James Turner

Work Experience 2015 to Current

ADM

Maintenance Superintendent for the Third Largest Flour Mill in the United states.

Manage 24 Maintenance employees total - 2 Supervisors, 2 Leads Mechanics,1

Instrument Tech, Planner Scheduler and MRO Parts Manager . I have

Implemented and integrated a Maximo CMM's system for all plant assets t o

manage all Maintenance Work Orders, PM's, Labor and Parts tracking

management laying a foundation for a Maintenance Excellence Strategy. This

approach has reduced Monthly EDT from 2.7% to .9% Improving plant reliability. I

manage AFE Capital Projects, employee training, department safety programs. I

build teams and mentor leadership to create critical mass with in the

maintenance department to achieve the needed results of a 21 st century

maintenance team.

Phoenix Closures Inc. 2013 to 2015

Maintenance Manager- Manage 25 Mechanics and 1 Assistant Maintenance

Manager to maintain Plastic Injection Molding Production Equipment, Cap Lining

Machines, Conveying Systems, Robotic stackers, Vision systems and Palletizers.

Responsibilities include HVAC chilled water systems. I manage the Maintenance

Budget and Oversee the Maintenance Management system, for PM’s, Work

Orders and Purchasing. Experience includes managing the installation of 5 new

lines and successfully assisting the plant with its start up to reach its capacity.

Kroger Manufacturing Pace Dairy 2009 to 2013.

Maintenance Manager– Manage 19 Personnel and maintain High Speed

Manufacturing Equipment and Robotics systems Including some PLC, My

experience includes, Ammonia Refrigeration, Utilities, Boilers. Manage

Maintenance TPM projects and work order back log for the plant equipment.

Maintain RMP/PSM/Hazmat program. I have Navigated, Managed Capital

Projects Process from start to finish for facilities and other areas of the plant with

in the Kroger system, working with vendors, engineers, and plant personnel to

develop scope and goals of the projects. Using CAP /CAT /CAR’s to submit, track

and execute projects. This experience includes obtaining competitive quotes,

managing budget, scheduling, supervising contractors and managing start up

from start to finish, this Includes training of effected personnel. My Project

experience includes a 6 month Plant A/C Chiller Replacement Project valued at

$480,000 successfully as planned without plant interruption. In my 4+ years of

employment with Kroger Manufacturing I completed an additional 13 Capital and

expense projects totaling $5,000,000 the largest project I

managed included building a plant expansion, with a new automated ammonia

system, for $8 million .During my time I also completed a new boiler install and

upgrading the existing boiler totaling another $325,000. That is a total of

$13,325,000 roughly in a relative short time. I have managed these funds in trust

from the Kroger Company to progress its goals for its customer and the

enterprise. As a Leader I am strong and fair and have received positive feedback

on all leadership surveys. I excel at team building and Leadership. I am a strong

proponent of and for TPM and Maintenance Excellence as well as Six Sigma

process.

Eli Lilly 2002 to 2009

Plant Utilities Maintenance Engineer the first 3 years Lafayette plant

Manage Operate and maintain 400 psi. Coal Stoker Boilers total, plant could

generate 600,000 lbs. per hr. I Managed Plant Potable Water Generation and all

Site Utilities. Responsibilities included overseeing plant power grid, and

generators.1200 hp R22 chillers for chilled water system. Oversee Maintenance

budget/PM programs, project management, and execution.

Maintenance Tech.

Last 3.5 years Perform Maintenance on High speed Manufacturing equipment

Fanuc Robotics Case Packer Palletizers at the Lilly Technology Center

department for making Insulin devices. Work With Maximo PM system in World

Class Manufacturing. Assist with the install of 2 Production line projects for

insulin devices from FAT to running production.

Enron 2001 to 2002

Utilities Maintenance Manager at Lilly Corporate Center, Supervise 12

employees to manage all site utilities, Maintenance and building management.

Responsibilities included overseeing plant power grid, and generators.1200 hp

R22 chillers for chilled water system. Plant Air system management. Worked

Until Enron collapsed.

Murco Foods 2000 to 2001

Contracted to manage 6 month project to over see plant utilities

10 million dollar upgrade, For Boiler, Ammonia Refrigeration and Cooler

expansion for their Beef Packing process.

Tyson Foods Pork Processing 1993 to 2000

: Tysons Operations and Maintenance Manager Last 3 Years

Oversee all Maintenance and Operations in plant utilities for

Boilers and 220,000 lbs. Ammonia Refrigeration systems. Manage 15 employees

Manage all Osha Programs for utilities Process Safety Management/Risk

Management Program/ Wastewater ISO1401 Program. Train and Maintain

On site Hazmat Program. Manage Capital Expenditure’s requests and Project

Management. Including ROI cost Justification and Budgeting maintenance cost.

: Tysons Maintenance Planner for 2 years of plant operation.

Plan generate and order parts for all 12 departments which included a total of

104 maintenance employees. Develop and establish PMs for all equipment.

This Included development of processes to maintain high levels of Maintenance

Reliability with in the planning program. This work included parts management

from ordering to setting up in parts system. Working closely with vendors. Also

handle set up of any new equipment stemming from capital projects and

upgrades.

Writing capital expenditure requests for repairs and upgrades to current and new

equipment.

:Tysons Maintenance Mechanic first 2 yrs. of plant start up. Working in a USDA

Regulated Environment. Doing Mechanical /Electrical/Hydraulic/ Repairs on

production Equipment.

Monon Semi Trailer 1990 to 1993

Work in R&D department as fabricator building /testing prototypes while working

with engineers to improve designs and Lower Cost. Also building and designing

production Jigs using all forms of welding,reading blue print and following

technical Specs. to achieve the goals and objectives of the department.

James E. Turner

Education

In the process of taking college courses for a Bachelors MET/ and an Associates

Design Technology Currently 2 full years into the process

Logansport High School

Graduated 1990

Lincoln Tech /Mechanical Drafting

8.0 Credit hrs. 1992

Tele Train Maintenance Journeyman Apprentice

Complete 1993

RETA Trained For Industrial Refrigeration

Complete 1993

Tele Train Electrician Apprentice

Complete 1994

IIAR 24 Hr. Trained on Ammonia Refrigeration

Complete 1995

40 Hr. Trainer Level A Hazmat

Complete 1996

Hawkeye Community College Maint/Planning

8.0 Credit hrs 1996

Hawkeye Community College Reliability Engineer

8.0 credit hrs. 1996

40 hr OSHA Trained RMP/PSM

Complete 1997

Zinger Miller Positive/Constructive Management Instructor

Certified 1997

N.A.P.E. Power plant Engineer Certified Plant Utilities, Operation and

Maintenance. 1998

IVY TECH Advanced Motor Controls and basic PLC

4.0 Credit hrs. 2000

High Voltage Training ( 13,800 /4160 volts)

Certified 2002

Trainned and Certified to operate and perform Maintenance on

Fanuc Robots. 2008



Contact this candidate