Job Objective: To obtain a Commissioning Head position for Coal / oil fired power plant /Plants of bigger size any where in the world ( and ready to relocate ) and so I can become a valued member of the team while moving forward with in this field.

Highlights of Expertise

Commissioning and operatios, (having rich 26 years of experience) Specialised in TG & Auxiliaries

Managing commissioning process and handover to operation smoothly,

Ensuring compliance to HSE standards and PTW during entire commissioning process of plant.

Managing transition period of project from projects stage to operation stage.

Managing commissioning team and guiding them for

getting project commissioned in line with planned

schedule.

Manage the commercial operation of plant with minimum most punch points.

Total 26 years of power plant commissioning experience. 21 years of BHEL power sector commissioning experience in different BHEL projects and 5 years of Chinese machines experience in APML( Adani Power Maharastra Limited, Tiroda).

Resigned as BHEL senior manager Post and Joined March 2011 In Adani Power Maharastra Limited Tiroda as DGM in O&M team. At present I am working as Additional General Manager In O&M commissioning team

Of Adani Power Maharastra Limited,Tiroda i.e Super Critical Thermal Power Plant 5 X 660 MW Size .

On deputation for 3 months supervised the AVANTHA 1 X 600 MW unit sub critical (BHEL’s Supply ) stabilisation to COD operation on behalf of ADANI, which is being taken over by ADANI company. Exceptional experience in commissioning of thermal power plants (26 years of experience) Experience in Super critical thermal power plants and commissioned six supercritical thermal power plants.

Expertise in commissioning of Turbine and Generator packages. Commissioned BHEL and CHINESE make machines

Ability to make commissioning procedures and equipment checklists Deciding cleanliness / completion criteria for different systems and convince concerned clients.

Ability to persue for commissioning driven project schedule. Ability to understand scope of work with time plan and project deliverables. Ability to make strategic commissioning schedule

Ability to get units commissioned on schedule

Ability to maintain accurate commissioning records Ability to resolve all complaints

Ability to lead the team

Ability to trouble shoot and resolve issues.

Ability to manage multiple units within deadline

Integration of systems.

Compliy to PTW and HSE systems during commissioning period. Planning for all inputs to suit to commissioning plan in agreement with Project manager like cooling water,DM water,11 KV,6.6 KV and 415 V power supply, aux steam,instrument air and fuel supply.

Planning for resources for commissioning activities and monitoring, Conducting commissioning meeting with projects/OEM engineers, Informing commissioning status to commissioning manger and following his directions/guidance.

Ensure plant drainage system, neutralisation pit,dosing system readiness, plant lighting and house keeping ready

Understanding clarity on mechanical completeness of the system like HT,NDT and Radiography .

Ensuring firefighting system readiness for commissioning activities. Persue and arrange project inputs for day today commissioning activities Technical Experience:

Working as Additional General Manager

APML Commissioning Team, O & M, 5 X 660 MW,

Super Critical Thermal Power PLANT,

Tiroda, Maharastra, INDIA.

March 2011 – Present

Engineer to Senior Manager,

Power sector, Southern region,Chennai.

BHEL Different projects.

Feb 1990 to March 2011

Full knowledge of coal fired power plants and its systems, Specialized in TG and auxiliaries. Proper under standing of PIDs and process,

Proper knowledge of commissioning sequence

Ensuring backup power for startup of unit

Deciding and ensuring valves in the system to be close setting with torque limit. Checking for completeness of the system ( erection completion) and making punch points before pre commissioning and persue for completeness of the system before commissioning commences

Ensuring cleanliness of the systems before pressing into service by different cleaning methods like

Air blasting

Air blowing

Water flushing

Chemical cleaning,

Mechanical cleaning

Oil flushing

Steam blowing

Boroscopic inspection etc and ensuring cleanliness criteria met (different for different systems) before taking system into service. Administered start up of commissioning units and equipments.and resolving confronted issues.

Guiding team to resolve problems during commissioning, Provided technical guidance to commissioning team. Evaluated process and equipments for flow diagram and ensured consistency. Maintained safe work according to HSE guidelines.

Reviewed equipment and plant performance on site.

Managed commissioning schedule and arranged resources for it. Analyzed all issues and provided technical solutions for problems Commissioned different rated sets Of Turbines from 20MW to 660MW rating Commissioning of TG and auxiliaries equipments,

Commissioning of governing systems,

Commissioning of different oil systems and oil flushing, Executing steam blowing activity,

Resolving all technical problems,

Interacting with OEMs for design problems,

Improvising systems by small changes at site level, Loading machine,

Regenerative system commissioning,

Getting rated vacuum,

Generator seal oil and stator water system commissioning Fuel handling knowledge,

Gas Turbines commissioning.

Mill reject system commissioning

HCSD (High concentration slurry disposal) system commissioning. Trouble shooting and establishing stable operation of Ash handling plant. AHP opearation

Education:

B.E Passed in First class with Distinction in 1984- 1988 Bachelors Degree in Mechanical Engineering,

GITAM Engg college,

Andhra University,

Visakhapatnam, Andhra Pradesh, INDIA.

CTC ; 45 lakhs per annum. (PMS is in progress,10% hike is considered).

Expected CTC : 50 lakhs per annum.

Trainings attended

1. General management programme At BHEL Hyderbad

2. Introductory Certificate in Project Management at APML, Tiroda 3. KWU steam turbine governing system At BHEL Haridwar 4. 500MW KWU steam turbine commissioning at BHEL Haridwar. 5. Group dynamics and Team building training at APML,Tiroda. PROJECTS commissioned

1. 2 X 210 MW, RTPP, Kalamalla, Cudappah Dist, A.P INDIA owned by APGENCO.

2. 2 X 250 MW, KTPS, Kothagudem, Khammam Dist,A.P,INDIA owned by APGENCO.

3. 2 X 120 MW JTPCL, Toranagallu, Bellary Dist, Karnataka,INDIA owned by JTPCL.

4. 2 X 500 MW STPP, Paravada, Visakhapatnam, INDIA owned by NTPC.

5. 1 X 500 MW III stage RSTPS, Ramagundam, A.P, INDIA owned by NTPC.

6. 2 X 25 MW Gas Turbines ( Fr 5) and HRSGs Of 60 TPH,CPP,HPCL, Visaakhapatnam, A.P, INDIA.

7. 2 X 125MW CPP,NALCO,ANGUL,ORISSA,INDIA.

8. 1 x 210 MW RTPP III stage APGENCO,Kalamalla Cuddapah dist, A.P. 9, 5 X 660 MW APML. Tiroda, Maharashtra Supercritical Thermal Power Plant.

10.. 1 X 600 MW Avantha Plant Raigarh Chathisgarh.