scanning and development of datum sets for fabrication, subfab, and utility processes.

Key Achievement:

oSemiconductor Facility Project, Hillsboro, OR: Leveraged LEAN/LPS principals to deliver an integral phase a $6B build-out on time and on budget.

Quality/Tech Services Manager

M+W GROUP (EXYTE), Portfolio of Sites, United States

Key Responsibilities:

oManaged site quality control for all trade construction intended for a semiconductor facility in Idaho. Trained and supervised field crews to implement and uphold high-tech, clean room quality standards. Developed work site’s QAP and quality tracking system. Coordinated mockup assessment and acceptance. Monitored and streamlined all documentation control activities.

o

Key Achievement:

oSemiconductor Facility Project, Boise, ID: Achieved quality standards and facilitated on-time delivery of all preconstruction services for $200M capital project.

*Prior position before transfer to Idaho: Process Superintendent

Key Responsibilities:

oDirected process controls within multi-level, multi-use, 130K – 285K sq. ft. industrial manufacturing facilities. Designed work efforts to generate construction documents for next generation capital investments. Managed processing quality systems for specialty/bulk gas, ultra-pure water, waste collection, and water treatment.

Key Achievement:

oSemiconductor Facility Project, Malta, NY: Satisfied all project requirements 2 months, 3 weeks ahead of schedule for an element of a $6B construction project; achieved compliance with zero negative impacts.

oSemiconductor Facility Project, Chandler, AZ: Completed all project and PSSS requirements 7 months ahead of schedule for the $300 Million project; achieved compliance without incident or negative impact.

CM/Superintendent

Hoffman Corp.

Key Responsibilities:

oManaged process conversion project; supervising de-installation and installation of deionized water, bulk gas, chemical, specialty gas, and multiple water treatment systems.

Key Achievement:

oSemiconductor Facility Project, Chandler, AZ: Provided oversight of 80-member crew for two trade partners; completed all PSSS requirements six weeks ahead of schedule in support of a $7B project; successfully facilitated project closeout without incident.

*More work history upon request but there were these positions also held:

•Quality Control Manager, TFS, Inc., Chandler, AZ

•General Foreman, BIG-J, Rio Rancho, NM

•Intel Process Piping Quality Assurance Representative, FST Technical Services, Rio Rancho, NM

Skills

Lean Production System (LPS), Semiconductor Projects, Specialty/Bulk Gas Process, Industrial Construction Processes, BB Regulatory Compliance, C-level Communications, Field Labor Force Management, Bi-Lingual (Spanish & English), Prolog, Primavera, & QuickBase, Quality Assurance (QA), Quality Control (QC), Quality Assurance Plan (QAP), GOVT Work Experience

Education

Certificate

Project Management Coursework

Community College of New Mexico, Albuquerque, NM

Certifications

Lean/LPS, OSHA-10, OSHA-30, MSHA-24, ASME B-31.3, EM 385-1-1 USACE Safety & Health, QCM-USACE, IR Fusion Level I & II, Intel QA/QC, New Mexico Pipefitters License #35389, LLC for Phoenix Resource Solutions.

Other Tools

PM Web, Prolog, Primavera, QuickBase, Touch plan, Microsoft Office Suite (Office, Word, Excel, PowerPoint)



Contact this candidate