John S. Sullivan
**** **** ***** ***** •Wasilla, AK 99623 *******@*******.*** • 907-***-**** c
CONSTRUCTION PROJECT MANAGEMENT
Safety-focused, results-driven professional with 20+ years of experience directing all phases of domestic and
international construction projects from initial concept and design through final delivery. Motivational leader with
a well-balanced management style, the highest standards of personal and professional integrity, and proven
expertise in training, coaching, mentoring, and supervising foremen, engineers, and crewmembers.
Solid history of success in completing all projects on time or ahead of schedule while meeting or exceeding
client needs and budget requirements. Consistent track record of providing superior leadership in difficult
working conditions, extreme climates, and dangerous global environments.
Areas of Expertise:
• Full Lifecycle Project Budget Development and Administration
Quality Control (QC) Supervision
Management
Safety and Security Oversight
• Estimating and Job
Team Building and Leadership
Cost Analysis
Client and Customer Relationships
• Design and Engineering
Leadership
• Project Planning and
Scheduling
• Statement of Work
(SOW) Preparation
PROFESSIONAL EXPERIENCE:
PRESENT : Project PM/Supt with Watermark Construction on the Koyukuk Health
Clinic
Previous to January 2014
NANACONSTRUCTION,LLC-PRUDHOE BAY, ALASKA 2013
PROJECT MANAGER,NORTH SLOPE OPERATIONS.URS/FLINT TARMAC OFFICE
COMPLEX INSTALLATION.CGFGAS RING REPLACEMENT.EAST CHECKPOINT REPLACEMENT
CONTRACT CHANGE ORDERS,RFI,PO,FIELD MATERIAL REQUESTS,LAYOUT AND DESIGN, CREW ASSIGNMENTS,BILLETING,SET
UP OF WHITE BOARD SAFETY MEETINGS,ATP,JHA,TASK ASSIGNMENTS.SCHEDULING WITH MSPROJECT.PRODUCT
PROCUREMENT, LOGISTICS,SHIPPING AND RECEIVING VERIFICATIONS.
PREVIOUS EXPERIENCE:
VALHALLA MANAGEMENT SERVICES (SCCI-JPGC) – Kandahar, Afghanistan 2012
Project Management Consulting.
Recruited to manage and turn around operations and projects suffering from previous leadership problems.
Selected Contributions:
Successfully renegotiated amended contract to complete work while overcoming existing contract
compliance issues, past due billing, and unpaid invoices.
Received letter of recommendation from CEO of SCCI-JPGC for unique level of experience and
success in overseeing all phases of on-time, on-budget construction projects.
…continued…
JOHN S.SULLIVAN 2
Page
ALASKA NATIVE TRIBAL HEALTH CONSORTIUM – Kiana, AK 2011
Site Supervisor
Oversaw project encompassing HDPE piping installation for water and sewer lines. Offered support to village’s
tribal council and designed road system through tundra sub-division progressing down to Kobuk River.
Performed all design calculations and engineering layouts. Provided river access by supervising and assisting in
1.5 miles of clearing, grubbing, layout, and earthwork. Led installation of six culverts and five manholes as well
as rehabilitation of pumps and lift stations.
Selected Contributions:
Delivered projects on time and within budget while meeting and exceeding client objectives.
Ensured completion of work in difficult conditions, including temperatures as low as -35 degrees.
ALMCO – Rumalya Province, Iraq, 2011
Project Manager(Ex-Pat), Schlumberger Project Selected
Contributions:
Continually maintained project on schedule by instituting nighttime crane and dozer operation and
redesigning foundations and concrete form systems.
Ensured completion of Statement of Work (SOW ) while achieving both company and client goals.
BYA – Gardez, Camp Thunder, and Gamberi, Afghanistan 2010
Construction Manager
Provided construction and project management, site engineering, and Quality Control (QC) for Iraqi company
completing work in Gardez, Camp Thunder, and Gamberi, Iraq.
Anchorage and Fairbanks, AK
Construction Manager / Site Superintendent 2009
Oversaw and participated in construction management and engineering for U.S. Army Corps of Engineers
(USACE) and Air Force Center for Engineering and the Environment (AFCEE) projects.
APPLIED PLANNING – Helmand Province, Afghanistan
Consulting Estimator 2/2009
Assessed Statement of Work (SOW) as sole estimator on three- Hydro turbine Kajaki Hydro Dam project. Set up
risk management and security forces for prime contractor (Black and Veatch).
Al Hameia, Rawa, and West Al Anbar Province, Iraq
Project Manager / Construction Manager 6/2006 to 1/2009
Served as Project Manager and Site Engineer for Iraqi Army FMS Standards project. Constructed base for light
infantry battalion. Functioned as Project Manager and Engineer on AFCEE project at Iraqi Army Base.
Continually trained and supported Project Managers, Superintendents, and Construction Managers.
Selected Contributions:
Expertly managed all phases, from groundbreaking to turnkey,on$40+ million Al Hameia project.
Delivered all projects ahead of schedule and under budgetwhile ensuring client satisfaction.
AREA 4 Baghdad, Iraq
Site Superintendent 2005 / 2006
JOHN S.SULLIVAN 3
…continued…
Page
Directed field operations for Iraqi contractor’s construction of building, barracks, auditorium, gymnasium, two
dining facilities, administrative offices, and infrastructure (water, sewer, electric, roads). Acted as Consulting
Design Engineer on DBE project in Basra to include setup of design engineering office, design equipment
procurement, hiring of staff engineers and CAD operators, and design team management.
NANAPACIFIC – Umm Qasr, Iraq
Project Manager 2004/ 2005
Led rehabilitation of high voltage system supplying power to North Port Dock utility including all Nelcon cranes,
lighting, power substations, and tie-in to Iraqi Grid.
OCEANIC COMPANY,INC. – Sealife Park, Hi
Project Manager 2003/ to (3/2004
Directed rehabilitation of Kimuki substation, Oceanic Institute wire boxes at Sealife Park.
LOCHER,LLC. – Anchorage, AK
Value Engineering Team Member 2002
Collaborated with other team members in completing all estimating work for $39-million Eagle River High School
project and $10-million Polar K-12 Phase One project for Anchorage School District.
VILLAGE SAFE WATER – Emmonak, AK
Site Supervisor 2001
Led installation of vacuum sewer and pressurized water system. Prepared estimates, compiled material takeoffs,
and coordinated arrangements for tools and shipping.
** *** **
Prior experience as General Superintendent (2000) with VECO Construction, Anchorage, AK, Project
Manager / Field Projects Superintendent (1999) with Valhalla Management Services, Notawa, MI, Structural
Superintendent (1997 and 1998) with Alaska Petroleum Contractors, Nikiski, AK, Superintendent (1996) with
VECO Construction, Anchorage, AK, Construction Manager (1994 and 1995) with Kikiktagruk Inupiat
Corporation, Kotzebue, AK, and Project Manager / Superintendent (1992 / 1991 / 1990) with Kapaau
Development, Big Island of Hawaii.
SELECTED LIST OF PREVIOUS PROJECTS
Project Superintendent, $2.2-million remodeling of Alakanuk High School, Alakanuk, AK (NANA Construction)
General Foreman, installation of 135 -- modular housing units (Wick Construction, Kirkland, WA)
Project Superintendent, $26-million Tuntituliak High School project (Alaska Diversified / Fischbach Moore)
Project Manager, residential and commercial facilities (Guinn Lumber and Construction, Bethel, AK)
Project Manager / Superintendent, multiple commercial projects (Tikigaq Construction, Point Hope, AK)
Quality Control Engineer, $22-million Skyview High School project, $19-million Nikiski High School project,
and $7-million North Star Elementary School project (Morrison-Knudsen, Soldotna, AK)
JOHN S.SULLIVAN 4
TRAINING AND CREDENTIALS
Page
Licensure / Certification
BSCE/ ASCET
Journeyman Status in Structural, Industrial, Civil, and Architectural Construction
Pilot Certificate for Single Engine Land and Sea
OSHA 30-Hour Construction Course Certificate
USACE Construction Management Certification
USMC Combat Veteran / Airborne Qualified
Technical Proficiencies
Microsoft Project, Primavera, Acad, Great Plains, Photo Suite, Microsoft Office (Excel, Word, PowerPoint)