Post Job Free

Resume

Sign in

Technician Engineering

Location:
Seguin, TX, 78155
Posted:
December 22, 2016

Contact this candidate

Resume:

Bryant C. Rhodes

*** ******* ****

830-***-****

Seguin, Texas 78155

acxzji@r.postjobfree.com

Summary of Relevant Knowledge, Expertise, and Skills

I bring 31 years of experience in the Instrumentation, Control, Measurement, Electrical, and Communications fields. This experience covers a wide array of industry applications in Petrochemical, Chemical, and Refining Processes and associated Pipeline and Storage entities along with Oil and Gas Production and associated

Mid-stream entities.

I have worked in different capacities as technician, field design and engineering, QA/QC and inspection, supervision and planning/scheduling.

Facets and environments worked in include new construction and capital projects, maintenance, turnarounds/shutdowns, startup and commissioning, and engineering support.

In my career I have been fortunate enough to evolve my skills and knowledge in the ever changing technology of the industries.

Pneumatic, electronic, and microprocessor based instrumentation and control systems. Various DCS, PLC, and SCADA control systems and the integration of these systems together.

Measurement systems associated with custody transfer and systems balance in production, pipeline, and storage.

Electrical power and distribution and motor controls.

Communications including radio, satellite, and cellular systems.

I have had exposure to extreme environments, working conditions, and living conditions along with experience working in a foreign country.

Received Associates Degree in Instrumentation Technology from Lee College in

Baytown, Texas in 1986.

Previous Employment History

1/2012 to 11/2016

I/C, MEASUREMENT, COMMUNICATIONS TECH: Atchafalaya Measurement- Eagle Ford Shale, South Texas

Worked as lead I/E Technician in the design, installation and commissioning of various measurement, control, and communications systems for various oil and gas production companies in the Eagle Ford Shale Region of South Texas.

8/2010 to 1/2012

INSTRUMENT SUPERINTENDENT: Strike Instrumentation and Electrical-Spring, Texas

Duties include assisting in developing and maintaining customer base, assisting in estimating job bids and developing proposals, working with customers in planning and executing jobs, and supervising jobs.

5/2008 to 8/2010

LEAD I/E TECH: Koch Pipeline-Liberty, Texas

Employed to Koch Pipeline after Flint Hills Resources’ buy out of Buckeye Pipeline’s Huntsman system which I was assigned to. Continued the same duties and responsibilities that I had with Buckeye Pipeline on this system. As a lead technician, I was responsible for scheduling and planning all routine maintenance and project work.

4/2006 to 5/2008

I/E, MEASUREMENT TECH: Buckeye Pipeline-Liberty, Texas

Responsibilities included routine maintenance of all communication, measurement, and control systems on various pipeline systems operated by Buckeye Pipeline. Also responsible for project work such as new meter installations, including flow computers, PLCs, radio and satellite communications. Buckeye operated several different systems for various other companies which created a great challenge in being exposed to many different applications in PLCs, meters, and communications/SCADA designs.

8/2000 to 4/2006

MEASUREMENT TECH: Equistar Pipeline-Mont Belvieu, Texas

Duties included routine calibration, proving, pychnometer test, and maintenance of orifice and turbine meters used in custody measurement. Calibration and maintenance of all instrumentation associated with pipeline control and regulatory compliance. Assisted pipeline technicians in maintenance duties such as pigging operations, overseeing contractor work, one calls, etc. Dealt with LPG products such as ethylene, propylene, NGL, ethane, propane, E/P mix, butane, benzene, C4’s and various condensates and feedstocks.

8/1996 to 8/2000

INSTRUMENT TECH: Arco Chemical/Lyondell Petrochemical-Channelview, Texas

In house duties included routine preventive maintenance, work order task, and special projects including unit turnarounds and DCS/PLC control system modifications. I left Lyondell Petrochemical when I took an opportunity to transfer to Equistar Pipeline’s Measurement Department. Equistar Pipeline was a subsidiary company of Lyondell.

4/1996 to 6/1996

I/C TECHNICAN: Contech Engineering-Arco Chemical-Channelview, Texas

Maintenance coverage in POSM II Unit during Mid Plant Turnaround. Asked by Arco I/E supervisor to apply for permanent position with Arco Chemical. Accepted offer with Arco 8/1996.

2/1996 to 4/1996

I/C TECHNICIAN: Contech Engineering-Exxon Chemical-Baytown, Texas

Assisted in cutover of existing instrumentation to Honeywell TDC 3000. Also performed functional checkout of unit instrumentation as a part of a multi-unit turnaround.

2/1996

I/C TECHNICIAN: TASC-Enterprise Products Corp.-Mont Belvieu, Texas

Assessment and repair of instrumentation damage after fire in Propylene Unit. Performed functional checkout after rebuild and assisted in start-up.

10/1995 to 1/1996

TECHNICAL SUPV: Walker Engineering-Advanced Micro Devices-Austin, Texas

Responsibilities included management of I/C technicians in calibrations, development of loop packages, and checkout of instrumentation after installation. Also assisted engineering group in design of special add-on packages in coordination with Jacobs Engineering.

7/1995 to 9/1995

I/E DESIGNER: CDI Stubbs Overbeck-Sunoco Marine Terminal-Nederland, Texas

Duties included assisting Senior Designer in designing and producing CAD drawings for new installation of PLC control systems for transfer pumps and loading racks. Also assisted Sunoco I/E technicians in programming Allen Bradley PLCs and in commissioning of these systems.

5/1995 to 7/1995

I/C TECHNICIAN: ITI-Shell DPMC-Deer Park, Texas

Worked as start-up technician on new Coker and Hydrotreater Units. Duties included checkout and commissioning of loops and assisting in start-up of units.

12/1994 to 4/1995

I/E QA/QC INSPECTOR: MMR Radon- Maraven Refinery-Punta Fijo, Venezuela

Worked directly with Foster Wheeler Carribe Engineering’s project management team in the construction of new Coker and MTBE Units. Duties included witnessing of functional checkout and calibrations being performed by MMR technicians and assisting in engineering and design situations that arose.

10/1994 to 12/1994

I/E FIELD DISIGNER: Udalhoven Oilfield System Services-North Slope, Alaska

P&ID update and verification of pump station facilities on the Trans-Alaska Pipeline. Duties included walking down pump stations and insuring accuracy of instrument and control scenarios on P&IDs and redlining drawings accordingly.

7/1994 to 11/1994

I/C TECH: Instrument Control Services-Gulf Coast Fractionators-Mont Belvieu, Texas

Worked fire and explosion damage to Fractionation Unit. Performed repair, replacement, and checkout of all damaged instrumentation. Also did checkout of newly installed Honeywell DCS and Modicon PLC.

1/1994 to 6/1994

I/C DESIGNER: Petrocon Engineering-Fina-Port Neches, Texas

Duties included P&ID and Loopsheet verification and updating of unit instrument indexes for plant-wide ISO 9000 compliance project. Performed DCS graphic configuration surveys on control systems to verify accuracy of P&IDs and Loopsheet along with unit walkdowns.

6/1993 to 11/1993

I/C TECH: Conceptual Technologies International-Exxon Mobile Bay Project-

Amelia, Louisiana/Dauphine Island, Alabama

Duties included calibration, functional checkout, and commissioning of instrumentation and control systems on new offshore natural gas production platforms during construction in the McDermott Ship Yard in Amelia and after final installation in Mobile Bay and the Gulf of Mexico.

4/1993 to 6/1993

INSTRUMENT TECH: ITI-Amoco Chemical Cedar Bayou Plant-Baytown, Texas

Duties included assisting Amoco I/E technicians in routine maintenance and project work in Low Density Polypropylene Unit.

1/1993 to 4/1993

INSTRUMENT TECH: Bay Controls-Valero Refinery-Corpus Christi, Texas

Duties include calibration and loopcheck of instrumentation and control for new Propylene Unit.

9/1992 to 11/1992

INSTRUMENT TECH: ITI-Shell DPMC-Deer Park, Texas

Duties included calibrations, loopchecks, and upgrades of instrumentation and control systems during a turnaround for CR3 and Hydrotreater Units.

8/1992 to 9/1992

INSTRUMENT TECH: Bay Controls- Texaco Refinery- Port Arthur, Texas

Calibration, loopcheck, and commissioning of instrumentation and control systems for new Hydrotreater Unit.

5/1991 to 4/1992

INSTRUMENT INSPECTOR/TECH: Austin Industrial-Quantum QE-1 Project- Laporte, Texas

Duties included witnessing and inspection of calibrations and loopchecks of new instrumentation for QE-1 Ethylene Unit. Worked as Instrument Technician during commissioning and start-up of unit.

1/1991 to 5/1991

INSTRUMENT TECH: Becon-Chevron Cedar Bayou-NAOU Project-Baytown, Texas

Calibration, loopcheck, and commissioning of of instrumentation and control systems for new Normal Alpha Olefins Unit.

5/1986 to 11/1990

Brown and Root and Instrument Technology International (ITI)-Houston Ship Channel Area

Began career with Brown and Root and ITI which was a subsidiary company of Brown and Root. Worked as an Instrument Technicians Helper, Instrument Fitters Helper, Instrument Fitter, and finally Instrument Technician at Shell DPMC-Deer Park, Texas and Champion Paper Mill-Sheldon, Texas. Worked turnarounds, capital projects, and in the Analyzer Installation Group (ITI) at Shell DPMC. Gained a lot of invaluable field experience during this time.

Education

Lee College, Baytown, Texas

Associates Degree in Instrumentation Technology

Received degree 1986

Rosemount System 3 DCS Training-Rosemount Facility-Burnsville, Minnesota

Triconex PLC School-Triconex Facility-LaMarque,Texas

OMNI Flow Computer Training-Stafford Texas

Pipeline I/E and Measurement Operator Qualifications (OQ’s) available in IS Net World



Contact this candidate