Resume:

*

PHILIP M. CAÑO

PERSONAL CONTACT ADDRESS

Filipino Sto. Rosario St. Bogo City, Cebu

Married Saudi Mobile No. +966-*********

Philippine Driving License

Saudi Driving License

Language: English, Tagalog, Visayan, Arabic

E-mail: ad3o2r@r.postjobfree.com

CAREER ADVANTAGE

Highly motivated and results driven Electrical Engineer. Aggressive in identifying and resolving inefficient procedures and processes. Adept in completing demanding projects within crucial timelines. Thorough in details and process oriented; strong follow through skills.

Vast “hands on” experience on a wide variety of projects such as Distribution Planning & Design, Distribution line Construction, Substation Construction and Network Operation & Maintenance.

Specialized in Safety, Project Management Control, Construction in Sub- transmission line and distribution line network. ( UNDERGROUND SYSTEM & OVERHEAD LINES ),115/11kv,13.8kv,33kv, 69/13.2kv.

Knowledgeable in troubleshooting and Maintenance.

Accustomed to manage large multinational workforce in difficult working conditions. PROFILE

A qualified engineer with extensive Electrical Engineering experience in Power Distribution Utilitity Company work permit system basis, Substation construction, Distribution Line Constrution Projects.

Experienced Project Management Control

Experienced in Distribution line Construction and Substation Construction

Experienced in Live line troubleshooting Sub-Transmission and Distribution in entire System. PROFESSIONAL QUALIFICATION

Philippine Registered Electrical Engineer – License No. 0033724

Member: Institute of Integrated Electrical Engineers of the Phils. CIT Chapter 1997-present EDUCATIONAL BACKGROUND

Cebu Institute of technology University - Technological Center Philippines Bachelor of Science in Electrical Engineering ( 1996 – 2000 ) 2

AVAILABLE DOCUMENTS

PASSPORT

Number : P8445828A

Date Issue : AUG. 22, 2018

Date Expire : AUG. 21, 2028

TRAINING AND SEMINARS ATTENDED

System Equiptment and Grounding

Power System Representation and Modelling

Electrical and Mechanical Equiptment

Plant tour at Palinpinon Power Plant

Guidelines Governing Occupational safety and Health in the Construction Industry

General Concept in the Application of Programmable Logic Controllers ( PLC )

Electrical Design Concepts of Medium Voltage Substation

Basic Preventive Maintenance Testing of Electrical Equiptment

Principles and Construction of Bruchless A.C. Generator Exemplified by a fabricated/Assembled Miniature Working Model unit out of surplus Accessories.

Ampacity Transmission Technology

SYNERGEE electric Version 3.8.1. Power Engineering Simulation and Analysis Software system presentation and Modelling, Electrical and Mechanical Equiptment

The Orientation on installation and Metering standards and safety practises

Energy Conservation and Electrical and Energy Audith

Operation and Maintenance of Power Substation ( Model: I Power Substation )

Operation and Maintenance of Power Substation ( Model: III Equiptment and System Protections)

Orientation of Installation and Metering Scheme and Standards of VECO, OBO Standards for Electrical applications and Electrical hazards and Safety.

Competency Training and Certification Program in Electric Power Distribution System Engineering on Fundamental Principles and Methods in Power System Analysis, Load Flow Analysis, System Loss Analysis, Short Circuit Analysis, Power System Reliability Analysis and Power System Modelling. National Engineering Center, University of the Philippines.

First AID and CPR Course conducted at SEC Dammam, HQ.

Basic Distribution Protective Relay’s Training Course at Dammam training Institute (SECO).

Distribution Safety Rules at Mubarraz Training Center.

Safe Isolation & Switching Procedures at Mubarraz Training Center. TESTING INTRUMENTS

Insulator Resistance Tester

Hi-Pot tester

Protection Relay Tester

Transformer loss tester

Dielectric Breakdown ( Transformer Oil ) Tester

Insulation Power Factor Tester

Portable Working Standard ( Metering ) Tester

BASIC SOFTWARE APPLICATION

Microsoft OS ( XP, VISTA, WINDOS 7 )

Microsoft Office ( Word, Excel, Powerpoint, Access) 3

AUTOCAD

MICROSTATION

SYNERGEE ( Engineering Modeling Software )

SAP System Software ( Niebras )

SYMDIST ( Engineering Modeling Software )

WMS – Work Management System Software

UDS – Unified Distribution System Software

DPAG ( Engineering Modeling Software )

MeterMate GE ( Metering Software )

WORKING EXPERIENCE HISTORY

Company : SAUDI ELECTRICITY COMPANY ( SECO )

Al-Hassa, KSA

Position : DISTRIBUTION ENGINEER/ PLANNING & DESIGN ENGINEER Inclusive Date : November 2014 – Present

Incharge for the Planning and design Underground System and Overhead line System ( Integration of new constructed Grid Substations, System Improvement of Network, Re-arrangement of feeders, MV &LV Voltage Cable Relocation, Line Conversion from Overhead network to UnderGround network, Augmentations of Unit Substation and RMU( Ring main Unit ).

Directly incharge for planning and design, Prepare Cost Estimates for new BULK COSTUMERS / LARGE COSTUMERS, Such as Medium Voltage and Low Voltages from 1MVA to 35MVA.

Prepare 1 year contingency plan ( 11kv, 13.8kv & 33kv ), Annual Budget for ( System improvement, Integration of feeders, Line conversion, Augmentations and Others.

In charge for the upgrading of electrical distribution of ( 115/13.8KV,11 KV&33KV ) distribution lines Overhead and Underground facilities.

Prepare necessary requirements for electrical Planning and design analysis of certain projects which involves specification, Conductor sizing,Calculation and choosing the right materials needed.

Prepare plans and check the site works of what to be done by the SEC Contractors prior to electrical distribution lines construction and Underground cconstruction.

Prepare Cost estimates plan for material on certain projects, thru UDS, SAP & WMS program.

Directly supervise electrical installation of ( 115/13.8KV,11KV & 33KV) distribution lines OH and UG lines,equipment,grounding,protection, substation facilities and other logistic materials.

Conduct analysis and evaluation of (11 KV,13.8KV&33KV), Overhead lines and Underground such as feeder load evaluation,Voltage regulation, Power Quality, Power Reliability, Protection rating,transformer load management,power factor correction, system loss reduction, Capacitor placement, AVR & ACR placement, thru Engineering Software SYMDIST modeling.

Prepare weekly Critical material report and weekly required material for transfer from other sister’s warehouse to be able to meet the requirements need for operation, maintenance and construction. PROJECTS ACCOMPLISHMENT – Substations (115KV/13.8/33KV & 34.5KV )

ABQAIQ#3 Power Substations, (3X67.5MVA) – Mar 2016.

UGAIR “A” Power Substations, (3x67.5MVA) – Feb2017.

UGAIR “B” Power Substations, (3x67.5MVA) – Apr2017.

FOODAH Power Substations, (3x67.5MVA) – Nov.2017.

SUPPORT INDUSTRY Power Substation, (3x100MVA) – Dec.2017. 4

PROJECTS ACCOMPLISHMENT – BULK Customers / LARGE Customers Projects

SBC CEMENT FACTORY – Contracted Demand (35MVA)

DELTA CORPORATION FACTORY – Contracted Demand (8MVA)

KLYBECK FACTORY – Contracted Demand (8MVA)

FOOD FACTORY – Contracted Demand ( 4MVA )

TORAY INDUSTRIAL FACTORY – Contracted Demand ( 8MVA)

ALBABTAIN INDUSTRIAL FACTORY#2 – Contracted Demand ( 2MVA)

VISION METAL INDUSTRIAL FACTORY – Contracted Demand ( 3MVA)

NATIONAL STEEL FACTORY – Contracted Demand (20MVA)

HIDA WATER TREATMENT PLANT – Contracted Demand (20MVA)

GULF PLY FACTORY – Contracted Demand (8MVA)

NATIONAL SULFUR FACTORY – Contracted Demand (7.5MVA)

EASTERN ALUMINUM FACTORY – Contracted Demand (7MVA)

AL BABTAIN FACTORY – Contracted Demand (8MVA)

NOV FACTORY – Contracted Demand (6MVA)

SAUDI SOAP POWDER FACTORY – Contacted Demand (6MVA)

STEELMESH FACTORY – Contracted Demand (5MVA)

YAMAMA FACTORY – Contracted Demand (5MVA)

3M FACTORY – Contracted Demand (4MVA)

SEWAGE WATER FACTORY – Contracted Demand (4MVA)

GCC#1 LABORATORY FACTORY – Contracted Demand (4MVA)

GCC#2 LABORATORY FACTORY – Contracted Demand (3MVA)

GCC#3 LABORATORY FACTORY – Contracted Demand (1.5MVA)

GCC#4 LABORATORY FACTORY – Contracted Demand (1.5MVA)

MARKIYAH FACTORY – Contracted Demand (3MVA)

ALPHAWOOD FACTROY – Contracted Demand (3MVA)

PETRO CHEMICAL FACTROY – Contracted Demand (3MVA)

SAUDI FOAM FACTORY – Contracted Demand (3MVA)

AL-BABTAIN FACTORY#1 – Contracted Demand (8MVA)

ARABIAN METAL FACTORY – Contracted Demand (5MVA)

SAUDI PETROCHEMICAL FACTORY – Contracted Demand (4.5MVA )

MENAFE FACTORY – Contracted Demand (3MVA)

ARABIAN POWER ELECTRONIC FACTORY – Contracted Demand(2MVA)

ARABIAN METAL & CHEMICAL FACTORY – Contracted Demand(5MVA) Company : DAR AL RIYADH HOLDING LTD.

AL KHOBAR, KSA

Position : Power Transfomer & GIS/ Supervisor Engineer Inclusive Date : August 19, 2013 – September 4, 2014

Supervised, erection & installation, testing & commissioning of various power transformers & attending warranty works in Hyundai Heavy Industries, Co., Ltd., Kindom of Saudi Arabia.

Supervised, erection & installation, testing & commissioning of various Gas Insulated Switchgear ( GIS )

& attending warranty works in Hyundai Heavy Industries, Co., Ltd., Kindom of Saudi Arabia.

Supervised, erection & installation, testing & commissioning of various UPS-500kva transformer and ATS

& attending warranty works in Dar AL Riyadh, Co., Ltd., Kindom of Saudi Arabia. 5

PROJECTS ACCOMPLISHMENT

Supervision and Installation, Vacuuming, Oil Filling and Testing and Commissioning (3x502MVA), BSP 380/115/13.8KV Transformer at SEC-COA, Riyadh Power Plant.

Supervision and Installation, Vacuuming, Oil Filling and Testing and Commissioning (2x60MVAR), BSP 380/115/13.8KV Transformer Shunt Reactor at SEC-COA, Riyadh Power Plant.

Supervision and Installation of UPS and 2 sets of ATS with 500KVA transformer back-up supply online server control monitoring at SEC main headquarters, Riyadh.

Supervision and Installation, testing, Gas vacuuming, Gas Filling, Replacement of defective or damage post insulators during HI-POT test results, HV & LV Cable link Installation, BSP 380/115/13.8KV ( Gas Insulated Switchgear ) GIS at Qatif SEC power plant. Company : CEBU II ELECTRIC COOPERATIVE INC. ( CEBECO II ) Malingin, Bogo City, Cebu

Position : DISRIBUTION ENGINEER / AREA ENGINEER

Inclusive Date : January 2, 2004 – August 15, 2013

Develops a comprehensive system map or single line diagram of the whole area coverage including all protective devices and its characteristics.

Develops a computed short circuit current on all nodes and its fault duties.

Simulate and analyze sizes of protective devices including its appropriate ratings and its characteristics.

Developing protective relay settings for utility and industrial/commercial electrical power Sub transmission and distribution systems.

2. 13.2KV Distribution System Operation and Maintenance Supervisor at Bogo City, Cebu, Philippines.

Directly supervises the execution of programs for Distribution line construction, operation, and maintenance in the area coverage.

Develops weekly work plans to address distribution line deficiencies and ensure an efficient, reliable, and safe delivery of electric power.

Monitors the daily assigned activities performed by the Linemen crew.

Oversees the implementation of Safety Precautionary Measures by the Linemen crew members in the performance of their tasks.

Prepares and maintains accurate records of the status of the distribution system including installed line equipment and substations serving the area coverage.

Keeps track and maintain records of changes and modifications made to the distribution system.

Assists in the preparation of the annual budget and comprehensive plan of the department.

Conduct regular weekly meetings with the crew members in order to map out plans for the coming week, assess previous week’s performance, and listen to their concerns.

Conduct skills upgrading training of crew members and culture development.

Involvement in 2011-2015 Distribution Capital Expenditure (CAPEX) Planning.

SPEARHEADED THE DISTRIBUTION CAPITAL EXPENDITURE (CAPEX) PLANNING : Develops Forecasting Model for Demand and Energy per Costumer Classification, Conduct Technical Simulations and Evaluations on all Distribution Line, Formulate Problem statement based on ERC “Must Meet” Criteria for DU, Conduct Economic Evaluations for Proposed Projects which address Problems on Distribution, Line formulated in Technical Analysis Simulations, Conducts Economic Power Substation, Transformer and Wire Sizing, Develops Network, Non Network, and Other Capex Based Projects. 6

DISTRIBUTION POWER SYSTEM ANALYSIS : Conduct Power System Modeling on all Distribution System Asset/Equipment, Manual and Software Base Calculation on Power Quality Analysis, Manual and Software Base Calculation on System Loss Analysis, Manual and Software Base Calculation on Short-Circuit Analysis, Manual and Software Base Calculation on Load Flow Analysis, Manual and Software Base Calculation on Power Reliability Analysis. Company : SOUTHERN TELECOMMUNICATION COMPANY ( SOTELCO ) Dela Vina, Bogo City, Cebu

Position : QUALITY CONTROL ENGINEER

Inclusive Date : December 2002 - December 2003

Conduct a routine inspection for all the support equipment’s especially back-up generator/ Facilities of the entire building

Monitor electrical and Mechanical during major works onsite involving power failure

Evaluate the new installation especially the wiring standards

Coordinate central office for the purchasing especially out of stock – (Cable wires, wire holder, modem etc.)

Conduct weekly meeting with the lineman crew for the improvement of service for the satisfaction of member consumers.

Responsible in making estimate of electrical works, reading schematic diagram.

In-charge in the implementation and supervision in undertaking of electrical works.

Preparing for submission of sample materials prior for approval or conform to relevant approved equivalent standard.

Verify that the installed equipment/system meet with the specified design intent through a series of test and adjustment.

Coordinated closely w/ line foreman w/ regards to some technical, material or even resource issues those effects on site.

Attend project staff meeting, construction coordination meeting, and site walkthrough together with designer and owner representative.

Company : VISAYAN ELECTRIC COMPANY ( VECO )

Banilad, Cebu City

Position : CADET ENGINEER

Inclusive Date : July 2001 – Dec. 2001

Assigned to system and engineering department, Applicant section

Involved in conducting transformer load networking survey that can be use in estimate and design for electrification (Three phase, V-phase, 1-phase, Open secondary).

Involved in preventive maintenance undertaking on a different VECO substation and actual hands-on. Initiate line upgrading on low voltage areas, (Re-conductoring or replace existing line conductor with a bigger size or capacity, Upgrade service drop wires by installing secondary line, Upgrade secondary line by installing primary line so that a distribution transformer can be installed, Upgrade overloaded single-phase primary line to v-phase or two-phase primary line, Upgrade overloaded to v-phase or two-phase primary line to three-phase primary line.)

Assessing and reporting safety hazard associated with maintenance of equipment.

Make a design of the distribution lines structure and computation of transformer requirement especially the large load thru DPAG software.

7