Professional skills in electrical engineering related to Oil and Gas industry. I have relevant experience in

installation, pre-commissioning, start-up, operation, maintenance, test, troubleshooting, repair and

overhaul of electrical equipment at a big leading petrochemical company in the Middle East.

I worked with a team of chemical, mechanical, electronic, electrical and process engineers near 14 years

and managed 62 employees of electrical department. I am a permanent resident of the United States and

eligible to work in the USA.

WORK HISTORY

Electrical Maintenance Department Manager

April 2013 – December2014

Amir Kabir Petrochemical Complex (6th Olefin)

Mahshahr, Iran

Responsibilities

Manage, plan, organize, assign and inspect the work of Electrical Maintenance Department.

Provide technical resources to support electrical maintenance efforts for troubleshooting

assistance and supporting projects to deal with identified equipment.

Lead and support electrical incident investigation with root cause analysis.

Provide technical support to production and maintenance organization to evaluate and resolve

maintenance problems and reduce maintenance costs.

Maintain protection of the environment and the health and safety of electrical department’s

employees and clients.

Prepare annual and long-range operation plans and objectives.

Develop detailed estimates leading to funding appropriation and approval.

Prepare scoping, review proposals and detailed designs, and follow-up on execution of important

projects.

Manage general engineering services (GES) design contractor activities during the development

of project proposal, including definition of project work scope and schedule requirements.

Assign the tasks of developing budgets, material, estimating labor and project construction costs.

Recruit, build, train and manage a team of professional engineers, technician and journeyman to

service all the electrical projects and maintenance procedures.

Place order for spare parts and maintain an inventory record of the same.

Electrical Maintenance Engineer

November 2006 – March 2013

Amir Kabir Petrochemical Complex (6th Olefin)

Mahshahr, Iran

Responsibilities

Head of electrical department of Olefin, Utility, Butadiene and Buten1 plants (July 2011 –

March 2013)

Supervisor of electrical department of Utility, Butadiene and Buten1 plants (May 2008 – June

2011)

Supervisor of electrical department of HDPE, Butadiene and Buten1 plants (Nov. 2006 –

April 2008)

Professional expertise in Industrial Electrical Maintenance and supervision responsibilities.

Prepare and perform electrical design packages and specify materials to add new equipment or

modify existing systems.

Prepare and justify cost estimates for plant electrical improvements and replacement of worn out

equipment in compliance with health, safety and environmental standards.

2

Perform testing, monitoring and calibration procedures for electrical equipment.

Conduct scheduled checks, inspect, and detect any short circuits and electrical malfunctions via

read blue prints.

Perform electrical system studies such as load flow, short circuit calculation, protective device

coordination and cable sizing, using computer software E-TAP 11.

Repair, replace and refurbish damaged electrical units.

Routine Tests of protective relays and electrical equipment.

Troubleshooting, repairing, maintain and doing PM programs (preventive and predictive) for

electrical utilities and distribution systems from 400V up to 132000V, power and distribution

transformers, breakers, protection relays, large electrical motors and MCC room, D.C. chargers

and UPS systems, Siemens PLC and VFD and all electrical subsystems like fire alarm, lighting,

switchgears, control circuits, Diesel generators and HVAC.

June 2001 – October 2006 Electrical Project Engineer (large Olefin plant project)

Amir Kabir Petrochemical Complex (6th Olefin)

Mahshahr, Iran

Responsibilities

Develop and execute of electrical projects such as installation, termination, test,

specification, pre-commissioning and commissioning electrical equipment from 400V to

132KV including Power and Distribution Transformers, Switchgear, Breaker

(SF6&Vacuum), MCC room, Distribution Board, Wiring, Cable pulling, Three phase

electric motors, UPS, D.C. Charger and Protection Relays.

Review and understand equipment and instrumentation/electrical specifications to ensure

equipment and materials are procured and installed as per regulatory bodies (IEC, IEEE,

NEC, API etc.) and company’s engineering standards and specifications.

Perform function checks, testing and start- up.

Resolve design or specification conflicts.

Coordinate and review vendor equipment, installation and other discipline drawings for

operability, reliability and maintainability input.

Monitoring installation and operation of electrical equipment in Hazardous areas.

Provide technical support to staff at all levels.

Skills and Qualifications:

Self-Motivator, able to work independently with minimal supervision.

Team Player, ability to work well with others.

Versatile, able to handle demands of dealing with vendors and customers in multiple

projects on a daily basis.

Leadership, strong management skills, able to oversee production of individual projects

and provide direction as need.

Problem Solver, ability to work through various challenges.

Innovator, finding innovative solutions for common and unusual problems.

3

Mechanical and Hands on.

EDUCATION

Electrical engineering (Power), Bachelor of Science

March 2001

Hormozgan University, Bandar Abbas, Iran

POST GRADUATE SHORT COURSES

2015, OSHA 30 Hour, General Industry - 360 training.com

2015, ESTS Electrical Worker USA V1.0, Arc Flash & Shock - NETA Training.org

2013, ETAP11 (Load flow, Relay coordination, Short circuit calculation and Cable sizing) – Aria

Petronir.co

2013, Selection, Testing, Maintenance & Protection Electric Motors – Aria Petronir.co

2012, Safety & 5S – Japan Cooperation Center for Middle East (JCCME) & NPC

2010, Problem Solving Tools as an Effective means of Team work - A.K.P.C.

2006, Emergency Response in Petroleum, Natural gas, and Petrochemical – kayen-co

2006, Electrical License for Supervising Building Construction - Iran Engineering Organization

Achievements and Awards

Defining, supervising and monitoring a project to changing the number of correction

factor from 0.85 to 0.95 in contact between Amir Kabir petrochemical co. and Fajr power

plant.

Cable resizing, cable route design, material ordering and installation of 18 single core

1*500 mm2, 6 KV of cooling tower substation.

Above grounding of joints of 6 single core cable 1*630mm2, 33 KV by changing of

route, joints & parts of cables of Olefin plant.

Changing of 12 ACBs of LV SWBs of HDPE & Buten1 plants by 3WL SIEMENS ACBs

including ordering and installation.

Team member of ISO9000, ISO14001, OHSAS18001 and IMS.

Introduced as a distinct H.S.E.Q in September 2007 at A.K.P.C.

Received an award for major repairs from our company’s CEO in August 2013.