Post Job Free

Resume

Sign in

Coating Painting Inspector

Location:
Batam, Riau Islands, Indonesia
Posted:
December 13, 2016

Contact this candidate

Resume:

R E S U M E

Personal Information

Education Background & Professional Training

No

Certificate Date

Professional Training

1

2

3

4

5

6

7

September 20, 2002

June 6, 2009

June 2, 2010

September 25, 2011

November 22, 2011

January 4, 2013

August 3, 2016

Degree of Information Management and Computer at YPTN-AMIK BATAM

Coating Inspector Indonesian corrosion Level-1 Conducted by an INDOCOR’S Authorized Training Body for research and development of corrosion and material product. Held in Bandung on June 1st – 6thth, 2009

Certificate no: 027/IC.I/I-65/VI/2009

Coating Inspector Indonesian corrosions Level-2 Conducted by an INDOCOR’S Authorized Training Body for research and development of corrosion and material product. Held in Bandung on May 31st – 2nd June 2010

Certificate no: 015/IC.II/16/V/2010

ASNT-SNT-TC-1A (2006), NDT UT Level-2 Conducted by Annamalai Institute of NDT Batam.

Certificate no: UT003/09/11

ASNT-SNT-TC-1A (2006), NDT MT/PT Level-2 Conducted by Annamalai Institute of NDT Batam.

Certificate no: MT04/11/11, PT004/11/11

T-BOSIET Training at PT. Indika Jaya Pratama, Balikpapan

CSWIP WI 3.0, Certificate No 110602, Exp. Date : 02 Aug 2021

Working Experiences

No

Company Name

Position

Project Name

1

PT REKAYASA INDUSTRI

Pipeline QC Coating, Painting, Insulation, Welding Inspector

Pertamina EP, Donggi - Senoro. Proyek Pengembangan Gas Matindok

Period

12 Dec 2013 – 30 June 2016

Job Description

Visual Inspection incoming bare pipe, Witness and monitoring on Inspection of surface preparation Blasting, Coating, Painting and Insulation (check abrasive, surface profile, environmental and Perform test such as Blother Test, Relative Humidity (RH), Dry Film Thickness (DFT), Salt Testing and Holiday test. Material Inspection Report and Traceability Records, Final Inspection.

Reason for leaving

End of Project

2

TOTAL EP & P Balikpapan on behalf of PT Radiant Utama Interinsco Tbk

NDT Phased Eddy Current Inspector

Maintenance of T970 Tank, Dia. 77Mtr

Period

20 August – 7 Sept 2013

Job Description

Visual Inspection of Coated welded joints, Inspection Welding Joint Annular to Shell of Tank with Phasec3 Tester. Analyses defect and reporting.

Reason for leaving

End of Project

3

PT Inwha Indonesia

QC Painting

Banyu Urip Project, EPC1

Period

28 March – 28 July 2013

Job Description

Visual Inspection of welded joints, Witness and monitoring on Inspection of surface preparation Blasting and Painting (check abrasive, surface profile, environmental and Perform test such as Relative Humidity (RH), Dry Film Thickness (DFT), Wet Film Thickness(WFT), Salt Testing and Holiday test, Material Inspection Report and Traceability Records, Final Inspection of Structural Assembly.

Reason for leaving

End of Contract

4

TOTAL EP & P Balikpapan on behalf of PT Radiant Utama Interinsco Tbk

NDT Phased Eddy Current Inspector

Maintenance of T1090 Tank, Dia. 77Mtr

Period

12 March – 26 March 2013

Job Description

Visual Inspection of Coated welded joints, Inspection Welding Joint Annular to Shell of Tank with Phasec3 Tester. Analyses defect and reporting.

Reason for leaving

End of Project

5

TUV on behalf of Thailand Nippon Steel

Coating/Painting Inspector

SALAMANDER ENERGY (BUALUANG) LIMITED, Process & Utility Modules BLPMB, Hydro Cyclone System

Period

4 February – 5 March 2013

Job Description

Visual Inspection of welded joints, Witness and monitoring on Inspection of surface preparation Blasting and Painting, Final Inspection of Structural Assembly.

Reason for leaving

Finished Project

6

PT PROFAB

QC Painting Inspector

OSX 3 FPSO, JN1026

Period

October 2012 – January 2013

Job Description

Visual Inspection of welded joints, Witness and monitoring on Inspection of surface preparation Blasting and Painting (check abrasive, surface profile, environmental and Perform test such as Relative Humidity (RH), Dry Film Thickness (DFT), Wet Film Thickness(WFT), Salt Testing and Holiday test, Material Inspection Report and Traceability Records, Final Inspection of Structural Assembly.

Reason of Leaving

Finished Project

7

PT. WASCO ENGINEERING on Behalf of PT Radiant Utama Interinsco, tbk

NDT MT/PT/UT Inspector

OSX 3 FPSO E-House, GLNG, D1 and CENDOR

Period

January – October 2012

Job Description

Prepare inspection procedure and inspection report forms, Responsible for technical data review, NDT Inspection as per clients spec, Report of Inspection.

Reason of Leaving

Finished Project

8

PT. McCONNEL DOWELL on Behalf of PT Radiant Utama Interinsco, tbk

NDT MT/PT/UT Inspector

TONKOLILI STAGE

Period

September – December 2011

Job Description

Prepare inspection procedure and inspection report forms, Responsible for technical data review, NDT Inspection as per clients spec, Report of Inspection.

Reason of Leaving

Finished Project

9

PT. Ho Wah Genting

Electrical Asst. Engineer

Wire and Cable Manufacturer

Period

August 2009 – September 2011

Job Description

Prepare Machine Operation/Repair/Maintenance/Modification Procedure, Responsible for technical data review, Product Inspection as per clients spec, Reporting.

Reason of Leaving

End of Contract

10

PT. Matsushita Kotobuki Peripheral Indonesia

Senior Technician

Harddisk Drive Manufacturer

Period

July 1994 – July 2009

Job Description

Prepare Machine Operation/Repair/Maintenance/Modification Procedure, Responsible for technical data review, Product Inspection, Reporting.

Reason of Leaving

Resigned