CURRICULUM VITAE
Proposed position : QA/QC ASST- Manager
Name of the firm : Larsen & Toubro Limited, ECC Division
Name : K. Vimalraj
Nationality : Indian
Date of Birth : 05.06.1982
Educational qualifications : 1.BE in Mechanical Engineering-April 2003
2. CSWIP-3.1 Welding Inspector
3. ISO 9001 Lead Auditor for L & T
4. ASNT LeveI-ll in, PT,UT, MT & RT
CODES AND STANDARDS
KNOWLEDGE : ASME SEC I, SEC VIII DIV-I,SEC IX & SEC V
ASME B 31.1,31.3,31.4 & 31.8
API 1104,API 5L
IS 3589,IS 4984
Total Work Experience : 11 Years
Contact : **************@*****.***, 900-***-****
Experience Profile
Project /Company Name : Larsen & Toubro, ECC Division
Position : QA/QC Asst-Manager
Period : September 2013 Onwards
Job Description : Responsibility
PROJECT HANDLED
Indian Oil Corporation Ltd, EPC Project for Oil Refinery Plant at Paradip,
1.
Orissa.
2. Mega lift Irrigation Project at Bolangir, Odissa.
To ensure that the processes needed for the
•
Quality management system are established,
implemented and maintained in all departments and
project sites.
Coordinate with Internal and External Audit for
•
Cluster and Site. Conduct Management Review
Meeting and Project Review Meeting Collecting report
send To HQ
Review of Non-conformances to carryout the
•
trend analysis. To provide adequate training to
personnel involved in performing the activities
assigned to them
Review of Contract Specific Procedures and
•
Quality Control plans prepared by the Project
Manager / Project Engineer.
Reporting on performance of Quality
•
Management system to Project Manager and
recommending suggestions for improvement.
Conducting Management Review meetings
•
periodically with all management staffs.
To approve the Sub-contractor’s Contract
•
Quality Plan and Quality Control Plan
To carry out Second Party audits on suppliers!
•
Subcontractors to meet Client/Code requirements
To analyze and report to the Top Management
•
on Performance of Processes, Product, Suppliers,
Internal Quality audit results, Customer complaints
and Customer Satisfaction.
Coordination with M/s DNV’s & Lloyds Register
•
Asia Lead Auditors for the ISO 9001 Re-certification
and Periodic Audits
• Conversant with various welding processes such as
SMAW, SAW, etc.
• Erection Carbon steel pipe and low alloy steel pipe from
OD 60mm to 450mm.
Fabrication and Erection MS Pipe from OD
•
500mm to 1700mm.
Vendor inspection of DI Pipe OD 250mm To
•
500mm, HDPE pipe OD 250mm To 450mm
Inspection for Raw materials Plates,MS
•
Pipes, HDPE Pipes, DI Pipes, valves, Pumps as
per codes &standards,Client Technical Specification
and PO, Test certificates,
Inspection for LS,CS Fit-up, Welding,NDT,
•
Hydro test, and dimensions checked as per
Inspection Test Plan, Quality assurance plan.
Inspection for Hydro testing of Pipeline as per
•
Client Specifications and as per codes & standards..
• Review of daily activities and planning for the work
accordingly.
• Preparation of Method Statement, Quality Control Plan
and Quality Control Procedures
• Updating the Welders Qualification at regular intervals.
Qualification of the welders and preparation of WQIR
• Request NDT required by code & piping specification
(RT,PT,MPT) up dating daily QC documentation.
• Witnessing of Hydro Test for MS, DI and HDPE Pipe line
• Maintain Controlled Documents(Drawing and Codes &
Standards), Technical Specification, Client Approved Procedure,
Approved Drawing, Site Documents & Records, Vendor
Evaluation & Procedure.
Finally Prepared Test Pack for each Project to
•
submit the Client.
Project/Company Name : BUREAU VERITAS INDIA (P) LTD, CHENNAI.
: Surveyor
Position
Period : Dec 2012 to July 2013
Job Description : Responsibility :
Working as a Third Party Inspector / Client
•
Inspector performing inspection & expediting services
for Oil & Gas / Power Plants construction/fabrication
• Inspection of Fabricated in Compliance with International
Standards for Steel, Cement, Sugar Plant, Power plant, Boilers
Pressure vessels, structural and Storage Tanks.
• Inspection of Boiler & Pressure vessels like Steam
Drum, Water wall panels, Super Heaters, Economizers, Air-
preheater, HP& LP Heater, Boiler Piping’s, etc as per Codes,
standards and QAP, Drawings
• Witnessing of Destructives Test, Bend Test, Toughness
Test and Hardness Test at Laboratories.
• Witnessing/Review and approval of various Non
destructive Examination such as Heat Treatment Chart(PWHT),
RT, UT, MT, and PT
• Review and Approval of QA Plans, Welding Procedures,
Welders Qualification Records, Heat Treatment Procedures, and
Hydro test Procedure.
• Familiar with various types of mechanical testing such as
tensile, bend, impact, hardness and positive material
identification
• Witnessing and Approval of WPS/PQR/WPQ
• Witnessing/Review of Final Dimension and Prepared
Inspection Report on Timely.
Project/Company Name : CETHAR LIMITED,TRICHY.
Position : Sr Engineer QC (FQA-SITE)
Period : July 2010 to Sep 2012
Job Description : Responsibility
PROJECT HANDLED
1). 2x350MW PC Boiler M/s Ind-Barath Energy (Utkal) Limited, Orissa (Boiler,External
Piping and ESP)
:
• Erection & Inspection for Static Equipment’s like
Economizer module, Evaporator module,
Dearator,Condenser,HP & LP Heaters, Steam Drum,De
super heater checking for alignment and Elevation
• Erection & Inspection for Rotating Equipment’s like
Turbine, Boiler Feed pump, PA,FD & ID Fans checking alignment
and Tail run
• Erection & Inspection for boiler Internal and External
Piping’s
• Piping materials checking as per standard and drawings
• The work involves structural Fabrication and Erection of
Non pressure parts of boiler component and supporting
structures like plus columns, box columns, Ducts and ESP
structures
• Witnessing welding procedure qualifications & Welder /
Welding operator Performance Qualification as per ASME
Section IX and AWS D1.1 requirements.
• Have through knowledge on GTAW, SMAW, GMAW, FCAW
and Stud arc welding
• Involved in various QC activities like raw material
inspection,Plate & Pipe cutting& Edge Preparation, Fit-up,
Welding, Pre Heating,Post Heating & PWHT, NDT Testing,
Hydro Testing and dimensional checkup's etc.
• Verify calibration status of Measuring & Monitoring
Devices used.
• Visual inspection of the weldments for dimensions, weld
geometry as per welding specification & welding standards
• Inspect &Witness all site Quality activities like Electrodes,
Fit up, Weld visual etc
• NDE Coordination, Interpretation of Radiographic films,
Witnessing Penetrant & Magnetic particle testing & offers the
same to client Evaluation of NDEs (PT, MT, UT, RT)
• Review NDT reports and Interpret Radiographic Films.
•
• Collect data to assess Welder performance/ Witness
Pressure gauge calibration and Monitoring Hydro test activity.
• Evaluation of Heat treatment process of Material and
weld joints (PWHT,SR)
• Incoming Material Inspection for Plate, Pipes,Tubes,
Fittings and valves, including Welding Consumables
• Preparation of test packages for Hydro Test and
Pneumatic Test
• Preparation of Final Dimension Report and Document
•
Project/Company Name :EMPEROR ENGINEERING WORKS(P)LTD,TRICHY
Position : Engineer QC-Mechanical
Period : Feb 2009 to Jun 2010
Job Description : Responsibility :
• The work involves fabrication and inspection of boiler
components and boiler supporting structures.
• Fabrication for Boiler Down comer Piping’s, Riser
Piping’s, Feed Piping’s and Super Heater Piping’s
• Inspect preheating,Inter pass temperature and post weld
heat treatment
• Request NDT required by code & piping specification
(RT,PT,MPT) up dating daily QC documentation.
• Incoming Material Inspection for Plate, Pipes,Tubes,
Fittings and valves, including Welding Consumables
• Incoming Material Inspection for Plate, Pipes,Tubes,
Fittings and valves, including Welding Consumables
• Preparation of Final Dimension Report and Document
Project/Company Name : Galfar Engineering & Contracting SAOG
(OMAN)
Position : QC/ Welding Inspector
Period : May 2008 to Jan 2009
Job Description : Responsibility :
• Review Purchase Orders assigned by the QA
Engineer
• Comply and implement Quality System Requirements
Preparation of Method Statement, Quality Control Plan and
Quality Control Procedures
• Material Handle for Carbon steel Pipes, Alloy Steel pipes, Stainless steel Pipes, and Duplex Stainless steel Pipes.
• Witnessing welding procedure qualifications & Welder /
Welding operator Performance Qualification as per ASME
Section IX and API 1104 requirements.
• Conduct visual inspection on pipe welding joints
• Conversant with various welding processes such as
GTAW, SMAW, SAW, FCAW, etc.
• Before, During & After Welding has to be inspected.
Electrode / Filler metal chosen as per WPS, Gas Flow, Pre heat
Temp., Interpass temp. & Post weld heat Treatment.
• Witnessing Non destructive testing (RT, UT, MT, PT ) wrt
applicable codes/standards, witnessing calibration of testing
instruments as per standard.
• Ensuring electrode baking, holding temperature for low
hydrogen electrodes, Review of test certificates for electrodes
and filler metals - conformance to ASME Section II Part C &
Clients Special Requirements while surveillance inspection
• Monitor subcontractors’ performance for compliance
with quality requirements.
• Piping/Pipeline checking and Pressure test witness
(Hydro test, kinematic test).
• Piping/Pipeline test package arrangement and checking
• Piping/Pipeline materials checking as per standard and
drawings.
• Incoming Material Inspection including Welding
Consumables
• Collect data to assess Welder performance/ Witness
Pressure gauge calibration and Monitoring Hydro test activity .
•
Project/Company Name : GB ENGINEERING ENTERPPRISES (P) LTD,TRICHY
Position : QC Engineer
Period : July 2006 to April 2008
Job Description : Responsibility :
Fully involved as nominated QA/QC task,
•
which controls Manufacturing process successfully
with reference to Drawings Quality Plans, Quality system
Procedures,Codes and Standards
Co-ordination with third party inspection
•
agencies (LLOYDS,TPL, BVIL, etc.,)
• Preparation of Inspection & Test Plan and Quality Control
Procedures in accordance with Client specifications and codes.
Inspection of weld Profile, Weld penetration,
•
Beads profile, Weld shape on Pressure vessels
parts like Economizer, water wall panels, Headers.
If it’s improper suggest Production people to
correct the weld profile as per WPS. The Major
Discontinues are to be avoided like Undercut,
Under fill, Surface porosity, Spatter, Face / root
reinforcement & Cracks.
• Have through knowledge on GTAW, SMAW, GMAW,
FCAW and Stud arc welding
• Issue of heat treatment cycle and review of heat
treatment charts for code compliance. Witnessing the Pre heat,
Post welding and Post weld Heat Treatment . Calculate the
Soaking Temperature and Time,Reviewing PWHT charts and
results
• Review of completion of all activities as per checklist and
issue product release note.
• Familiar with various types of mechanical testing such as
tensile, bend, impact, hardness and positive material
identification
• Inspection of High Pressure Boiler Pressure parts such
as Boiler Drums, Headers, Piping, etc, from raw material to
finished products.
• Verification of Mill certificates and Test certificates to code
compliance.
• Preparation of History cards and test reports.
• Witnessing of Mechanical testing and Hydro testing
• Witnessing of Welder’s qualification and preparation of
reports.
• Conversant with various heat treatment procedures
applicable to high-pressure boiler parts
• Welding booklets WPS, PQR, WPQR and Applicable
WPS verification with reference to ASME SEC IX, IBR format.
• Stage inspection viz.,
• Dimensional Inspection
• In process control document preparation like.
• Layout report
• First of trial
• Fit up report
• Visual inspection
• Final dimension inspection.
• Heat treatment.
• Hydro Test
o Final Inspection.
o Stage by stage document preparation like
.
Project /Company Name : PARAGON INDUSTRIES, TRICHY
Position : Engineer-QA/QC(Mechanical)
Period : Jan 2004 to July 2006
Job Description ; Responsibility :
The work involves structural fabrication of
•
boiler supporting structures like plus columns and
box columns
Fabrication of Air Pre-heater, different types
•
of ducts and silencer assembly
Fit up and dimension Inspection for steel
•
structures as per ITP, approved drawings and
specifications.
• Verification of Mill certificates and Test certificates to code
compliance.
• Preparation of History cards and test reports.
• Witnessing of Mechanical testing and Hydro testing
• Conversant with various welding processes such as
GTAW, SMAW, SAW, FCAW, ESW, etc.
• Witnessing of Welder’s qualification and preparation of
reports.
Follow the work status and ensure the
•
customer requirements and standards and give the
drawing clarification when required
Declaration
I here by declare that the all above furnished information are true,
Complete and correct to the best of my knowledge.
(Vimal Raj. k)