CURRICULUM VITAE
BUHARI M
Bodinayakanur
Theni Dist -625513
Course : B.E,MBA
Mobile : 098********,781-***-****
EMail:********@*****.***,**************@*****.***
OBJECTIVE
Seeking a challenging and growth oriented position in engineering field, which utilizes my skills while mutually benefiting my employer and myself. To keep myself updated to meet the challenges of the fast changing technology
WORK EXPERIENCE
Company : EICS Power Services (P) Ltd., Chennai.
Designation : Project Management & Execution Engineer.
Type of Project : Coal Based & Waste Heat Recovery Power Plant
Tenure : From Nov 2009 to Till Nov 2014
Experience : 5+ years Experience (Thermal Power Plant)
Boiler make
SL.NO
Boiler
Make
Fuel
Produced
1
AFBC (Atmospheric Fluidised Bed Combustion)
M/s.Cethar vessels Pvt Limited - Tiruchirapalli
Coal
Steam
2
WHRB (Waste heat recovery boiler)
M/s.Cethar vessels Limited - Tiruchirapalli
Char
Steam
Turbine make
SL.NO
Turbine
Make
Type
Inlet Steam Pressure
Inlet Steam Temperature
Produced
1
Steam Turbine
M/s.Triveni Turbine Pvt Limited (Bangalore,Karnataka)
Multistage, impulse, nozzle governed bleed cum condensing
64 Ata
4800c
Steam
Site Experience:
Deputed to site for 5 months to look after AFBC & WHRB Erection.
RESPONSIBILITY & RESPONSIBILITIES
Reporting to Manager.
Guiding & Provide Inputs to Contractors
Maintaining of Drawings & Documents
Maintain Quality & Quantity of work at site
Preparation of Protocols & Test Reports
Preparation of site indent
Preparation of Weekly site progress report
Reporting Design Changes required & Site feedback to manager
Checking the quality & Quantity of the materials received at site
Preparation of Materials Receipt note.
Preparation of Gist of Agreement / Equipment Purchase Order
Updating list of deliverables
Updating of supplier schedule
Periodical updating of Documents & Record.
Preparation & Maintenance of all documents / Records
Follow up with site for receipt of documents & Records
Follow up with site to get Status of Project.
Checking of Contract bills.
Checking of protocol along with drawings
Preparation of Process Monitoring
Preparation of Monthly progress report.
Maintain ISO and able to carry out internal audits as per ISO 9001:2008
PROJECTS HANDLED
Client : M/s. Basai Steels (P) Ltd. Bellary, Karnataka.
CONFIGURATIONS:
1 x 20 MW Coal & Waste Heat Recovery Based Captive Power Plant.
1 x 80 TPH AFBC Boiler & 2 x 10 TPH WHR Boilers.
20 MW Steam Turbine Generator with Air Cooled Condenser.
Fuel – Indian Coal & Char
PROJECTS HANDLED
Client : M/s. Padmavati Ferrous Ltd. Bellary, Karnataka.(On-going Project)
CONFIGURATIONS:
1 x 12 MW Waste Heat Recovery Based Captive Power Plant.
1 x 27 TPH AFBC Boiler & 4 x 10 TPH WHR Boilers.
12 MW Steam Turbine Generator with Water Cooled Condenser.
Fuel – Indian Coal & Char.
EDUCATIONAL QUALIFICATION.IFICATION
FICATION
BACHELOR OF ENGINEERING (2003 - 2007)
SPECIALIZATION : MECHANICAL ENGINEERING.
PROGRAMME : 4 YEARS.
INSTITUTION : ANNAMALAI UNIVERSITY, TAMIL NADU.
UNIVERSITY : ANNAMALAI UNIVERSITY, TAMIL NADU.
PERCENTAGE : 7.05* (* CGPA out of 10)
MASTER OF BUSINESS ADMINISTRATION
SPECIALIZATION : HUMAN RESOURCE MANAGEMENT
PROGRAMME : 2 YEARS.
UNIVERSITY : ANNAMALAI UNIVERSITY, TAMIL NADU.
TRAININGS
Professional Programme in CATIA(Computer-Aided Three-Dimensional Interactive Application),
Course Conducted by:
Tiruchirappalli Regional Engineering College Science & Technology Entrepreneurs Park.
(Promoted by : Dept of Science and Technology, Govt of India, New Delhi)
OUT-OF-WORK ACHIEVEMENTS, INTERESTS AND HOBBIES
Reading books and playing cricket.
PERSONAL DETAILS
Father Name : NPKS.Mohamed Nainar
Gender : Male
Languages known : English, Tamil
DECLARATION
I hereby declare that the information furnished above is true to the best of my knowledge.
Place: Chennai (M.BUHARI)
Date:25.08.2016 f