I have been in Startup, Maintenance, Project Management, and Management in the commercial power generation field for over twenty-five years. I am experienced in almost all phases of maintenance and preventive maintenance including Plant Engineering and Planning/Scheduling. I am Safety conscious and detail oriented. I have experience in biofuels and the oil and gas industry. I also have experience in cost estimating of modular pipe racks and process modules for the oil and gas industry and large water processing plants. I have performed Planning and Scheduling for Chemical Demilitarization sites and Combined Cycle power generation plants in my career. My background shows I have worked both as a ‘regular’ employee and a Contractor.
Career Accomplishments include:
Development of Maintenance Planning and Scheduling group for Chemical Demilitarization facility
Development of Work Control procedures for Maintenance Department at Chemical Demilitarization facility
Successful audits of the Work Control by Government entities at Chemical Demilitarization facility
Cost savings of approximately $135k annually by design and installation of heat exchangers for decant tank reheat at Biodiesel facility
Cost savings of approximately $130k annually due to design of equipment to sparge reboilers on distillation towers at Biodiesel facility
Design of wastewater handling system including pumps, valves, and surge tank for Biodiesel facility
Design of flare testing methodology for Biodiesel facility
Design of steam heated buildings for temperature-sensitive equipment and material at the Biodiesel facility
Design and installation of reject water reclaim system for two 100GPM Alfa Laval centrifuges resulting in cost savings of approximately $15k annually
Contractor oversight and Project Management for Cooling Tower construction at a Combined-cycle power plant
Served on the Training team for development, roll-out, and training of the Maximo-based Work Management Policy for the Calpine fleet of Generating Stations throughout the US
Background
December 2014 to Present
Advanced Technologies Sweetwater, Tx
Maintenance Planner/Scheduler
Plan work packages for Maintenance
Plan and schedule weekly Down Day work
Consult with Site Manager and Maintenance Supervisor on daily work
Get quotes from vendors for contract work during outages and down days
Schedule outage work
Coordinate material for daily and outage work
Set up any Pms not already in the system (MP2)
Write job plans for daily and PM Work Orders
Create monthly metrics Powerpoint slideshows based on data mined from MP2 and other sources
Present monthly metrics to Management and customer with data analysis discussions
Create ad-hoc reports and charts including MTBF, MTTR, manpower utilization, Downtime Pareto and others
May 2014 to December 2014
TXI/Martin Marietta New Braunfels, Tx
Maintenance Planner/Scheduler
Plan work packages for Maintenance
Consult with Maintenance Manager and Supervisors on Outage projects
Get quotes from vendors for contract work during outages and down days
Schedule major and minor outages
Coordinate material for daily and outage work
Set up Gantt chart for outages
Set up any Pms not already in the system (Oracle EAM 12)
Write job plans for daily and PM Work Orders
Supervise and develop Planner Assistant
January 2014 to May 2014
CDI Pueblo, Colorado
Maintenance Planner
Plan work packages for Maintenance
Consult with other Planners on Maximo use
Schedule and perform pre-planning job walkdowns with responsible personnel
Write detailed work instructions
Consult with Engineering on design change documents in order to plan properly
Review work packages returning from field
April 2012 to December 2013
Lauren Engineers and Constructors Abilene, Texas
Senior Estimator
Estimated and developed bid packages for the Constructors division
Projects ranged from over $175,000 to over $27,000,000
Developed bid packages for budgetary, lump sum, cost plus, and unit rate quotes from 3D models, PIDs, concept drawings, specs, ISOs.
Developed the Excel format for Instrumentation and Electrical estimates and integrated it into the main Excel worksheets
Read and understood detailed scope of work in order to define the parameters of the bid
Developed list of clarifications and exceptions pertinent to the bid
Utilized knowledge in IEEE, ANSI, NEC, ASTM, and the Canadian equivalent codes
Performed materials takeoffs, generated materials lists, and developed requests for quotes
Sent requests for quotes to multiple vendors, evaluated the returned quote, and entered data into worksheet
Met with Plant Management to evaluate final data before developing bid package
February 2010 to March 2012
Calpine Magic Valley Energy Center/ Hidalgo Energy Center Edinburg, Texas
Senior Maintenance Planner/ Scheduler
Planner/ Scheduler for both the Magic Valley and the Hidalgo power plants.
Planned and scheduled a complete plant outage including teardown and inspection of all three generators and rebuild of both CT rotors.
Built Gantt charts, tracked the schedule, ensured parts were available and on site on time, and added any backlog items that were not part of the borescope task but could be accomplished during this time.
Managed the work order backlog
Coordinated tasks with vendors and contractors
Trained several of the Calpine Power Plants on use of Maximo, the Work Management Plan, and Backlog Management
Developed and implemented Start Centers in Maximo to include Management tools to facilitate managing the Work Orders by writing automated SQL statements
Wrote a search routine for Excel to pull inventory lists from the Maximo warehouse module from multiple power plant sites
Team member for Work Control procedures development and implementation for the fleet
Ordered and staged parts for work orders
Wrote scopes of work for in-house Technicians and outside contractors
Ensured task instructions met safety and QA/QC guidelines
Obtained quotes from vendors and contractors and made decisions on purchases based on those quotes
December 2009 – January 2010
IVRR Imperial Valley CA.
Plant Engineer / HSE Engineer
I was contracted to perform Plant Engineering and HSE for a short time at a 16Mw biomass electric generating station due to an immediate vacancy. I set up a tool to track reporting deadlines for air, water, and waste in accordance with the Plant permits. I set up the OSHA training matrix.
January 2009 – November 2009
NAES Victoria WLE, LP Victoria, Texas
Plant Engineer/ HSE Coordinator
Development and maintenance of the HSE and Training for a 300MW combined-cycle repowered facility. I was also responsible for maintenance of the CMMS system (MP2) along with my Plant Engineering duties.
2007- December 2008
Green Earth Fuels of Houston Galena Park, Texas
Plant Engineer/ Assistant Plant Manager
Maintained the Safety, Administration, and Plant procedures for this facility. Programmed the CMMS database (Access proprietary). I designed plant modifications and managed the construction and testing for modifications. I coordinated on-site activities with contractors and ensured the safe completion of projects I designed. I assisted the Director of Operations in development and maintenance of the Plant budget. I had approval and design authority for the Management of Change activities.
2003-2007
Parsons Engineering Newport Chemical Depot Newport, Indiana
Maintenance Planning and Scheduling Supervisor /Programmer
Developed and supervised the Maintenance Planning/ Scheduling Department. Interviewed prospective Planners, Schedulers, Maintenance Technicians, and Maintenance Supervisors and made recommendations. Developed the CHAMPS CMMS database for this location. Served as CHAMPS database Administrator. Wrote ad-hoc reports in MS-SQL as required. Set up and maintained work flow in CHAMPS. Created Excel spreadsheets and small Access databases as needed. Directed Planners, Data Entry Operators, Schedulers, Programmers, and Tech Writers in daily tasks. Ensured task instructions were clear and met safety and QA/QC guidelines. Interfaced regularly with Government auditors and personnel from other departments to demonstrate the Departmental methods.
2003
Parsons Engineering Newport Chemical Depot Newport, Indiana.
Startup Electrical Lead
Responsible for directing Techs who tested and commissioned various electrical/mechanical systems at the Chemical Weapons Demilitarization Facility. This activity included startup of 4160 volt switchgear, 480 volt switchgear, 480 volt MCCs, FCS control systems, PLC systems, and other process-related equipment.
2002-2003
ZUE Tenaska Central Alabama facility.
Senior Electrical Engineering Tech, Startup Turnover Coordinator
Responsible for engineering interface, manpower and materials cost projections, material estimates and material takeoffs.
Startup Electrical Engineer
Responsible for testing and commissioning of various electrical and electrical/mechanical systems at this combined cycle power plant.
2001- 2002
Nepco Wolf Hollow Power Plant Granbury, Texas
Startup and Commissioning Engineer
Checkout, Startup, and Commissioning of BOP systems, Circulating water system, Plant 4160 volt switchgear, 480 volt switchgear, instrumentation loops on Deltak HRSGs and vibration monitoring equipment on the Cooling Tower fans.
2000-2001 Double B Foods, Inc. Schulenburg, Texas
Plant Engineer, Meat Snack Division, Information Services Manager, Corporate
Plant Engineering and Maintenance of USDA inspected food-processing plant. Prepared annual budget for Maintenance Department, assigned work, set crew schedules. Developed work order and PM database. Designed equipment and controls as needed. Generated and submitted cost analysis for capital projects to Board of Directors. Also managed the network and computers.
1984-1997 Texas Utilities/ Comanche Peak Glen Rose, Texas
Plant Maintenance Electrician, Nuclear
Electrical maintenance on motors, switchgear, motor operated valves, air operated valves, calibration of valve operators, preventive/ predictive maintenance on electrical equipment including centrifugal water chillers, electric motors ranging from fractional to 7,000 horsepower vertical motors, troubleshot controls and relays, tested and calibrated molded-case breakers and switchgear. Temporarily assigned as Electrical Maintenance Planner during outage times. Assisted with writing, critiquing, and testing procedures for Maintenance, developed detailed work packages for outage work including permanent and temporary modifications. Qualified as Field and Classroom Trainer including course development and presentation.
SOFTWARE SKILLS (proficient)
MS Word MS Access MS Excel Oracle EAM 12
MS Outlook MS Project MS PowerPoint Cognos Reports
MS Visio MS Internet Explorer DIA Linux Mint
GANTT Project AutoCAD Firefox Linux Ubuntu
CHAMPS CMMS MP2 MAXIMO LibreOffice
PowerBuilder Infomaker Crystal Reports MS SQL
Oracle SQL Benthic Golden 32 File Maker Pro
CURRENT AND RECENT MEMBERSHIPS/ AFFILIATIONS
Board of Directors Abilene Community Theater
Active volunteer teaching computer classes at Cross Plains Public Library
EDUCATION
1977-1978 TSTI Waco, Texas Electronics Technology
1985 York, Inc. York, PA. York Centrifugal Water Chiller Teardown and Maintenance.
1984-1997 Texas Utilities Glen Rose, Texas Continuing technical training at TU training center
This training included TEAM training such as ROPES and management courses including
SIX THINKING HATS.
A list of the technical training is available upon request.
CHAMPs CMMS Administrator training
CORNERSTONE Administrator training
American Management Association Management for Professionals
REFERENCES:
Glenn Garrison Lauren Engineers and Constructors 325-***-****
Stephen Kite Advanced Technology Services 325-***-****
Troy King Advanced Technology Services 859-***-****
Roy Long IHI Power Services Corp 760-***-****