Work Experience 2015 to Current
ADM
Maintenance Superintendent for the Third Largest Flour Mill in the United states.
Manage 24 Maintenance employees total - 2 Supervisors, 2 Leads Mechanics,1
Instrument Tech, Planner Scheduler and MRO Parts Manager . I have
Implemented and integrated a Maximo CMM's system for all plant assets t o
manage all Maintenance Work Orders, PM's, Labor and Parts tracking
management laying a foundation for a Maintenance Excellence Strategy. This
approach has reduced Monthly EDT from 2.7% to .9% Improving plant reliability. I
manage AFE Capital Projects, employee training, department safety programs. I
build teams and mentor leadership to create critical mass with in the
maintenance department to achieve the needed results of a 21 st century
maintenance team.
Phoenix Closures Inc. 2013 to 2015
Maintenance Manager- Manage 25 Mechanics and 1 Assistant Maintenance
Manager to maintain Plastic Injection Molding Production Equipment, Cap Lining
Machines, Conveying Systems, Robotic stackers, Vision systems and Palletizers.
Responsibilities include HVAC chilled water systems. I manage the Maintenance
Budget and Oversee the Maintenance Management system, for PM’s, Work
Orders and Purchasing. Experience includes managing the installation of 5 new
lines and successfully assisting the plant with its start up to reach its capacity.
Kroger Manufacturing Pace Dairy 2009 to 2013.
Maintenance Manager– Manage 19 Personnel and maintain High Speed
Manufacturing Equipment and Robotics systems Including some PLC, My
experience includes, Ammonia Refrigeration, Utilities, Boilers. Manage
Maintenance TPM projects and work order back log for the plant equipment.
Maintain RMP/PSM/Hazmat program. I have Navigated, Managed Capital
Projects Process from start to finish for facilities and other areas of the plant with
in the Kroger system, working with vendors, engineers, and plant personnel to
develop scope and goals of the projects. Using CAP /CAT /CAR’s to submit, track
and execute projects. This experience includes obtaining competitive quotes,
managing budget, scheduling, supervising contractors and managing start up
from start to finish, this Includes training of effected personnel. My Project
experience includes a 6 month Plant A/C Chiller Replacement Project valued at
$480,000 successfully as planned without plant interruption. In my 4+ years of
employment with Kroger Manufacturing I completed an additional 13 Capital and
expense projects totaling $5,000,000 the largest project I
managed included building a plant expansion, with a new automated ammonia
system, for $8 million .During my time I also completed a new boiler install and
upgrading the existing boiler totaling another $325,000. That is a total of
$13,325,000 roughly in a relative short time. I have managed these funds in trust
from the Kroger Company to progress its goals for its customer and the
enterprise. As a Leader I am strong and fair and have received positive feedback
on all leadership surveys. I excel at team building and Leadership. I am a strong
proponent of and for TPM and Maintenance Excellence as well as Six Sigma
process.
Eli Lilly 2002 to 2009
Plant Utilities Maintenance Engineer the first 3 years Lafayette plant
Manage Operate and maintain 400 psi. Coal Stoker Boilers total, plant could
generate 600,000 lbs. per hr. I Managed Plant Potable Water Generation and all
Site Utilities. Responsibilities included overseeing plant power grid, and
generators.1200 hp R22 chillers for chilled water system. Oversee Maintenance
budget/PM programs, project management, and execution.
Maintenance Tech.
Last 3.5 years Perform Maintenance on High speed Manufacturing equipment
Fanuc Robotics Case Packer Palletizers at the Lilly Technology Center
department for making Insulin devices. Work With Maximo PM system in World
Class Manufacturing. Assist with the install of 2 Production line projects for
insulin devices from FAT to running production.
Enron 2001 to 2002
Utilities Maintenance Manager at Lilly Corporate Center, Supervise 12
employees to manage all site utilities, Maintenance and building management.
Responsibilities included overseeing plant power grid, and generators.1200 hp
R22 chillers for chilled water system. Plant Air system management. Worked
Until Enron collapsed.
Murco Foods 2000 to 2001
Contracted to manage 6 month project to over see plant utilities
10 million dollar upgrade, For Boiler, Ammonia Refrigeration and Cooler
expansion for their Beef Packing process.
Tyson Foods Pork Processing 1993 to 2000
: Tysons Operations and Maintenance Manager Last 3 Years
Oversee all Maintenance and Operations in plant utilities for
Boilers and 220,000 lbs. Ammonia Refrigeration systems. Manage 15 employees
Manage all Osha Programs for utilities Process Safety Management/Risk
Management Program/ Wastewater ISO1401 Program. Train and Maintain
On site Hazmat Program. Manage Capital Expenditure’s requests and Project
Management. Including ROI cost Justification and Budgeting maintenance cost.
: Tysons Maintenance Planner for 2 years of plant operation.
Plan generate and order parts for all 12 departments which included a total of
104 maintenance employees. Develop and establish PMs for all equipment.
This Included development of processes to maintain high levels of Maintenance
Reliability with in the planning program. This work included parts management
from ordering to setting up in parts system. Working closely with vendors. Also
handle set up of any new equipment stemming from capital projects and
upgrades.
Writing capital expenditure requests for repairs and upgrades to current and new
equipment.
:Tysons Maintenance Mechanic first 2 yrs. of plant start up. Working in a USDA
Regulated Environment. Doing Mechanical /Electrical/Hydraulic/ Repairs on
production Equipment.
Monon Semi Trailer 1990 to 1993
Work in R&D department as fabricator building /testing prototypes while working
with engineers to improve designs and Lower Cost. Also building and designing
production Jigs using all forms of welding,reading blue print and following
technical Specs. to achieve the goals and objectives of the department.
James E. Turner
Education
In the process of taking college courses for a Bachelors MET/ and an Associates
Design Technology Currently 2 full years into the process
Logansport High School
Graduated 1990
Lincoln Tech /Mechanical Drafting
8.0 Credit hrs. 1992
Tele Train Maintenance Journeyman Apprentice
Complete 1993
RETA Trained For Industrial Refrigeration
Complete 1993
Tele Train Electrician Apprentice
Complete 1994
IIAR 24 Hr. Trained on Ammonia Refrigeration
Complete 1995
40 Hr. Trainer Level A Hazmat
Complete 1996
Hawkeye Community College Maint/Planning
8.0 Credit hrs 1996
Hawkeye Community College Reliability Engineer
8.0 credit hrs. 1996
40 hr OSHA Trained RMP/PSM
Complete 1997
Zinger Miller Positive/Constructive Management Instructor
Certified 1997
N.A.P.E. Power plant Engineer Certified Plant Utilities, Operation and
Maintenance. 1998
IVY TECH Advanced Motor Controls and basic PLC
4.0 Credit hrs. 2000
High Voltage Training ( 13,800 /4160 volts)
Certified 2002
Trainned and Certified to operate and perform Maintenance on
Fanuc Robots. 2008