WORK EXPERIENCES:

MAKATI DEVELOPMENT CORPORATION

MDC Corporate Center Radiant Street,

Building and Civil Engineering Contractors

ARCA South Western Bicutan,Taguig City

June 03, 2019- June 30, 2020

Project : Ayala Malls Vermosa -Retail

Imus Cavite Philippines

Position : Land Surveyor

Duties and Responsibilities

Establishment of the property boundary using survey instruments before the start of construction based from relocation survey.

Establishment of horizontal and vertical control points within the project area

Establishment of construction gridlines for vertical Projects

Layout of the building footprint for Vertical Projects.

Perform survey computation, both manual and computerized

Conduct as-built, settings and other layout surveys

Ensure the implementation of the quality plans and objectives of the project

Perform task in accordance with the processes defined in the company’s standards

Performs other related tasks that may be assigned from time to time.

NATIONAL WHEEL J & P L.L.C.

Building & Civil Engineering Contractors

P.O.BOX 4624 DUBAI UNITED ARAB EMIRATES

March 04, 2017 to Dec. 15, 2017 (Finished Contract)

Project : AL MAKTOUM INTERNATIONAL AIRPORT SOUTH DUBAI UAE

Position : Land Surveyor

Duties and Responsibilities

Establishment of horizontal and vertical control points for fixed reference using TOTAL STATION AND AUTOMATIC LEVEL ( SOKKIA CX SERIES DX SERIES, LAICA) GPS (ARCHER AND TREMBLE)

Profile and cross sectioning of areas covered by site construction area to determine portion to be cut for excavation of 1st layer and 2nd layer basement.

Preparation for apron slab, setting out every 10 meters-20 meters point of apron slab and mark the formation level, sub grade layer, aggregate sub-base course, crushed aggregate base course, polyethylene sheet and the final Portland cement concrete, the height of the apron slab according to the plan.

Lay-out all substation building, water line airfield fuel line, storm water, trench, LV & HV line, manhole, 400hz PIT, street light, communication line, ITS line, cable vision, and installation of all underground utilities.

Paving of new access road inside the airport.

Perform other related works as may assigned.

Client: Dubai Aviation Engineering projects-DAEP

JOANNOU & PARASKEVAIDES QATAR W.L.L.

Building & Civil Engineering Contractors

P.O. BOX 13637, DOHA QATAR

February 23, 2015 to March 03, 2017

Project : Design and Construct New Orbital Highway and Truck Route(PO23)-

Contract 1-New Doha Port to Orbital Highway

Position : Land Surveyor

Duties and Responsibilities

Establishment of horizontal and vertical control points for fixed reference using TOTAL STATION AND AUTOMATIC LEVEL (SOKKIA, CX SERIES, DX SERIES LAICA GTS-700 SERIES NIKKON 300 SERIES,TOP CON-700 SERIES) GPS (ARCHER,GEOMAX AND TREMBLE).

Profile and cross sectioning of areas covered by site construction area to determine portion to be cut for excavation of 3rd 2nd and 1st layer / basement.

Setting out the center line of the roads every 10 meters or 20 meters and the roads limit to determine portion to be cut for sub grade layer, aggregate sub base course, crushed aggregate base course and the final 1st layer and 2nd layer asphalt.

Lay out four interchanges with cross roads, collectors, distributors, overpass and underpass structure.

Lay out TSE line, storm water, manhole, street light ITS line, cable line,trench, LV & HV Line and installation of underground facilities.

Perform other related work as may assigned.

Client: Public Works Authority-Al Andalus

Value: U SD 893,818,878

SUNGDO PHILIPPINES CONSTRUCTION INC.

PETRON BATAAN REFINERY (RMP-2) PROJECT

LIMAY BATAAN, PHILIPPINES

May 25, 2013 – May 15, 2014(Finished Contract)

Project : Refinery Master Plan – 2

Position : Land Surveyor

Total Station, Theodolite and Dumpy Level (SOKKIA)

Duties and Responsibilities:

Perform accurate lay-out of site boundaries, horizontal and vertical control points of construction area.

Ensure that all survey lay-out confirm as shown in the approved construction plan.

Lay-out exact location and elevations of all structure such as foundations, paddings, column, pipe rack, pipe support and horizontal and vertical vessels, steel structure plumbness, compressor pump and exchanger centering for pocket grouting and levelling of flunges, discharge and suction for pipe connectionand final alignment.

Prepare survey data for inspection.

Perform other related works as may assign.

UNITED DEVELOPMENT CORPORATION PROJECT

JOANNOU & PARASKEVAIDES QATAR W.L.L.

Building & Civil Engineering Contractors

P.O. Box 18637, Doha Qatar

January 25, 2009 to December 05, 2013

Project : Qanat Quarters, Pearl Qatar and

Construction of Male and female student housing for Qatar Foundation

Education City

Position : Land Surveyor

TOTAL STATION (SOKKIA -Set 330, 220 series TOPCOM-GTS 700 series)

Automatic Level

Duties and Responsibilities:

Establishment of horizontal and vertical control points for fixed refrain using TOTAL STATION ( SOKKIA,LAICA,TREMBLE TOPCON), GPS( ARCHER,GEOMAX & TREMBLE)

Profile and cross sectioning of areas covered by site construction are to determine portion to be cut for excavation of 2nd and 1st basement.

Lay-out and setting out of vertical and horizontal alignment of concrete column, footing, slabs, doors elevators, windows, stairs, other concrete structure mechanical lay out and electrical lay out.

As built all structure facilities based on design plain such as footing column, other revised structures, water pipe line and other underground facilities.

Setting out required vertical elevation for all architectural finishing.

SAUDI ARAMCO PROJECT

GAMA INSDUSTRY ARABIA LTD.

P.O. Box 20184, Al – Thoqba 31952, K.S.A.

February 10, 2007 – October 10, 2008

Project : Polymer Plant Project (Petro Rabigh )

Position : Land Surveyor

TOTAL STATION ( Sokkia 330, Automatic Level)

Project Description:

Construction of new Polymer Plant ( PC1 and PC3 ) for Petro Rabigh K.S.A. which includes construction of sub- station buildings, process interface building, extrusion building, pellet and powder silo, reactor foundations, pipe rack, equipment and vessel foundation, installation of all underground utilities and paving of new access road inside the plant.

Duties and Responsibilities:

Check survey control points &bench marks given on plan.

Prepare data calculation of all structure given on plan.

Lay-out exact location and elevation of all structures such as foundations, pipe rack, building and underground utilities.

Prepare as built data as built drawing for inspection.

Prepare roads centerline and elevation.

Perform roads other related works as may be assigned.

Prepare as built data/ as built drawing after construction.

BECHTEL INTERNATIONAL PROJECT

BESIX AND PIHL & SON JOINT VENTURE

Equatorial Guinea West Africa

LNG Train I Project

Punta Europa

P.O. Box 2024- Malabo, Bioko Norte

Phone: (240) 267410

ad3mz0@r.postjobfree.com

November 11, 2005 – November 15, 2006

Project : EG LNG Jetty Train I Offshore

Loading Terminal and Marine Facilities Project

Position : Land Surveyor

TOTAL STATION AND GPS ( SOKKIA CX SERIES, Laica GTS - 700 Series

and automatic level)

Duties and Responsibilities:

For Building Survey:

Run vertical and horizontal survey control around the project area.

Prepare of drawing for layout.

Updating the drawing register of plans revise sets.

Preparation of building layout using survey instrument total station includes: voltsposition and elevation, horizontal and vertical alignment and structural erections.

Take off quantities both structural and architectural according to its specification and details.

Coordinate with engineers and designers for queries.

Responsible for field survey for construction of building, roads, bridges, retaining wall, layout of pipes, ditches manhole, pipe supports, staircase, ladder handrail alignment and elevations.

For Piling:

Preparation of data of pipe for setting out by using GPS.

Setting out of the pile position and elevation by using survey instrument total station.

Checking the exact position & elevation before driving the pile.

Mark the cut-off level after piling by using total station.

Installing the crossheads after cutting the pile.

Checking the position & alignment of crossheads before concreting.

Stake out the position of plate bearing and mark center line.

Level the exact elevation of plate bearing.

Supervise for the installation of beam.

Layout all position of pipelines & pipe supports and elevations as well as staircase, ladder, handrail alignment and elevation.

Layout loading terminal and marine facilities

Includes: all volts, elevation and structural erections

Topographic and hydrographic survey.

Performs other related works as may be assigned.

Gather and check field information of as built structures within the project.

LANDMASS DEVELOPMENT CORPORATION

# 12 Magdalene Circle, Magallanes Village

Makati City, Philippines

Tel. No. 02-8528952/02-8528954

November 19, 2002 – July 31, 2005

Project : Realty Developer (Palazzo Bello Subdivision)

Position : Land Surveyor

TOTAL STATION (NIKKON 300 AND 700 Series and automatically level)

Duties and Responsibilities:

Inchange of all boundary tech. description

(Includes Land development & Housing layout)

Supervise & inspect land development construction to ensure that contractor conforms with the plan specification.

Estimate & request of land development and material quantity take off from time to time.

Monitor & supervise land development contractors daily quality activities.

Lay out of water system and drainage line.

Road layout, curb & gutter, right of way sign and project boundaries.

Profile, cross section of roads.

Establish & monitor the exact elevation of sub-grade,base course and finish concrete.

DAEWOO CORPORATION

Sultanate of Oman

Muscat P.O. Box 478 Postal Code 1323, Ak-khuwair

Sohar P.O. Box 277 Postal Code 325, Liwa

April 23, 2001- February 3, 2002

Project : Sohar breakwater Project

Position : Land Surveyor

(GPS, Topcon- GTS 100 & 700 Series and automatic Level )

Duties and Responsibilities:

Run vertical and horizontal survey control around the project area.

Cross-section of rivers to determine what kind of structure to be designed.

Determine shorelines of harbor & rivers from which to draw an outline map of body of water and also by means of sounding the submerged relief of ocean bottom & to know the quantities of underwater excavation.

Crane setting for placing of rock apron and rock armour for exact position and elevation.

Placing core lock for exact position & elevation using global positioning system (GPS).

Layout setting lines for lean concrete.

Prepare layout and check structure for concreting.

Establish exact elevation for concreting of crest wall.

Topographic and hydrographic survey.

FILIPINAS DRAVO CORPORATION

Architecture and Engineering Consultants

2/F PNCC Bldg. Edsa cor. Reliance St. Mandaluyong City

Philippines

May 14, 19996- April 18, 2000

Project : Genesis point Village, Condominium

Irisan, Tuba, Benguet

: South Luzon Toolway (Rehabilitation & Extension)

Living Water Subdivision Project

Pililia, Rizal

: Calbayog-Tacloban City National Highway

( Rehabilatation & Widening)

Position : Land Surveyor

TOTAL STATION (Nikkon 300 and 700 series and automatic level)

Duties and Responsibilities:

Run vertical and horizontal survey control.

Profile and cross-section of road.

Computation and plotting of field data.

Road layout of curb & gutters, right of way and sign and project boundaries.

Layout of water system and drainage line.

Check volume of available filling materials for the project.

Topographic and hydrographic survey.

MA. TERESA S. CESAR

Surveying Office and Associates

Philippines

December 1993- May 1995

Duties and Responsibilities:

Relocation of boundaries.

Parcellary of land.

Computation and plotting of field data.

EDUCATIONAL ATTAINMENT

College : University of the Cordilleras (BCF) Baguio City

Geodetic Engineering

1984- 1988

Secondary : Santo Tomas High School, Mangaldan, Pangasinan

1980-1984

Primary : David Elementary School, Mangaldan, Pangasinan

1974- 1980

Special Skills : AutoCAD knowledgeable (2D & 3D)

Can operate survey instruments

TOTAL STATION (SOKKIA, LAICA, NIKKON, TOPCON 300 AND 700 SERIES)

GPS (ARCHERS, GEOMAX AND TREMBLE)

Automatic Level & Theodolite

Driving proficient

Welding (gas & electric weld )

PERSONAL INFORMATION:

Nickname : Nel

Date of Birth : February 18, 1968

Place of Birth : Mangaldan, Pangasinan, Philippines

Civil Status : Single

SSS No. : 02-1257773-2

Pagibig No. : 121*-****-****

PhilHealth No. : 19-025870305-0

TIN No. : 743********

Passport No. : P8979349A

Driver Lic. No. : A05-12-000878

Nationality : Filipino

Religion : Roman Catholic

Language Spoken : English, Tagalog, Pangasinense, Ilocano

CHARACTER REFERENCES:

Engr. Matheos Agrotis Joannou & Paraskevaides Qatar W.L.L.

Chief Land Surveyor P.O. Box: 18637DOHA-QATAR

+974********

Engr. Jun M. Cabingas Makati Development Corporation

Head Survey Taguig City

091********

Engr. Alfredo Villasper Filipinas Bravo Corporation

Survey Manager PNCC Bldg., cor., Reliance St. Mandaluyong City

I hereby certify that the above information is true and correct to the best of my knowledge and belief.

NELY N. MEJIA

Land Surveyor



Contact this candidate