Post Job Free
Sign in

Manager Project

Location:
Carlsbad, CA
Posted:
May 14, 2015

Contact this candidate

Resume:

Matthew R. Smith

Project Manager/Construction Manager

**** ******** ***.

Carlsbad, CA 92008

760-***-**** (home)

619-***-**** (cell)

***********@*****.***

Professional Background

BS/1989/Construction Management, California Polytechnic State University-

SLO

Years in Practice: 24

Years in Last Firm: 16

Affiliations:

Construction Management Association of America

Background

I have over 24 years of specialized experience in project management,

construction management, contract administration, estimating and scheduling

services on water treatment, wastewater treatment plants, water

transmission pipelines, pump stations, large power generating facilities,

ocean dredging projects and upstream oil and gas programs. As a

project/construction manager, my responsibilities included planning, design

oversight, oversight of land acquisition, permitting, pre-construction,

estimating, scheduling, subcontracting, project completion, start-up and

close-out.

After leaving JPM Co I worked part-time, interviewed with several companies

while steadfastly looking for full time work.

Representative Project Experience (JPM Co., Jacobs, Sverdrup, LH Woods &

Sons, Hunter Corp.)

Jacobs Civil, Inc. (1995-2011) Project/Construction Manager primarily

involved in five of the largest CIP projects in the country namely the San

Diego Clean Water Program, the Gwinnett County Georgia CIP, the San Diego

County Water Authority, the SFPUC Hetch Hetchy Program and the BP San Juan

Coal Bed Methane Project.

Point Loma Wastewater Treatment Plant Grit Improvement Project San Diego,

CA (2010-2011).

SFPUC Project East Bay Pipeline San Francisco, CA (2010-2010 Short term six

month assignments).

BP San Juan Coal Bed Methane Project Durango, CO (2010-2010 Short term six

month assignments).

San Diego County Water Authority Peak Services Contract San Diego, CA (2007-

2010).

Gwinnett County Department of Public Utilities Gwinnett County, GA (2004-

2007).

Point Loma Wastewater Treatment Plant expansion as part of the $1.2 billion

Capital Improvement Program for the San Diego Clean Water Program San

Diego, CA (1997-2004). I worked as a Contracts Manager then Deputy

Construction Manager for direct on-site manager, including inspection,

quality control, and safety team for the delivery of ten separate

construction contracts. The Point Loma Wastewater Treatment Plant expansion

(250 MGD) consisted of $168 million of the program.

L.H. Woods & Son, Inc.: (1996-1997). Senior Estimator responsible for

estimating the costs of large diameter water transmission pipeline projects

for public agencies. This effort involved the detailed quantity take off

and pricing of all costs for materials, labor, equipment, subcontractors,

and overheads in addition to the closing of the bid. Also responsible for

schedule creation and updating, preparation and negotiation of change

orders, coordination of subcontractors and vendors and attending progress

meetings with the owner agency staff. Personally developed a computer-based

estimating program using Timberline Estimating software, which was tailored

to suit specifically the way LHW put bids together for these projects,

enabling them to bid work more accurately and efficiently.

Hunter Corporation: (1989-1996). Senior Estimator responsible for

estimating the costs of construction for water and wastewater treatment

facilities, large diameter water transmission pipeline projects, water and

wastewater treatment facilities and marine dredging projects. This effort

involved the detailed quantity take off and pricing of all costs for

materials, labor, equipment, subcontractors, and overheads in addition to

the closing of the bid. Also responsible for schedule creation and

updating, preparation and negotiation of change orders, coordination of

subcontractors and vendors and attending progress meetings with the owner

agency staff. Personally developed a computer-based estimating program

using Timberline Estimating software, which was tailored to suit

specifically the way Hunter put bids together for these projects, enabling

them to bid work more accurately and efficiently.

References:

Richard Snow

Senior Civil Engineer

Metropolitan Wastewater

Department

1902 Gatchell Road

San Diego, CA 92106

619-***-****

Jerry Williams

Plant Engineer

Metropolitan Wastewater

Department

1902 Gatchell Road

San Diego, CA 92106

619-***-****

Paul Winkler

General Manager

Apex Technical Sales

1214 Park Street

Suite 201

Paso Robles, CA. 93446

505-***-****

Marty Glaske

Director of Labor Relations

Gafcon

5960 Cornerstone Court West

Suite 100

San Diego, CA 92121

858-***-****

Project List by Client

City of San Diego Point Loma Wastewater Treatment Plant Grit Improvement

Project San Diego, CA (2008-2011). Construction Manager, On-site manager

for the delivery of construction management services responsible for

construction management and inspection team. The Point Loma Wastewater

Treatment GIP project is valued at $28 million which will last three years

with multiple plant shutdowns. We were especially pleased to introduce the

City of San Diego Engineering and Capital Improvements Division to

Sharepointe project management system for team collaboration during the

execution of this project. This software allowed us to share information

online in real time between all necessary team members. This vastly

improved the time for the turnaround of critical project documentation and

decision making necessary to cut down on paper as well as mailing expenses

to the Owner.

SFPUC Project East Bay Pipeline San Francisco, CA (2007-2008). Construction

Manager for a $69 million seven mile 72 inch welded steel water

transmission main connecting the east bay transmission main to the

connection of water mains leading to the city of San Francisco. This was

one major project in the overall $4.3 billion program improving delivery of

water from the Hetch Hethcy reservoir to the larger Bay Area.

British Petroleum (BP) San Juan Coal Bed Methane Project Durango, CO (2006-

2007). Site Coordinator as part of a General Contractor team role

supervising both Jacobs staff as well as on-site subcontractor tradesmen

serving BP in developing its' 800 well head sites as well as distribution

piping systems, compressor stations and production water disposal systems.

The program is part of the $1.4 billion EPCM construction phase that Jacobs

was involved in 2008. The program included interfacing with engineering,

procurement, construction oversight of subcontractor tradesmen, operations,

start-up and turnover to client staff.

San Diego County Water Authority Peak Services Contract San Diego, CA (2003-

2007). Capital Improvement Program as a Project Manager as part of a team

serving the Authority to deliver the $3.1 billion CIP. Projects include

pipe relining program, flow control facilities, master planning for

emergency storage projects, other program related activities.

Gwinnett County Department of Public Utilities Gwinnett County, GA (2007-

2010). Project/Construction Manager for multiple large PCCP water

transmission replacement pipelines, water treatment plant upgrades and

sewer pipeline replacement projects.

Lanier Filter Plant Water Production Facility - Various plant upgrades to

150 MGD primary water production facility including; new raw water

distribution structure, filter facility rehabilitation, facility

security, chemical storage facilities, filter rehabilitation, ozone

generator, architectural improvements, and overall site spill containment

facilities.

DPU-Mezzanine Build-out Project - Tenant improvement project of space that

will provide over 130 additional staff office spaces for the execution of

the overall program.

PCCP Replacement Program - Replacement of 48" PCCP water pipe including

evaluation and assessment of existing PCCP water pipe. Program to include

professional services contract to evaluate 38 miles of 48", and 72" PCCP

in the County's raw water and transmission system and to design and

construct replacement pipe for these lines.

Raw Water Distribution Structure - This project consisted of a concrete

distribution structure along with inter-connecting piping between the

existing raw water head chamber and the new facility along with valves,

controls, and other architectural features.

Dacula 16 inch Water Main Project - 19,000 lf of new water main service

an area of the county critical to future development.

Danbury Creek Sewer Replacement - Replacement of 4,000 lf of deteriorated

sewer lines in established neighborhoods running down the middle of a

creek. The construction methods included traditional dig and lay, cure

in place pipe replacement and pipe bursting.

Hammond Dr/Lanier Blvd Water/Sewer Replacement Project - 5,600 lf of

gravity sewer and water distribution main project to alleviate chronic

sewer back-ups while providing better fire protection capability.

Skyland Drive Water Main Replacement Project - 7,000 lf of water

distribution main project to alleviate chronic system breaks.

Point Loma Wastewater Treatment Plant expansion as part of the $1.2 billion

Capital Improvement Program for the San Diego Clean Water Program San

Diego, CA (2002-2004). Deputy Construction Manager, On-site manager for

the delivery of construction management services responsible for

construction management and inspection team for multiple contracts. The

Point Loma Wastewater Treatment Plant expansion (250 MGD) consisted of $168

million of that program.

Maintenance Building Expansion- The addition of a second story which

consisted of office space and conference rooms as well as rehabilitation

of the first floor along with exterior architectural improvements to

comply with overall plant site color scheme and architectural plan.

North Operations Building- The construction of a new three story

operations, control and laboratory facility housing in one location all

supervisory control from the Distributed Control System for the entire

plant. This new building also complies with the architectural

improvements to comply with overall plant site color scheme and

architectural plan.

New Chemical Building and Chemical Storage Facility- The facility

included the construction of a new chemical storage facility with

containment walls, distribution piping, pumping, and metering. This

project also entailed the rehabilitation and re-use of and abandoned

building once used for a similar use. The main objective of the facility

was safety improvements for overall plant staff and that of the chemical

delivery safety.

Digesters 7&8 - Construction of two new digesters, methane gas balancing

tank, new excess gas flare facility, and development of large earthen

berm from material excavated on-site from new digesters in order to hide

the overall plant site from the historic Cabrillo National Monument. Also

included was the adjoining mechanical facility housing all of the large

piping, valves, pumps heat exchangers, electrical, digester cover

insulation, I&C and supervisory control from the Distributed Control

System.

Point Loma Wastewater Treatment Plant - San Diego, CA (1997-2002). As

Contracts Manager for the $1.2 billion Clean Water Program, managed all

facets of construction for five projects.

North Shoreline Protection Improvement Project - This project included

the preparation for, and placement of 8-ton rocks as a revetment at the

base of the coastal bluff to mitigate marine erosion, and the

construction of a 30+-foot high tied-back shot crete wall to stabilize

the upper bluff.

Scum Removal, Concrete Restoration and Odor Control Upgrades- This

project consisted of the complete concrete restoration of the secondary

clarifier tanks which included protective concrete coating system to

prevent future corrosion of the concrete above the water line, along with

scum removal equipment, sludge removal equipment, odor control equipment,

electrical/piping bridge, I&C and the addition of supervisory control

from the Distributed Control System.

Gas Utilization Facility Pre-purchase - This project required working

with the Owner, the designer and the construction manager to procure a

supplier to furnish for installation by a General Construction

Contractor, two-digester gas/natural gas fueled engine generator sets,

all associated heat recovery systems, and all associated appurtenances

including switchgear.

Gas Utilization Facility Package A - This project modified the existing

Gas Utilization Facility (GUF) to allow installation of a 1500 Kilowatt

diesel engine generator. Also included were new heat exchangers, new

effluent pumps, restoration of the existing and construction of new

compressor facilities as well as a new motor control center with

supervisory control from the Distributed Control System.

Gas Utilization Facility Package B&C - This project upgraded the existing

Gas Utilization Facility (GUF) to allow the installation of new

electrical distribution switchgear, power generators, heat recovery

equipment, site-wide electrical distribution duct banks and power

centers. Also included were new heat exchangers, hot water distribution

pumps, all with supervisory control from the Distributed Control System.

Digester C1&C2 Upgrades - Complete rehabilitation of two of the existing

eight digesters. Included was the adjoining mechanical facility housing

all of the large piping, valves, pumps heat exchangers, electrical,

digester cover insulation, I&C and supervisory control from the

Distributed Control System.



Contact this candidate