Summary of Experience
Specialist of mechanical piping design; plant layout and checking.
Experienced in petro-chem, co-generation, geo-thermal, refinery expansion,
upstream facilities, clean fuels modernization, grass roots and revamped
facilities. Experience with most all petro-chem equipment, such as; multi-
pass trayed distallation columns, fired heaters, reactors, reciprocating
and centrifical compressors, high pressure exchangers, high temperature
pump systems, steam turbines, and air coolers. Experience with cross-
country pipelines and well-pad equipment layout. Extensive refinery revamp
experience. Supervision of up to ten designers and checkers.
Work History
. Ramsgate Eng., Inc., Bakersfield, Ca. Mar. 2013- Feb. 2015
Design Specialist, Oil Field Production & Gas Gathering, Steam
Injection, Aera Belridge Leases, Ca.,
Layout of oil and gas gathering piping requiring extensive field
surveys. Production of contract deliverables, such as Plot Plans,
Piping Plans, Sections, Material Bills and Iso's, utilizing Autocad
2013, Cadworx 2D and Excel.
Title 5 Upgade, Plains Gas Plt, Schafer, Ca. Layout of three pairs of
compressors, routing of tie in piping requiring field surveys.
Hydrogen heater upgade. Development and production of contract
deliverables, such as Plot Plans, Piping Plans, Sections, Material
Bills and Iso's, utilizing Autocad 2013, Cadworx 2D and Excel.
. Mustang Engineering, Bakersfield, Ca. Mar. 2010- Mar. 2013
Design Specialist, Water Plant Upgrade, Extensive revamp requiring
addition of Uni-Cell, 10 process pumps, drain tank and pumps. Approx.
2 miles of X-Country Pipeline. Field surveys utilizing Trimble GPS.
Development and production of contract deliverables, such as Plot
Plans, Piping Plans, Sections, Material Bills and Iso's, utilizing
Autocad 2008, Cadworx 2D and Excel..
Compressor Upgrade Modification, Oxy, Elk Hills, Ca.
Revamp layout of 12 compressors and associated equipment. Increased
suction line from 16" to 20", new off skid suction drum, larger lube
system and cooler. Off plot piping tie ins, field survey utilizing
Trimble GPS. Development and production of contract deliverables,
such as Plot Plans, Piping Plans, Sections, Material Bills and Iso's,
utilizing Autocad 2008,Cadworx 2D and Excel.
. Fluor Corp., So.- Ca. Apr- 2006 - Feb. 2010
Marathon Oil, Delayed Coker Unit, Detroit, Mich.
Design Supervisor, utilizing autocad 2004, preformed layout of unit
plot plan, vessel orientations, pump systems, air coolers/ blowdown
system, exchanger areas and pipeway studies. Responsible for eight
designers PDS input, utilizing Smart Plant Review. Responsible for
client model reviews and client interface during design development.
Tesoro, Delayed Coker Unit, Martinez, Ca.
Lead Checker, Auditing of piping Isometricts utilizing Smart Plant
Review.
Tesoro, Delayed Coker Unit, Anacortes, Wa.,
Design Specialist, P&ID reviews and development, layout unit plot
plan, utilizing Autocad 2004.
. TJCross Engineering Co., Bakersfield, CA. Feb. 2006 - Apr. 2006
ChevronTexaco, Walnut Filter Expansion, Lost Hills, CA
Design Specialist, Revamp requiring addition of several skid mounted
walnut shell filters and layout of associated piping and tie ins.
Development and production of contract deliverables, such as Plot
Plans, Piping Plans, Sections, Material Bills and Iso's, utilizing
Autocad 2004 and Excel.
. Raymond Professional Group, Inc., Bakersfield, CA. Nov. 2005 -
Feb. 2006
U.S. Borax, Zinc-Borate Expansion, Wilmington Refinery,CA.
Design Specialist, layout of piping and equipment required for borax
expansion project, utilizing Autocad 2004.
. Fluor Corp., So.- Ca. 1974-2004
Hamaca Crude Upgrader Project, Jose, Venezuela
Design Specialist, layout and design of Amine and Sour Water Units.
Vessel orientations, pump systems, exchanger train and air coolers
using Autocad. Supervision of PDS input of off-shore office utilizing
Smart Plant Review.
Irving Oil Limited, Refinery Upgrade Project, St. John, New Brunswick,
Canada
Principal Designer, Design of blowdown system, vessel orientations.
Auditing of PDS input of off shore office using Smart Plant Review.
ARCO Products Company, Polypropylene OBL Project.
Principal Designer, Manual vessel orientations, exchanger train
layout. Auditing of Isometrics.
Unocal Geothermal, Salak, Indonesia
Design Supervisor, Routing of x-country steam gathering piping, well
pad layouts, brine separator orientations, acumlators and pump
systems. Responsible for 4 designers. Development of contract
deliverables, such as Piping Plans and Sects.,utilizing Autocad 13.
Chevron El Segundo New Generation Facility, Ca.
Principal Designer, responsible for all off plot piping tie ins.
Deliverables were manual Iso drawings.
Unocal Reformulated Fuels Program, Wilminton, Ca.
Senior Designer, Layout of regenerating reactors, exchanger system.
Providing manual sketches for cad input.
Unocal Fertilizer Plant Expansion, Sac., Ca.
Senior Designer, vessel orientations, pump systems. Complicated layout
of vessel containment area, requiring double containment with leak
detection instrumentation. Manual drafting for cad input.
ARDS Unit Fuel Upgrading Project, FINA Raffinadeij Antwerp, Belgium
Senior Designer, vessel orientations, high pressure coalessor filters.
Responsible for plastic model completion.