EDUCATION

Bachelor in Architecture

New York Institute of

Technology

Old Westbury, NY 1999

CERTIFICATIONS

OSHA Construction Safety

& Health (30-Hour)

OSHA 40-Hour

HAZWOPER Training

NYC DOB 4-Hour

Supported Scaffold User

LICENSE

NYFD Construction Fire

Site Safety Manager

COMPUTER SKILLS

MS Suite

MS Project

AutoCAD

Ryan Capozzi is a project management and superintendent professional with over 20 years of experience working on various construction projects ranging from schools, residential towers, medical facilities and laboratories. He has worked with NY agencies such as the DDC and the SCA.

MCG CONSTRUCTION, Bronx, NY 2012 – Present

Formerly Marson Contracting

Superintendent

Responsible for the coordination of all Subcontractors needed to accomplish the assigned Project. Responsible for all necessary coordination between Professional Designers, General Contractors, and Owners.

Montefiore Tower Two

Directed the construction of a $400M, ground up building project of a 280K SF class A medical office building fully leased to Montefiore Medical Center for its new ambulatory care center. The 11-story building includes 12 operating rooms and 4 procedure rooms; an advanced imaging center; onsite laboratory services and pharmacy. Mount Sinai

A 90K SF medical facility project whose renovations included the fitting out of an existing building for medical use

Boyce Thompson Center, Yonkers, NY

A $36M commercial development project approximately 4.5 acres on the site of the former Boyce Thompson Institute including the development of a new center used for medical and retail space. The historic Boyce Thompson building, which was built in the early 1900’s, was restored to its original character. Tasked with coordination between all trades.

.

SKANSKA, New York, NY 2017

United Nations

Superintendent

Oversaw the construction refit of the United Nations Secretariat Building, which included the replacement of the glass on the exterior curtain wall. Collaborated with architects, structural engineers, MEP engineers and design consultants throughout the process. MANAFORT BROTHERS, Bronx, NY 2011 - 2012

Superintendent

Oversaw the project laying the foundation work for the boathouse structure at Pier 26. MARSON CONTRACTING, Bronx, NY 2007 - 2011

Project Manager/Project Superintendent/Field Engineer/Safety Coordinator Responsible for all design and construction phases for multiple projects. Solicited bids from subcontractors and suppliers via Requests for Proposal (RFP) and Sole Source procurement mechanisms; awarded contracts in conjunction with internal legal and financial guidelines. Tracked change orders, potential and actual, through all phases, from mobilization through project closeout. Scheduled material deliveries and onsite presence of skilled trades workers to maximize labor productivity. Projects included:

• Brookhaven National Laboratory. Occupied lab upgrade

• Brookhaven National Laboratory. Laboratory renovation

• Long Island Vets Hospital. Addition to existing building

• Hudson River Pier 25/26. 3 new buildings (2 upland and 1 on the pier)

• DDC Weeksville Heritage Museum Renovation

• Cantilevered out of the ground high-rise building in Downtown Brooklyn Ryan

Capozzi

ad02s1@r.postjobfree.com

516-***-****

WORKS-IN-PROGRESS ASSOCIATES, New York, NY 2006 - 2007 Project Manager/Construction Management

School Construction Authority

Oversaw renovation projects for public schools throughout New York City. Projects involved replacement of all exterior windows and window guards; reinstallation of all A/C units and replacement of A/C brackets; remove and replace fixtures in students’ toilets; remove and replace wall & floor tiles, scrape & paint wall and ceiling in students’ toilets; remove & replace safety systems (exterior security & Intrusion alarm system); remove bricks at selective window lintels, scrape and paint window lintel with rust inhibitive paint

& provide new bricks at window lintels at selected locations; remove and replace fire alarm system; remove and replace elevators; provide new fire rated walls at elevator machine rooms; provide bituminous roof covering over existing skylight located over elevator machine room.

Hudson River Park Trust Pier 76 NYPD Mounted Unit under the Division of Design and Construction Project and Onsite Construction Management In charge of daily on-site construction oversight for a mayoral mandated high profile

$6.2M project under contract to Skanska USA. The goal of the project was to relocate the NYPD Mounted Unit (equestrian) currently housed in another pier in order to commence construction. The approximately 25K SF project included renovation of the south wing of the pier on Hudson River providing space for New York Police Parking Enforcement District (PED) Troop B and the Mounted Unit headquarters which included offices, locker rooms, toilets, storage, horse stalls, hay loft and exercise ring. All components, except the exercise ring, are within the existing pier building envelope; the ring is a tensile structure in the yard adjacent and attached to the building. The associated space for PED included replacing storage, office and locker space which was displaced by the stables. The mounted unit project also included improvements to a parking area to accommodate 40 cars.

METROTECH CONTRACTING CORPORATION, Jamaica, NY 2003 - 2006 Project Manager

Responsibilities included reviewing construction documents, soliciting bids for all trades, drafting subcontracts, conducting meetings, recording and distributing meeting minutes, procuring materials, coordinating all aspects of subcontractors work for parks and landscape projects. Created and implemented site safety plans and provided site supervision.

Pier 84 Hudson River Park Trust

Tasked with setting up field office, setting up job logs, creating submittals, creating shop drawings, RFI’s and Logistical plans. Created safety plan in cooperation with insurance carrier. Conducted internal coordination meetings with subcontractors and reported job needs to upper management. Procured material and scheduled deliveries accordingly. Provided labor and safety supervision. Assisted general superintendent on a full-time basis throughout the duration of the project.

George Washington High School Synthetic Athletic Fields Responsibilities included site supervision on a $1M budgeted project for a 90K SF installation of a new athletic field for public school project. Old Boys High School Synthetic Turf Field

Responsibilities included project management for a new 95K SF athletic field project with a project cost of approximately $5M. The field was designed to accommodate a wide range of athletic activities.

Ryan

Capozzi

ad02s1@r.postjobfree.com

516-***-****

Brooklyn Botanic Garden (BBG) Eastern Parkway Entrance & Related Areas Contract value approximately $ 7M. Erected two new cast in place concrete structures along the Eastern Parkway entrance along with other various restoration projects throughout the garden for the BBG and Department of Design and Construction. Spiral Fountain Battery Park City

New York City Parks Department/Battery Park City Authority (NYCPD/BPCA) Constructed a $1.2M spiral fountain within the Bosque Gardens approximately 60’-0” in diameter. Work included heavy plumbing and stone fabrication. Tasked with shop drawing creation and trade integration.

Bosque Gardens at Battery Park City

Contract value approximately $4.9M. Assisted chief project manager in constructing a park along the waterfront in Battery Park City.

ARCHITECTURAL COMMUNICATIONS, Port Washington, NY 1999 - 2006 Architectural Intern & Independent Consultant

Responsibilities included reviewing building files with local municipality, Survey existing site conditions, creating ground up construction documents, implementing all zoning and code information, meeting with clients to review design needs, schedule and budget. Visited site to conduct construction progress inspections. HIGHLAND ASSOCIATES, New York, NY 1999 - 2003

Architectural Intern

Cornell Thornwood Office Building

Tasked with transferring project from code study to construction documents. Other responsibilities included creating design drawings for presentation, coordinating with In- house team, MEP and structural engineering consultants. The Center for Discovery

Converted a pump building to multiple classroom space while introducing a covered bridge for access. Created design drawings as well as construction documents. Conducted construction inspections and coordinated with MEP and structural engineers. Sterns Bayshore

Responsibilities included the design of the exterior insulation and finish system (EIFS) Façade, surveying existing conditions and reporting existing façade conditions to owner. Eckerd Drugs Accounts

Lead project team with corporate fit-outs and ground up building design. Met with Eckerd Project Mangers to discuss store location and special needs. Surveyed fit-out spaces and made adjustments to the corporate standards to accommodate space. Macy’s Bay Plaza

Worked with senior partners to design and create construction documents. Beginning with feasibility study working toward design concept, hand built chip-board presentation model and presented in-house to federated upper management. Coordinated with all trades.

Old Navy Headquarters

Stationed at the Old Navy Headquarters in construction administration to lead in-house team with the design and construction documents. Created construction documents which altered store standards to comply with applicable building and zoning codes. Coordinated with building management, MEP and structural engineers. Williams Real Estate, 16 West Street

Lobby renovation project in which a new lobby entrance was created. Coordinated work with the building management and owners. Other responsibilities included selection of materials and sources, coordination with lighting designers, and MEP building systems. In charge of creating construction documents including demolition plans. Ryan

Capozzi

ad02s1@r.postjobfree.com

516-***-****

Williams Real Estate, 60 Hudson Street

Assisted with the Design and presentation of the façade restoration to the Landmarks Preservation Commission for the window grille replacements. Visited site to review progress and consulted with building management. Designed and procured a new brickwork security desk seamlessly matching the existing landmark brick. Met with the owner and building management to discuss design intent coupled with material selection. Designed a new security bollard system along with seating promenade. Surveyed existing conditions, demarked all utilities and fill stations. Prepared construction documents as well as D.O.T. submission drawings. Interior Design NYC Buildings Department

Surveyed site and created a new counter for permit processing. Surveyed private residences as well as space to plan and design millwork. MCI WorldCom Telecommunications Projects

Created design layout for UPS room, surveyed site, created office space and rack space, coordinated rack layout with equipment manufacturer & MEP. Responsibilities included review of shop drawings.

60 Hudson Street, Elevator Shaft Conversion

Surveyed site, converted elevator shaft way to mechanical room and horizontal access. 60 Hudson Street, Transformer Vaults

Surveyed site, converted a double height theater into transformer vaults. Created blast proof Con Edison vaults to specifications. Planned heavy demolition to create vaults on the mezzanine level as well as on the ground floor. Coordinated with Con Edison, MEP and structural engineers.

Goldman Sachs & Co.

UOS and generator upgrade project. Tasked with surveying site, designing generator space, and planning logistics for generator installation. Coordinated with the MEP and structural.

TOWN OF NORTH HEMPSTEAD BUILDING DEPT., Manhassett, NY 1997 - 1999 Commissioner’s Assistant

Assisted the commissioner on a daily basis to review proposed plans for conformity to local zoning code as well as life safety code issues. Reviewed building permit applications for accuracy and completeness. Reviewed contractor’s insurance and licenses prior to permit approval, and processed approved permits. Attended variance hearings and performed field inspections assuring conformance to the construction documents.

BLACARSKI PLUMBING & BUILDING, Glen Cove, NY 1993 - 1996 Plumbers Assistant & Contractors Assistant

Assisted master plumbers and carpenters during all phases of construction on multiple projects.