COMISSIONING & MAINTENANCE I&C ENGINEER

PERSONAL DETAILS

Date of birth : 30 /5/1979

Nationality : Egyptian

Military Service Status: Exempted

Marital Status : Married

Religion : Muslim

Driving license : valid

Driving license

: valid

SKILLS

Lead a team of engineers and technologists in project team.

Preparation of tag assignments, logic drawings shutdown keys &control narrative.

Reading and understanding engineering drawing and in particular p&ID and loop

diagrams.

Experience of dealing with subcontractors and clients as required in field.

Understanding of steam, condensate and feed water level and flow measurement.

Experienced in testing and calibration of all instrumentation.

Experienced in loop checking instrumentation and electrical signals from field into

the DCS .

Experience in valve commissioning.

Experience in functional and interlock test.

Work Experience in instrumentation commissioning.

Study and understanding the project specifications, procedures and contract

•PCs assembly & maintenance.

•Office 2007.

•Visual Basic.

•Control strategy implementation

•HMI Web display builder

LANGUAGE SKILLS

•Native language : Arabic

•First language : English Grade : Very Good

•Some French

TRAINING COURSES

[29/3/2014 to 29/4/2014]

Honeywell Experion process knowledge system PKS GIZA systems company

[23/11/2013 to 28/11/2013]

Maintenance of measuring & control instruments Middle Delta Electricity Production Company TALKHA Power Plant 2X210 MW

[9/11/2013 to 14/11/2013]

Civil defense &fire fighting Civil Protection Department Security Directorate DAKAHLIA

[8/6/2013to 13/6/2013]

Turbine supervision instruments Middle Delta Electricity Production Company TALKHA Power Plant 2X210 MW

[30/8/ 2003 to 4/9/ 2003]

Protection and control in Boilers

Observing Boilers Protection systems and the control of Boilers operation.

East Delta Electricity Production Company,

OYUON MOSSA Power Plant (2X320 MW)

[5/4/ 2003 to 10/4/ 2003]

Operating of Steam turbine Observing Steam turbine operation.

East Delta Electricity Production Company,

OYUON MOSSA Power Plant (2X320 MW)

[15/8/ 2000 to 12/9/ 2000]

PDH & SDH TRANSMISSION SYSTEMS

Observing transmission systems including creating ring connection between a numbers of main Exchanges "MANSOURA RING A, MANSOURA RING B ".

ALCATEL (EGYPT)

[15/7/ 2000 to 15/8/ 2000]

(OCB 283 ALCATEL Exchange )

Observing Exchange system operation including: “microwave systems, transmission systems, fiber optics, welding two fiber cables”.

TELECOM EGYPT

[1/7/ 1999 to 15/8/ 1999]

Maintenance of Electronic equipments.

Design and manufacturing of electronic circuits and boards, Maintenance of color TV, cassettes, computers, etc.

MANSURA University

EDUCATION

1996-2001

B. SC. OF ELECTRONIC & COMMUNICATION ENGINEERING, JUNE 2001 FACULTY OF ENGINEERING, MANSOURA UNIVERSITY.

Graduation Grade : (very good).

General Cumulative grade : (good) 70.85%.

GRADUATION PROJECT

The Next Generation of Telecommunication & Cellular Networks.

Grade : ( Excellent).

Summary of Graduation Project :

PSTN Structure, Local Loop, Transmission systems PDH &SDH, Fiber Optical, GSM SYSTEMS.

WORKING EXPERIENCE

[ 1/1/2013 - Till now ]

Middle Delta Electricity Production Company, Egypt.

TALKHA Power Plant 2X210 MW

Position : SENIOR I&C ENGINEER

Responsibilities:

•Perform commissioning tests & function check for all instruments during SKODA turbine control retrofit for unit #1. "Emerson -ovation system "

•Identifying and investigate the problems to troubleshoot.

•Monitoring the behavior of all instruments with the Ovation system

•Troubleshooting internal and external fault in modules in OVATION system

•Supervising & Perform BMS retrofit for unit #1 "HONEYWELL EXPERION PKS R410 "

•Perform FAT for Rehabilitation of unit 1 control system by Invensys company

[1/4/2011 - 30/12/2012]

KHARAFINATIONAL COMPANY

AL-SHABAB SIMPLE CYCLE GAS TURBINE 8 X 125 MW "GE- MARK VI 9E " [1/4/2011 -22/2/2012]

WEST-DAMITTA SIMPLE CYCLE GAS TURBINE 4 X 125 MW "GE- MARK VI 9E"[23/2/2012-30/12/2012]

Position : Commissioning I&C ENGINEER

Responsibilities:

• Commissioning and start-up of 4X125MW GE gas turbine.

•Making loop check and function test.

•Commissioning and start up of all GT systems(air processing unit - gas fuel - oil fuel - inlet guide vane - lube oil & hydraulic oil - closed cooling - inlet air filter -Flame detector-turbine & compressor water wash-water injection).

•Calibration of all field instruments.

•Calibration of supervisory instruments.

•Calibration of inlet guide vane.

•Commission and start up of fire protection system.

•Calibration of all valves (pneumatic - motorized - hydraulic).

•Responsible for the preparation, organizing and authorization of the required forms prior the execution of any activities under the custody and control of the Commissioning team.

•Responsible for supporting commissioning team in the preparation and issuing the required authorization in a timely manner so as not to delay the schedule of daily activities .

•Calibration of all valves (pneumatic - motorized - hydraulic).

•Operation engineer during start up & reliability test.

[28/10/2009 - 30/12/2010]

PGESCO

CAIRO ELECTRICITY PRODUCTION COMPANY

EL TEBBEN 2X350 MW TPP

Position : Commissioning Engineer

Responsibilities:

•Supervising and coordinating between contractors during start up and operation of the units.

•Following up operation schedule and try to achieve it.

•Monitoring all contractors activities involve with start up and operation and push them to achieve plant schedule.

•Permit to work for work orders and precede LOTO to facilitate the isolation. Of equipments for maintenance.

•On job training and supervise owner shift engineers.

•Identifying and investigate the problems to troubleshoot.

[ 1/10/ 2008 - 30/9/2009]

Cockerill Maintenance & Ingénierie company

ELKURIMAT 2 POWER STATION 750 MW COMBINED CYCLE [1/10/ 2008 - 30/12/2008]

NEW TALKHA POWER STATION 750 MW COMBINED CYCLE [ 1/1/ 2009 - 30/9/2009]

Position : Commissioning And Start Up Engineer.

Responsibilities:

•Monitoring and operating of the plant Equipments from the local.

•Reach Normal Points of the normal operation of all plant .

•Calibration of all field instruments.

•Calibration of supervisory instruments.

•Calibration of all valves (pneumatic - motorized - hydraulic).

•Troubleshooting for any problem that appears during tests.

•Monitoring the behavior of all instruments with the Ovation system; start up& preparation. Calibration of all field instruments.

[1/1/2008 - 30/9/2008]

SKODA PRAHA

NEW TALKHA POWER STATION 750 MW COMBINED CYCLE [1/1/2008 - 30/5/2008 ]

ELKURIMAT 2 POWER STATION 750 MW COMBINED CYCLE [1/6/2008 - 30/9/2008]

Position : Commissioning And Start Up Engineer.

•Monitoring and operating of the plant Equipments from the local.

•Reach Normal Points of the normal operation of all plant .

•Calibration of all field instruments.

•Calibration of supervisory instruments.

•Calibration of all valves (pneumatic - motorized - hydraulic).

•Troubleshooting for any problem that appears during tests.

•Monitoring the behavior of all instruments with the Ovation system ; start up& preparation(steam blow, bypass operation, reliability test)

•Familiar to make energize for any (motorized, pneumatic) valves from MCC.

•Troubleshooting internal and external fault in modules in DCS (OVATION system)

[23/3/2002 - 30/12/2007]

East Delta Electricity Production Company, Egypt.

TALKHA Power Plant 2X210 MW [ 13 /3/2004 - 20/9/2007]

Position: Shift Engineer

Responsibilities:

•Operation of intake Pump Station.

•Operation of fire fighting systems.

•Perform Switchgear operation with national Control Center to connect and disconnect 220KV unified grid functions.

•Operation of steam Turbine.

OYUON MOSSA Power Plant 2X320 MW [23/3/ 2002 to 13/3/ 2004]

Position : I&C Maintenance ENGINEER

Responsibilities:

•Calibration of all instruments in field (pressure transmitters& switches-level transmitters & Switches-thermocouples-smart valves).

•Troubleshooting for any problem with BAILEY DCS control system during unit operation.

•Perform maintenance for all plant instruments.

•Perform maintenance and recalibration of all valves (pneumatic - motorized - hydraulic).