NITIN PARMAR Vill.-Nougama, Teh.-Bagidora, Dist.-Banswara, Raj. 327001
*****.****@*****.*** • Mobile: 774-***-****
Power Plant Project Engineer
Summary
Overall 12 years of experience in the Project Management for Thermal, Combined Cycle and Biomass Power Plant. Project management experience includes liaisoning, preparation of schedules (L3), preparing punch and check list for AFBC, GT, HRSG, STG & BOP and close monitoring of pre-commissioning and commissioning activities to meet the target dates. Graduate in Mechanical engineering from IIT (Indian Institute of Technology) Delhi and Post graduate diploma in Piping Design and Construction from Trinity Academy of Professional Training, Pune.
Experience
Banswara Biomass Energy Pvt Ltd, Banswara Dec’2015 to Sep’2016
Plant Head (DGM)
Being the head of 6 MW biomass based power plant in Banswara
Coordination with Govt. agency and get the power connection and permission for bore well.
Get the quotation, comparison and ordering of transformer.
Preparing the project schedule.
Follow up the construction activities.
Review of construction drawings.
Handling the agitation of local people.
Survey of fields and identifying the land for storage yard.
To prepare the execution plan for fuel collection.
To prepare the various policies and formats to help in building the system.
To carry out the RCA for the issues at site.
Tata Consulting Engineers Ltd, Saudi Arabia Nov’2013 to Jan’2015
Mechanical Commissioning Consultant
3925 MW Qurayyah Independent Power Plant (QIPP), Saudi Arabia
As a start-up engineer I was responsible for-
• The commissioning of Fuel oil system
– Being a lead engineer, completed fuel oil flushing for 12nos. GTs.
– Monitoring of flushing activities and inspection of strainers.
– Restoration of fuel oil system.
• Water-Steam cycle
– Monitored lube oil flushing for BFPs.
– Solo, Heat run of pumps and motors and system functional test.
– System walk down for commissioning and initial startup.
– Monitoring of Steam blowing.
– Mechanical troubleshooting.
– Preparation of commissioning hand over documents(CCC).
– Carry out predictive maintenance.
Lansh Engineering Pvt. Ltd, Mumbai Sep’2012 to June 2013
Manager (Projects)
Handling an EPC project of “Hot Water System”. Includes following responsibilities:-
• Being a single point contact person for consultant and clients resolving all engineering, procurement and execution related queries.
• Preparing project schedule (L3) on MS Project for monitoring progress and critical activities.
• Preparing Weekly and Monthly progress report for client.
• Responsible for meeting the project goals in terms of schedule, cost and performance.
• Keeping coordination among the Engineering, Procurement and Production dept. to meet the project deadline.
• Conducting site visits to resolve engineering issues.
• Providing supports to the Engineering and Procurement department.
• Act proactively and take initiative to address and solve issues.
• Prepare and present project progress and contingency plan to client.
• Assigning work to sub-ordinates and guiding them to get the work done in due course of time.
Steag Energy Services (India) Pvt. Ltd, Surat Nov’2010 to Aug 2012
Shift Engineer (Operation)
Responsible for handling the smooth start-up and operation of 501 MW CCPP also includes
• Daily gas nomination and imbalance management.
• Monitoring the daily generation as per SLDC schedule and regular communication for the availability if the plant.
• Supervised various erection and commissioning activities of 350MW CCPP (GE 9FA)
• Coordinated hydro testing of HP, IP and LP circuit of HRSG.
• Collected technical details for the equipments.
• Monitored lube oil flushing of GT, ST and BFP.
• Recorded protocols for various activities in the project.
• Monitored the detergent flushing and Alkali Boil-out of HRSG.
• Monitored the steam blowing of HP, IP and LP circuit.
Hyundai Heavy Industries Ltd, Bahrain Dec’2009 to Aug’2010
Mechanical Commissioning Engineer
Responsible for Pre-commissioning and Commissioning of 1350 MW Combined Cycle Power Plant. Independently performed Pre-commissioning activities for GE Make, Frame 9FA gas turbine such as charging of H2 gas in Generator, CO2 concentration test, Lube & Lift oil commissioning, IGV Calibration and Turbine water washing. Successfully completed the commissioning of gas turbine with minimal teething problem in my first ever CCPP.
• Completed pre-commissioning of the Gas turbine in 15days.
• Minimized Hydrogen gas leakages from Generator from 20m3/day to 6m3/Day.
• Prepared and executed Operating manual and starting check list for Gas Turbines.
• Given Training to field operators to improve their technical skills resulting in higher efficiency.
Finolex Industries Ltd., Ratnagiri June’2007 to Feb’2009
Asst. Manager, CPP
My major responsibilities included preparing schedule for 43 MW Thermal power project, preparing BOM for HP and LP piping, Erection and Testing of Condenser, Erection of Turbine and Boiler auxiliaries, Fabrication, erection and NDT of LP & HP piping.
• Completed a water cooled condenser erection and testing within stipulated time.
• Project monitoring as per the project schedule and highlighting the bottle neck to crash the project.
Jubilant Organosys Ltd., Gajraula, UP May’2005 to June’2007
Asst. Manager, CPP
Optimization of Steam and Power cost Increasing Steam generation from AFBC boiler and Steam Turbine instead of Oil fired boiler and DG respectively. Monitoring of rotary equipments to avoid breakdown, Smooth operation of utility plant to ensure uninterrupted supply to the power block and process plant, commissioning of 90T AFBC boiler.
• Ensured smooth running of rotary equipments by implementing predictive maintenance.
• Timely updating the generation and consumption of Utility plant in BAAN.
• Successfully implemented the 5 ‘S’ in power block to obtain an organizing, cleaning, developing, and sustaining productive work environment.
Jubilant Organosys Ltd., Gajraula, UP June’2004 to May’2005
Graduate Engineer Trainee
Traced all utility pipelines in power block and prepared a piping layout for further modification and expansion of plant.
• Steam and condensate mass balancing to increase condensate recovery by 10%.
• Inventory management for the process plant maintenance reduced the downtime of the equipments.
Education
IIT Delhi, New Delhi 2004
B.Tech, Mechanical Engineer
Maa Bharti Senior Secondary School, Kota, Rajasthan 1996
Senior Secondary, XII
Mayank Secondary School, Kota, Rajasthan 1994
Secondary School, X
Skills
• Software: MS Office, MS Project, AutoCAD, Windows 7
• ERP: MAXIMO, BAAN, SAP
Training
• Post Graduation Diploma in piping design and construction,
Trinity Academy of Professional Training, Pune, Maharashtra, Jan’2009 to Apr’2009. Pipe sizing,
Material selection, Stress calculations, Layout, MTO, BOM, Isometric preparation.
• Hazop Study, Telos Consultancy Services (P) Ltd, Ratnagiri, Maharashtra, 2007. Hazop study of power plant
Honors
• Awarded Blazer, for achievement in Weightlifting Competitions, IIT Delhi.
• Gold Medal, in weightlifting at Inter-hostel and Inter-IIT level competitions.
Personal details
• Date of Birth : 28th Dec, 1979.
• Marital status : Married.
• Passport No : L3635913