Post Job Free

Resume

Sign in

Project Manager

Location:
Chino Hills, CA
Salary:
75 us plus per deum
Posted:
April 21, 2016

Contact this candidate

Resume:

RESUME OF LARRY BASHOR

*** * ******* **. **.

Las Vegas, NV. 89107

CELL No. 909-***-****

EMAIL – acugf5@r.postjobfree.com

Highly Skilled, motivated and loyal, Piping Design Supervisor / Senior Piping Designer with 30+ years' experience in the Oil & Gas Industry – specializing in petro chemical. Extensive domestic and international project experience. Effective management of project, construction and client development – with complete ownership of team performance. Receptive to both long and short term assignments, closely coordination with all members of the team / organization to attain meeting of the Company Objectives. With a focus on ensure design integrity with, operation maintenance and safety in mind at all times.

EDUCATION: AA Degree in Pressure Piping Design from Rio Hondo College Whittier, CA

Currently Pursuing BS in Mechanical Engineering.

TRAINING: Fluor Training in Petrochemical Plant Layout 1, 2, 3, & 4, P&ID Layout, Intergraph, Training for PDS, Piping and Equipment, Auto-Cad 2004

PROFESSIONAL STRENGTHS

All aspects of project execution, including definition of objectives / team building / opportunity assessments / checking / design / design management in single or multiple office structure / field work / construction.

Strict conformance to budget / schedule / change management mandates / quality, safety and ethical standards.

Solicitation and execution of the most challenging assignments in either established product lines or new company technologies and markets.

Troubleshooting experience.

Establishment of plant layout to client and company standards.

Highly skilled in taking lead role through design development and implementation inclusive of regular client coordination.

Operated: PDS, Piping and Equipment with over 15 Years of experience, Bentley Plant space, Auto CAD version 13, Auto CAD MEP, Excel, word.

I do have a TWIC’s cared.

PROFESSIONAL EXPERIENCE

Jabo Industries

Los Angeles, California

12/2/2014 to Present, Senior Piping Designer

Working on Line Breaks, and Pipe Line Replacement, for Southern California Gas, duets include, scheduling work, tracking work completed, attending meeting, interacting with the client, and other disciplines, preparing documents, develop piping drawings, as well as other disciplines drawings.

Zachry Engineering

Denver, Colorado

1/15/2014 to 11/21/2014, Senior Piping Designer

Working on LG &E Mill Greek Cole fired power plant, on system piping from high pressure steam lines to and from the steam turbine to cooling water, laying out of pumps, vessels, storage tanks, cooling towers, pipe racks, area and process, underground drain lines, utilizing, and Bentley Plant space. Using AutoCAD

Silver Eagle Refinery

Evanston Wyoming

5/17/2013 to 12/18/2013, Senior Piping Designer

Multiple challenging projects, adding pumps, vessels, underground drains, underground process piping, for turner around, Responsible for designing changes, review of vendor drawings, field routing, and dim’s, of changes, included field review of the project, working with other disciplines, utilizing PDS Equipment and piping Modeling,

Jacobs

Denver, Colorado

Morencs, Arizona

1/13/2013 to 4/1/2013, Supervisor / Senior Piping Designer

Worked on the Shell Oil, oil sands project in Fort McMurray, Canada, I was responsible for the layout of three new Enclosed Module Transfer Pumps, and re-work of an existing pump, and pipe line, also directed five other people in their work, field assignment at Freeport McMoran Copper & Gold, for the 55K copper expansion, responsible for: solving field problems, locating material, soling interferences between disciplines, coordination between contactor, attending daily Safety and coordination meetings, working with, PDS Equipment and piping modeling.

CHM2Hill

Phoenix, Arizona

Portland, Oregon

Dublin, Ireland

2/18/2012 to 1/13/2013, Senior Piping Designer

Equipment layout for new research facilities for Intel Corporation, in their Phoenix, AZ. Portland, OR. and Dublin Ireland plants, Layout of pipe ways, storage tanks, pumps, drains, General Layouts per revisions, utilizing Auto CAD MEP, Equipment layout for new research facilities for Intel Corporation Phoenix AZ. plan, Layout of pipe ways, storage tanks, pumps, General Layouts per revisions, utilizing, PDS Equipment and piping modeling.

Peak Technical

Monrovia, California

8/8/2011– 2/10/2012, Senior Piping Designer.

On contract with Worley Parsons, Front end layout, of a Naphtha Splitter and Continuous Catalytic Reformer units, for The New Zealand Refining Co. My primary tasks consisted of the preliminary layout of the, Heater, Reactors, Air Coolers, Vessels, Pipe ways and Pumps, underground drain systems, for the Continuous Catalytic Reformer units, on the Naphtha Splitter, laid out the 185’ tall Naphtha Splitter Columns and Reboiler, Exchangers, pumps, Horizontal Vessel and Pipe Racks, following the preliminary review, rolled over to final design, using PDS Equipment and piping Modeling.

CHM2Hill

Phoenix, Arizona

Portland, Oregon

12/17/2010 – 8/11/2011, Senior Piping Designer

Equipment layout for new research facilities for Intel Corporation Phoenix AZ. plan,

Layout of pipe ways and storage tanks, pumps, Portland OR. Equipment layout for new research facilities for Intel Corporation Portland OR. Plant, Layout of pipe ways, Stripers, Pumps and tanks, utilizing Auto CAD MEP

Technip USA, Inc

Claremont, California

2006 – 2009 Piping Design Supervisor

Lead designer on a Hydrogen Plant HOU2, for GS Caltex, in Korea, primary responsibility, supervise 6 designers, scheduling work, tracking work completed, attending meeting both locally and international, interacting with the client and other disciplines, the preliminary layout of the unit, progress reviews, interacting with contractor, fabricators, and suppliers, thru the design stage of the project, and supported the field during construction, both in the office and in the field, the project was on time and under budget

Due to the success of the first project GS Caltex requested the same team to build a second Hydrogen Plant HOU4, for GS Caltex, in Korea, My responsibility, were the same as for the first project

Preformed a preliminary lay out of a CO2 plant for bid purposes working with PDS Equipment and piping Modeling.

Checker on a hydrogen plant.

Field work on CNRL in Canada to resolve construction conflicts.

.

CB &A.

Birmingham, Alabama

2005 – 2006 Project Mgmt

Project manager, multiple challenging projects on a polymer plant for Daikin America, Inc, Responsible for project up to 1 million dollars, Duties included field review of the project, review vendor drawings, design routing of the of lines, utilizing PDS Equipment and piping Modeling, assemble construction bid packages, reviewed the bid packages, worked closely with the construction contractors, during construction coroneted between the refinery, management, and the contractors.

JHK Systems

Birmingham, AL

2004 – 2005 Piping Designer

Revamping paper mill projects, reviewed project requirements, scheduling work, field rout line, worked closely with other disciplines to resolve conflicts in plant design.

J & D Group

Birmingham, AL

2001– 2004 Principal Piping Designer

Managed several small projects of Process Plants, coordinated between other disciplines, project management and with the Client, followed up with the field during construction, Worked closely with project to obtain required budget and schedule performance.

I can supply complete work history if needed.



Contact this candidate